Production of one of the F-35′s most anticipated bombs has been on hold for almost a year

By:

WASHINGTON — Deliveries of a new precision-guided bomb under development by Raytheon for the F-35 and other fighter jets have been at a standstill for about a year as the company struggles to correct a technical problem involving a key component.

A fix for the issue, which brought production of the Small Diameter Bomb II to a halt in July 2019, could be approved by the government as soon as July, said Air Force spokesman Capt. Jake Bailey in response to questions by Defense News.

However, a June report by the Government Accountability Office pointed out that continued technical issues have already caused a delay in fielding the munition, with Raytheon forced to redesign a key component and retrofit all 598 bombs already delivered to the Air Force and Navy.

The Small Diameter Bomb II — also known as the GBU-53 StormBreaker — was designed with a tri-mode seeker that includes a millimeter wave radar, imaging infrared and semi-active laser that allow the weapon to engage targets in all weather conditions and environments where visibility is obscured by dust and debris.

The Air Force and Navy plan to integrate SDB II with a range of fighter aircraft including the F-15, F/A-18 Super Hornet and F-35 joint strike fighter, but the munition has been mired in development for more than a decade.

This latest stoppage in production was prompted by internal audits by Raytheon, which found that the clips used to hold the bomb's fins in place “suffered vibration fatigue over long flight hours,” Bailey said. The clips serve “as the backup fin storage device” used to keep the fins in place in case other components fail, noted Bailey, who added that there have been no incidents during tests involving the SDB II fins inadvertently deploying.

However, the GAO wrote that the premature deployment of the fins, which help guide the bomb in flight, could damage the weapon as well as cause a safety hazard for the aircraft carrying it.

“While this problem could affect all aircraft carrying the bomb, officials said the greatest impact is to the F-35, because the bomb is carried in the aircraft's internal weapons bay and could cause serious damage if the fins deploy while the bomb is in the bay,” the GAO stated.

Raytheon declined to comment on this story, directing questions to the Air Force.

Raytheon plans on mitigating the issue with a newly designed clip that reduces the vibration of the fins, and will completely pay for developing the fix and retrofitting it on the bombs that have already been delivered, the GAO said. The Air Force confirmed that testing of the new device has already been completed and is going through final reviews.

But while Raytheon and the Air Force had hoped to restart production in April, travel restrictions caused by the ongoing global COVID-19 pandemic contributed to further delays. The government now hopes to approve the fix in July, after which production will restart and the retrofit process for existing bombs will begin.

“The fin clip failure is the sole reason production was partially halted; once final government approval is obtained, ‘all up round' production can resume,” Bailey said, using a phrase that describes a fully assembled weapon. The Air Force estimates that retrofits will be completed by August, as Raytheon's supplier has already begun manufacturing the replacement component, which are easily installed on the outside of the weapon.

“Until production resumes, the total Lot 3 deliveries remain at 204 of the 312 assets on contract,” Bailey said.

All this puts initial operational capability at least a year later than the service's original timeline, which predicted IOC would occur in September 2019. The Air Force declined to name a current estimate for when IOC would be achieved, but said it would happen after a separate milestone known as the “initial fielding decision,” which involves the approval of the head of Air Combat Command and is set for the third quarter of 2020.

The issue with SDB II's fins is just one of several technical problems with which Raytheon is grappling. The program completed operational tests in 2019, but hardware and software changes are needed after 11 failures were reported. Two hardware fixes have already been put in place, and eight failures were related to software problems that will be addressed in future updates, the GAO said.

The sole outstanding issue involves an anomaly with SDB II's guidance system. Fixing it could require Raytheon to redesign the component and conduct retrofits on all bombs already delivered, according to GAO.

A review board of the problem is in the “final stages of analysis,” Bailey said. The Air Force and Raytheon plan to establish whether a replacement component is necessary no later than June 30.

Although the weapon has not even been officially fielded, some components are already becoming obsolete. A Raytheon subcontractor that makes circuit cards used in the guidance system is expected to stop producing those components years sooner than anticipated.

As a result, that the Defense Department may have to order all circuit cards needed for the program of record before December, according to the GAO.

That timeline has now been extended to January 2022, “which provides ample time for program office action before the new deadline,” Bailey said.

Despite the bomb's ongoing problems, Raytheon continues to rake in contracts for the program. In February, the Defense Department awarded a $15 million increase to a previous SDB II contract for additional technical support. In September, the company received a $200 million contract for lifecycle support during the bomb's engineering and manufacturing development phase.

According to a Raytheon news release, the Navy recently completed the first guided release of SDB II from a F/A-18E/F Super Hornet.

https://www.defensenews.com/air/2020/06/12/production-of-one-of-the-f-35s-most-anticipated-bombs-has-been-on-hold-for-almost-a-year

On the same subject

  • Finland issues revised request for tenders for HX programme

    November 5, 2019 | International, Aerospace

    Finland issues revised request for tenders for HX programme

    The Finnish Ministry of Defence (MoD) has issued a revised call for tenders to five companies for the country's programme to replace its ageing fighter aircraft fleet. The MoD has issued a Revised Request for Quotation and the five companies have time to respond until 31 January 2020. The programme for the replacement of the Finnish Air Force's Boeing F-18 Hornet fighter jets is called HX. Contenders to replace the aircraft include Lockheed Martin F-35, Boeing F/A-18 Super Hornet, Eurofighter Typhoon, Dassault Rafale and Saab Gripen. The HX programme is crucial for Finland's defence capability as the current fighters will reach the end of their service life by 2030. The Finnish Government has capped the budget for the acquisition of the new aircraft at €10bn. In a statement, the MoD said: “Within the budget set for the project, the tenderers must prepare a performance package that meets the set requirements and includes not only the aircraft but also other technical systems, training systems, necessary maintenance equipment, test equipment and spare parts, along with weapons, sensors and other required type-specific support functions. “The package must also include the changes in management and information systems required for its integration into the defence system, as well as the construction of security-critical infrastructure.” Tendering phase for the HX programme started last year when the MoD issued an initial invitation to negotiate and a request for quotations. The government then started the first phase of the programme negotiations. The revised call for tenders provides contenders with an opportunity to gather the information and present a ‘clear, updated and improved package'. Following the second phase of negotiations, the MoD will release the request for the final offer next year. A final decision on the procurement of the replacement fighters is expected in 2021. https://www.airforce-technology.com/news/finland-revised-request-tenders-hx-fighter-programme/

  • US Air Force says it’s on verge of rapid electronic warfare updates

    June 6, 2024 | International, Aerospace

    US Air Force says it’s on verge of rapid electronic warfare updates

    Col. Josh Koslov, commander of the 350th Spectrum Warfare Wing, once called a three-hour EW update a "moonshot," but said it's now within reach.

  • Lockheed Martin receives $2.3B deal for helicopter parts maintenance

    February 3, 2020 | International, Aerospace

    Lockheed Martin receives $2.3B deal for helicopter parts maintenance

    ByChristen McCurdy Jan. 31 (UPI) -- Lockheed Martin has received a $2.3 billion contract for parts maintenance for MH-60R and MH-60S helicopters for the U.S. Navy, the Department of Defense announced. The MH-60R -- also called the 'Romeo' aircraft -- has been operational since 2006. The helicopters are jointly built by Lockheed and Sikorsky Aircraft Corp. According to Lockheed, MH-60R replaces the SH-60B Bravo and SH-60F Foxtrot, and is equipped for combat duty as well as high-risk rescues. Itcan fly at speeds of up to 180 knots while carrying extra fuel tanks or torpedoes and Hellfire missiles. The MH-60S, also called the Knighthawk, replaced the CH-46 Sea Knight helicopters in 2001 and is used seek out and destroy naval mines from the air. Both models have a digital cockpit with four flat-panel color display screens that provide the crew access to advanced surveillance and information on weather conditions. The contract funds approximately 1,049 weapon replaceable assemblies and shop replaceable assemblies associated with both helicopter models. Forty-eight percent of work on the contract will be performed at various contractor supplier locations throughout the U.S., with 38 percent of work taking place in Stratford, Conn., and Owego, N.Y. Work should be completed by January 2025, but the contract does include an option that would extend the work through January 2027. https://www.upi.com/Defense-News/2020/01/31/Lockheed-Martin-receives-23B-deal-for-helicopter-parts-maintenance/3901580519254/

All news