Production of one of the F-35′s most anticipated bombs has been on hold for almost a year

By:

WASHINGTON — Deliveries of a new precision-guided bomb under development by Raytheon for the F-35 and other fighter jets have been at a standstill for about a year as the company struggles to correct a technical problem involving a key component.

A fix for the issue, which brought production of the Small Diameter Bomb II to a halt in July 2019, could be approved by the government as soon as July, said Air Force spokesman Capt. Jake Bailey in response to questions by Defense News.

However, a June report by the Government Accountability Office pointed out that continued technical issues have already caused a delay in fielding the munition, with Raytheon forced to redesign a key component and retrofit all 598 bombs already delivered to the Air Force and Navy.

The Small Diameter Bomb II — also known as the GBU-53 StormBreaker — was designed with a tri-mode seeker that includes a millimeter wave radar, imaging infrared and semi-active laser that allow the weapon to engage targets in all weather conditions and environments where visibility is obscured by dust and debris.

The Air Force and Navy plan to integrate SDB II with a range of fighter aircraft including the F-15, F/A-18 Super Hornet and F-35 joint strike fighter, but the munition has been mired in development for more than a decade.

This latest stoppage in production was prompted by internal audits by Raytheon, which found that the clips used to hold the bomb's fins in place “suffered vibration fatigue over long flight hours,” Bailey said. The clips serve “as the backup fin storage device” used to keep the fins in place in case other components fail, noted Bailey, who added that there have been no incidents during tests involving the SDB II fins inadvertently deploying.

However, the GAO wrote that the premature deployment of the fins, which help guide the bomb in flight, could damage the weapon as well as cause a safety hazard for the aircraft carrying it.

“While this problem could affect all aircraft carrying the bomb, officials said the greatest impact is to the F-35, because the bomb is carried in the aircraft's internal weapons bay and could cause serious damage if the fins deploy while the bomb is in the bay,” the GAO stated.

Raytheon declined to comment on this story, directing questions to the Air Force.

Raytheon plans on mitigating the issue with a newly designed clip that reduces the vibration of the fins, and will completely pay for developing the fix and retrofitting it on the bombs that have already been delivered, the GAO said. The Air Force confirmed that testing of the new device has already been completed and is going through final reviews.

But while Raytheon and the Air Force had hoped to restart production in April, travel restrictions caused by the ongoing global COVID-19 pandemic contributed to further delays. The government now hopes to approve the fix in July, after which production will restart and the retrofit process for existing bombs will begin.

“The fin clip failure is the sole reason production was partially halted; once final government approval is obtained, ‘all up round' production can resume,” Bailey said, using a phrase that describes a fully assembled weapon. The Air Force estimates that retrofits will be completed by August, as Raytheon's supplier has already begun manufacturing the replacement component, which are easily installed on the outside of the weapon.

“Until production resumes, the total Lot 3 deliveries remain at 204 of the 312 assets on contract,” Bailey said.

All this puts initial operational capability at least a year later than the service's original timeline, which predicted IOC would occur in September 2019. The Air Force declined to name a current estimate for when IOC would be achieved, but said it would happen after a separate milestone known as the “initial fielding decision,” which involves the approval of the head of Air Combat Command and is set for the third quarter of 2020.

The issue with SDB II's fins is just one of several technical problems with which Raytheon is grappling. The program completed operational tests in 2019, but hardware and software changes are needed after 11 failures were reported. Two hardware fixes have already been put in place, and eight failures were related to software problems that will be addressed in future updates, the GAO said.

The sole outstanding issue involves an anomaly with SDB II's guidance system. Fixing it could require Raytheon to redesign the component and conduct retrofits on all bombs already delivered, according to GAO.

A review board of the problem is in the “final stages of analysis,” Bailey said. The Air Force and Raytheon plan to establish whether a replacement component is necessary no later than June 30.

Although the weapon has not even been officially fielded, some components are already becoming obsolete. A Raytheon subcontractor that makes circuit cards used in the guidance system is expected to stop producing those components years sooner than anticipated.

As a result, that the Defense Department may have to order all circuit cards needed for the program of record before December, according to the GAO.

That timeline has now been extended to January 2022, “which provides ample time for program office action before the new deadline,” Bailey said.

Despite the bomb's ongoing problems, Raytheon continues to rake in contracts for the program. In February, the Defense Department awarded a $15 million increase to a previous SDB II contract for additional technical support. In September, the company received a $200 million contract for lifecycle support during the bomb's engineering and manufacturing development phase.

According to a Raytheon news release, the Navy recently completed the first guided release of SDB II from a F/A-18E/F Super Hornet.

https://www.defensenews.com/air/2020/06/12/production-of-one-of-the-f-35s-most-anticipated-bombs-has-been-on-hold-for-almost-a-year

Sur le même sujet

  • Strict export regulations may be costing US industry billions in foreign sales

    19 juin 2018 | International, C4ISR

    Strict export regulations may be costing US industry billions in foreign sales

    WASHINGTON ― A new RAND report assessing the proliferation of unmanned aerial vehicles suggests existing export controls for drones may hurt the U.S. more than it helps. Limiting U.S. drone exports has left a hole in the global market for the technology, especially in historically U.S.-dominated Middle East markets, which has been readily filled by U.S. competitors — specifically China and Russia. The Trump administration recently unveiled a new set of export policies regarding military technology in an attempt to facilitate the transfer of military technology, but the changes do not change the status of drones under the Missile Technology Control Regime, or MTCR. How does the MTCR work? The MTCR is a voluntary export control consortium of 35 nations designed to prevent signatories from proliferating longer-range cruise and ballistic missile technology. The arms control regime was extended to UAVs because early iterations of drones were considered a subset of cruise missile technology due to their active guidance system. The regime divides missiles into two categories. Category I items are capable of delivering a 500 kg payload more than 300 km. The sale of category I systems is restricted by a “strong presumption of denial,” meaning they are only exported in rare circumstances. The MQ-9 Reaper, RQ-4 Global Hawk and MQ-4 Triton are well-known unmanned systems that fall under this category. Over the past several years, U.S. partners such as Jordan, Saudi Arabia and UAE were denied requests to purchase American drones, and have since turned to China to purchase comparable systems. Trump administration officials have been attempting to alter the regime by adding new languagethat would drop any vehicle that flies under 650 kilometers per hour to category II systems. This would make all but the most advanced U.S. systems available for international sale. For example, the MQ-9 Reaper clocks in with a cruise speed of 230 mph or 370 kph, according to an Air Force facts sheet. Drone proliferation RAND found that 10 nations operate category I drones, and more than 15 operate near-category I systems that register just below the MTCR's payload and distance restrictions. The report says increased proliferation rates are due to a handful of countries, specifically China, Israel and the United Arab Emirates, who are not party to the MCTR. More countries are expected to procure drones, which pose a “growing threat to U.S. and allied military operations,” the report says. While category I systems can deploy missiles and other guided munitions, their main threat lies in “their ability to conduct intelligence, surveillance, and reconnaissance (ISR) operations against U.S. forces prior to hostilities,” according to RAND. “Adversaries that would otherwise have difficulty detecting U.S. force deployments, monitoring U.S. operations, and maintaining targeting data on U.S. units can employ UAVs to maintain situational awareness of U.S. capabilities” The report identifies Russia, China and Iran as unfriendly nations that will seek to utilize drones to complicate U.S. military operations. For example, China and Saudi Arabia recently agreed to set up a UAV manufacturing plant in Saudi Arabia for up to 300 new UAVs, and Italy will receive 20 Hammerhead UAVs from the UAE. The coproduction of regional drone factories “could further exacerbate the proliferation of large UAVs to the degree that these systems are exported to other nations,” according to RAND, and that hurts U.S. industry. A U.S.-sized hole Voluntarily restricting U.S. drone exports have allowed competitors to establish themselves in a market Rand expects to “grow from about $6 billion in 2015 to about $12 billion in 2025.” RAND expect export controls to have a negative impact on the U.S. industrial base, something those in industry already know. “What you are enabling the competition to do is not just to sell some hardware,” Linden Blue, General Atomic's chief executive, told reporters during an Aug. 16, 2017 roundtable at the company's headquarters in Poway, California. “You're enabling it to build a customer base for at least 20 years, I would say. You're enabling them to build a logistics system. It will take them many years to get to where we are right now, but you're helping them start out. They should be very thankful.” https://www.defensenews.com/newsletters/unmanned-systems/2018/06/18/strict-export-regulations-may-be-costing-us-industry-billions-in-foreign-sales/

  • Intel Agency Studies MQ-25 For Surveillance Role

    3 octobre 2019 | International, Aérospatial, Naval

    Intel Agency Studies MQ-25 For Surveillance Role

    Steve Trimble The U.S. Navy's MQ-25 is being developed as a carrier-based aerial refueler, but an intelligence agency is showing interest in the unmanned aircraft system for a maritime surveillance role. The National Geospatial-Intelligence Agency (NGA) has commissioned Boeing to study the integration requirements for installing the company's Multi-Mission Pod (MMP) on the MQ-25. Boeing developed the MMP using internal funding for the P-8A, a submarine hunter derived from the 737NG. It is designed to carry multiple payloads, including communication and electronic intelligence receivers. The NGA-sponsored study will evaluate how to use the MMP to introduce the agency's “maritime program” on the P-8A and MQ-25 fleets. The agency on Sept. 30 published a “justification and approval” notice for the study contract awarded to Boeing in May. Such notices are required to justify any contract awarded to a single contractor without a competition. In this case, the sole source award was justified because the MQ-25 is still early in the development phase, the NGA says, so Boeing is the only company that has access to the design data. The Navy awarded Boeing an $805 million in August 2018 to deliver four MQ-25 aircraft during the engineering and manufacturing development phase. The overall value of the deal has since risen to $944 million, of which $436 million, or 46.1%, has been obligated, according to the USASpending.gov procurement tracking site. Last month, Boeing completed the first flight of a company-funded test asset for the MQ-25 program at an airport in Illinois. The study also suggests the P-8A and MQ-25 fleet could be used to help replace the electronic intelligence capability once performed by the Lockheed EP-3E fleet. The Navy has said that the EP-3E will be replaced by a family of manned and unmanned aircraft, including the P-8A and the MQ-4C unmanned aircraft system. https://aviationweek.com/defense/intel-agency-studies-mq-25-surveillance-role

  • Hawaii to receive $2.6B to improve Army facilities across state

    4 mai 2018 | International, Terrestre

    Hawaii to receive $2.6B to improve Army facilities across state

    Anna Hrushka Army installations across Hawaii will receive $2.6 billion in funding over a 32-year period to build and upgrade facilities, as part of he Army's Hawaii Infrastructure Readiness Initiative. According to a statement released by U.S. Sen. Brian Schatz, D-Hawaii, a member of the Senate Appropriations Committee, the Army will begin with an initial five-year investment of $350 million in military construction “to improve the shortfall of aviation facilities at Wheeler Army Air Field that are necessary to support a number of new aircraft the Army has brought to Hawaii in recent years, including AH-64 Apaches with the 25th Combat Aviation Brigade.” The initial funding will also be used to improve operations facilities at Schofield Barracks. “This long-term plan to upgrade and build new facilities represents the Army's commitment to Hawaii and our key role in the region,” Schatz said in a statement. “The planned funding is critical to Hawaii, to the Army's success, and to our national security. Fulfilling this plan will require timely and predictable funding, and the Department of Defense has my commitment to provide just that as we get back to the regular business of passing appropriations bills on time.” https://www.bizjournals.com/pacific/news/2018/05/02/hawaii-to-receive-2-6b-to-improve-army-facilities.html

Toutes les nouvelles