$1 billion and counting: Inside Canada's troubled efforts to build new warships

Federal government tables figures showing what it's spent on the projects to date
Murray Brewster

The federal government has spent slightly more than $1.01 billion over the last seven years on design and preparatory contracts for the navy's new frigates and supply ships — and the projects still haven't bought anything that floats.

The figures, tabled recently in Parliament, represent the first comprehensive snapshot of what has been spent thus far on the frequently-delayed project to build replacement warships.

It's an enormous amount of money for two programs that have been operating for more than a decade with little to show for their efforts to date.

It will be years before the Canadian Surface Combatant project — which aims to replace the navy's frontline frigates with 15 state-of-the-art vessels — and the Joint Support Ship program for two replenishment vessels actually deliver warships.

The numbers and details for each advance contract were produced in the House of Commons in response to written questions from the Conservative opposition.

The money was divided almost evenly between the federal government's two go-to shipyards: Irving Shipbuilding in Halifax, the prime contractor for the new frigates, and Seaspan of Vancouver, the builder of the supply ships.

The breakdown raises critical questions about at least one of the programs, said a defence analyst, but it also shines a light on promises made by both Liberal and Conservative governments to keep spending under control for both of these projects — which could end up costing more than $64 billion.

"I think there should be a level of concern [among the public] about whether or not what's being delivered in practice is what was advertised at the outset," said Dave Perry, a procurement expert and vice president of the Canadian Global Affairs Institute.

A design still in flux

Most of his concerns revolve around the new support ships, which the Liberal government says are in the process of being built now.

The written responses, tabled in Parliament, note that the projected cost for the two supply ships — $3.4 billion — remains under review "as the design effort finalizes."

Perry said he was astonished to learn that, "seven years and half-a-billion dollars into design work on an off-the-shelf design," the navy doesn't have the support ships, even though "the middle third of the ship is built" — and officials now say "the design effort isn't finished."

Usually, he said, ships are designed before they're built.

The head of the Department of National Defence's materiel branch said most of the preparatory contracts were needed to re-establish a Canadian shipbuilding industry that had been allowed to wither.

'A lot of patience'

"I think we have to look at the totality of everything that's being accomplished under" the national shipbuilding strategy, said Troy Crosby, assistant deputy minister of materiel at DND.

"Over that period of time, and with these expenditures, we've built a shipbuilding capability on two coasts, not just through National Defence but also through the coast guard, offshore fisheries science vessels. I understand it has taken a lot of patience, I suppose, and probably some uncertainty, but we're really getting to the point now where we can see delivering these capabilities to the navy."

The largest cash outlays involve what's known as definition contracts, which went individually to both shipyards and were in excess of $330 million each. They're meant to cover the supervision of the projects and — more importantly — to help convert pre-existing warship designs purchased by the federal government to Canadian standards.

The choices on each project were made at different times by different governments, but ministers serving both Liberal and Conservative governments decided that going with proven, off-the-shelf designs would be faster and less expensive than building from scratch.

Now, after all the delays, it's still not clear that choosing off-the-shelf designs has saved any money.

"I would be completely speculating on what it would cost to invest to develop the kind of expertise and capacity inside the government, inside National Defence and everybody involved, to be able to do something like that in-house," said Crosby.

"The approach we've taken at this point, by basing both the Joint Support Ship and the Canadian Surface Combatant on pre-existing designs, allows us to retire a lot of risk in the way forward."

When Crosby talks about "retiring risk," he's talking about the potential for further delays and cost overruns.

Among the contracts, Irving Shipbuilding was given $136 million to support the drawing up of the design tender for the new frigates and to pay for the shipbuilding advice Irving was giving the federal government throughout the bidding process.

Years ago, the federal government had enough in-house expertise to dispense with private sector guidance — but almost all of that expertise was lost over the past two decades as successive federal governments cut the defence and public works branches that would have done that work.

The last time Canada built major warships was in the 1990s, when the current fleet of 12 patrol frigates was inaugurated.

The federal government has chosen to base its new warships on the BAE Systems Type-26 design, which has been selected by the Royal Navy and the Royal Australian Navy.

The hull and propulsion system on the new frigates will be "largely unchanged" from the British design, but the combat system will be different and uniquely Canadian, said Crosby.

The project is still on track to start cutting steel for the new combat ships in 2023. Crosby said he would not speculate on when the navy will take delivery of the first one.

Delivery of the joint support ships is expected to be staggered, with the first one due in 2024.

There will be a two-year gap between ships, said Crosby, as the navy and the yard work through any technical issues arising with the first ship.

If that timeline holds, the first support ship will arrive two decades after it was first proposed and announced by the Liberal government of former prime minister Paul Martin.

https://www.cbc.ca/news/politics/frigates-joint-supply-ships-navy-procurement-canada-1.5474312

On the same subject

  • BELL TEAMS WITH INDUSTRY LEADERS FOR U.S. ARMY FUTURE ATTACK RECONNAISSANCE AIRCRAFT PROGRAM

    June 5, 2020 | Local, Aerospace

    BELL TEAMS WITH INDUSTRY LEADERS FOR U.S. ARMY FUTURE ATTACK RECONNAISSANCE AIRCRAFT PROGRAM

    Team Invictus brings together programmatic and operational expertise to deliver a transformational, affordable scout aircraft to soldiers, the Bell 360 Invictus Fort Worth, Texas (June 4, 2020) – Bell Textron Inc., a Textron Inc. (NYSE: TXT) company, has announced agreements with nine premier aerospace industry leaders to form Team Invictus. The companies are producing the Bell 360 Invictus prototype submission as part of the U.S. Army's Future Attack Reconnaissance Aircraft (FARA) program. Each industry partner brings unique experience and technological expertise to provide a low-risk path for the Army's acquisition of a lethal, affordable rotorcraft with advanced mission systems to modernize aviation for multi-domain operations (MDO). “Team Invictus is working together to show how cutting-edge technology will give soldiers the ability to confidently operate in the complex and contested battlespace of multi-domain operations,” said Chris Gehler, vice president and program director for FARA at Bell. “Future Vertical Lift is critical for the Army's ability to win in multi-domain operations with FARA defeating defensive layers and the Future Long-Range Assault Aircraft (FLRAA) exploiting opened areas to achieve operational objectives.” Team members are working closely together to deliver the Bell 360 Invictus prototype using a configuration that emphasizes operational availability, sustainability, and maintainability. The members of Team Invictus include: Astronics Corporation for a modular framework of airframe power generation, conversion, and distribution products Collins Aerospace for integration of a new generation of avionics hardware and software featuring cyber-hardened and digital backbone solutions to configure and integrate mission systems GE Aviation for the 3,000-SHP T901 engine and working on the aircraft Health Awareness System (HAS) ITT-Enidine Inc. for the passive Liquid Inertia Vibration Eliminator (LIVE) units for all modes of operation including high speed L3Harris Technologies for the WESCAM™ MX-15D, an advanced, stabilized multi-sensor, multi-spectral imaging and targeting system Parker Lord for rotor dampers, the main rotor CF bearing, the tail rotor tension torsion strap, and the Active Vibration Control (AVC) System Mecaer Aviation Group, Inc. for a fully retractable, tail dragger landing gear system MOOG Inc. for flight control computer (FCC) electronics, software, and flight control actuation, critical components of the Bell fly-by-wire, Flight Control System (FCS) TRU Simulation + Training for a high-fidelity flight simulator that gives pilots a true sense of the aircraft flight controls Team Invictus is applying digital design and manufacturing technologies, including maintenance as part of the design process, and use of emerging commercial practices to bring a holistic view of digital models, processing and analysis to reduce lifecycle maintenance and servicing requirements—and thus reducing sustainment costs. “Each team member brings a capability that is vital to the success of the Bell 360 and we are honored to have proven, capable, and well-respected industry partners on Team Invictus,” stated Gehler. “This is an outstanding industry team, and we are working diligently to produce a FARA weapon system that is operationally effective and affordably sustainable, as well as complementary and in many ways common to the FLRAA program.” Following the selection of the Bell 360 Invictus for the competitive prototype in March 2020, Team Invictus continues to rapidly move forward. Team Invictus' collective expertise reduces program risk while preserving the Army's FARA schedule leading to a first flight targeted for the fourth quarter of fiscal 2022. To learn more about Bell 360 Invictus and FVL, please visit the Bell 360 Invictus website, and follow us on YouTube, LinkedIn, Twitter, Facebook, and Instagram. https://news.bellflight.com/en-US/189083-bell-teams-with-industry-leaders-for-u-s-army-future-attack-reconnaissance-aircraft-program

  • Top soldier says military looking for 'clarity' on Ottawa's budget plans | CBC News

    May 5, 2024 | Local, Land

    Top soldier says military looking for 'clarity' on Ottawa's budget plans | CBC News

    Just over a month into the new fiscal year and two weeks after the federal budget, the Department of National Defence is struggling to reconcile the Liberal government's approach to military funding — giving with one hand while taking with the other.

  • NEARLY $3 MILLION FOR AEROSPACE SMES

    November 14, 2018 | Local, Aerospace

    NEARLY $3 MILLION FOR AEROSPACE SMES

    Federal strategy for innovation and growth of Québec regions: NEARLY $3 MILLION FOR AEROSPACE SMEs Objective: Adoption of breakthrough technologies in aerospace Gaspé, November 9, 2018 — Aéro Montréal, Québec's aerospace cluster, received $2.977 million in funding today to support the development of the StartAero360° initiative during the launch of the federal strategy for innovation and growth of Québec regions. The Honourable Navdeep Bains, Minister of Innovation, Science and Economic Development and Minister responsible for Canada Economic Development for Québec Regions (CED), made the announcement this morning in Gaspé. This initiative aims to support Québec aerospace technology SMEs in the pre-commercialization phase of their innovative products. The SMEs participating in the initiative will be supported through a structured process, with the aim of collaboratively responding to a business opportunity that requires the development of an industrial proof of concept. This initiative will: Promote and accelerate the adoption of breakthrough innovations on the market; Support entrepreneurship and job creation in Canada by enabling SMEs to grow through the commercialization of new products; Boost the presence of Canadian industry internationally through the adoption and export of new and innovative niche technologies. To develop, aerospace SMEs need to increasingly deal with breakthrough technologies, such as digital technologies, metadata, artificial intelligence, and additive manufacturing. Our role is to provide SMEs with effective tools, in collaboration with both levels of government, to encourage them to adopt breakthrough technologies. “Our technology SMEs are still struggling to get past the pre-commercialization phase, which is necessary to ensure their commercial success. The StartAero360° initiative has been developed to give our SMEs the support they need to pre-commercialize their most innovative products,”says Suzanne M. Benoît, President of Aéro Montréal. The StartAero360° initiative aims to support 30 SMEs over 3 years. The program will have a total budget of $4.385 million, of which $1.4 million will be provided by the private sector. About Aéro Montréal Created in 2006, Aéro Montréal is a strategic think tank that groups all major decision makers in Québec's aerospace sector, including companies, educational and research institutions, as well as associations and unions. The activities of Aéro Montréal are made possible thanks to the participation of the governments of Québec and Canada and the Montréal Metropolitan Community, as well as company members of the cluster. -30- For more information: Gwenaël Brisé Manager, Communications and Media Relations Aéro Montréal 438 497-3857 gwenael.brise@aeromontreal.ca https://www.aeromontreal.ca/nearly-3-million-aerospace-smes.html

All news