25 février 2020 | Local, Naval

$1 billion and counting: Inside Canada's troubled efforts to build new warships

Federal government tables figures showing what it's spent on the projects to date
Murray Brewster

The federal government has spent slightly more than $1.01 billion over the last seven years on design and preparatory contracts for the navy's new frigates and supply ships — and the projects still haven't bought anything that floats.

The figures, tabled recently in Parliament, represent the first comprehensive snapshot of what has been spent thus far on the frequently-delayed project to build replacement warships.

It's an enormous amount of money for two programs that have been operating for more than a decade with little to show for their efforts to date.

It will be years before the Canadian Surface Combatant project — which aims to replace the navy's frontline frigates with 15 state-of-the-art vessels — and the Joint Support Ship program for two replenishment vessels actually deliver warships.

The numbers and details for each advance contract were produced in the House of Commons in response to written questions from the Conservative opposition.

The money was divided almost evenly between the federal government's two go-to shipyards: Irving Shipbuilding in Halifax, the prime contractor for the new frigates, and Seaspan of Vancouver, the builder of the supply ships.

The breakdown raises critical questions about at least one of the programs, said a defence analyst, but it also shines a light on promises made by both Liberal and Conservative governments to keep spending under control for both of these projects — which could end up costing more than $64 billion.

"I think there should be a level of concern [among the public] about whether or not what's being delivered in practice is what was advertised at the outset," said Dave Perry, a procurement expert and vice president of the Canadian Global Affairs Institute.

A design still in flux

Most of his concerns revolve around the new support ships, which the Liberal government says are in the process of being built now.

The written responses, tabled in Parliament, note that the projected cost for the two supply ships — $3.4 billion — remains under review "as the design effort finalizes."

Perry said he was astonished to learn that, "seven years and half-a-billion dollars into design work on an off-the-shelf design," the navy doesn't have the support ships, even though "the middle third of the ship is built" — and officials now say "the design effort isn't finished."

Usually, he said, ships are designed before they're built.

The head of the Department of National Defence's materiel branch said most of the preparatory contracts were needed to re-establish a Canadian shipbuilding industry that had been allowed to wither.

'A lot of patience'

"I think we have to look at the totality of everything that's being accomplished under" the national shipbuilding strategy, said Troy Crosby, assistant deputy minister of materiel at DND.

"Over that period of time, and with these expenditures, we've built a shipbuilding capability on two coasts, not just through National Defence but also through the coast guard, offshore fisheries science vessels. I understand it has taken a lot of patience, I suppose, and probably some uncertainty, but we're really getting to the point now where we can see delivering these capabilities to the navy."

The largest cash outlays involve what's known as definition contracts, which went individually to both shipyards and were in excess of $330 million each. They're meant to cover the supervision of the projects and — more importantly — to help convert pre-existing warship designs purchased by the federal government to Canadian standards.

The choices on each project were made at different times by different governments, but ministers serving both Liberal and Conservative governments decided that going with proven, off-the-shelf designs would be faster and less expensive than building from scratch.

Now, after all the delays, it's still not clear that choosing off-the-shelf designs has saved any money.

"I would be completely speculating on what it would cost to invest to develop the kind of expertise and capacity inside the government, inside National Defence and everybody involved, to be able to do something like that in-house," said Crosby.

"The approach we've taken at this point, by basing both the Joint Support Ship and the Canadian Surface Combatant on pre-existing designs, allows us to retire a lot of risk in the way forward."

When Crosby talks about "retiring risk," he's talking about the potential for further delays and cost overruns.

Among the contracts, Irving Shipbuilding was given $136 million to support the drawing up of the design tender for the new frigates and to pay for the shipbuilding advice Irving was giving the federal government throughout the bidding process.

Years ago, the federal government had enough in-house expertise to dispense with private sector guidance — but almost all of that expertise was lost over the past two decades as successive federal governments cut the defence and public works branches that would have done that work.

The last time Canada built major warships was in the 1990s, when the current fleet of 12 patrol frigates was inaugurated.

The federal government has chosen to base its new warships on the BAE Systems Type-26 design, which has been selected by the Royal Navy and the Royal Australian Navy.

The hull and propulsion system on the new frigates will be "largely unchanged" from the British design, but the combat system will be different and uniquely Canadian, said Crosby.

The project is still on track to start cutting steel for the new combat ships in 2023. Crosby said he would not speculate on when the navy will take delivery of the first one.

Delivery of the joint support ships is expected to be staggered, with the first one due in 2024.

There will be a two-year gap between ships, said Crosby, as the navy and the yard work through any technical issues arising with the first ship.

If that timeline holds, the first support ship will arrive two decades after it was first proposed and announced by the Liberal government of former prime minister Paul Martin.

https://www.cbc.ca/news/politics/frigates-joint-supply-ships-navy-procurement-canada-1.5474312

Sur le même sujet

  • PAL Aerospace seeks talent for SAR operating bases

    21 août 2018 | Local, Aérospatial

    PAL Aerospace seeks talent for SAR operating bases

    Chris Thatcher PAL Aerospace is on the hunt for maintenance, materiel, information technology and other support talent to staff the Royal Canadian Air Force's (RCAF's) four search and rescue main operating bases. Twenty months after the federal government selected 16 Airbus CC-295W fixed-wing search and rescue aircraft to replace six CC-115 Buffalos and 12 CC-130 H-model Hercules, St. John's, N.L.-based PAL is ready to hire the team that will deliver in-service support (ISS) for the new fleet. “PAL Aerospace will be providing a wide assortment of program management services as we prepare to undertake the maintenance and logistics support, heavy maintenance, including a mobile repair team, and centralize supply chain management activities for this aircraft,” Eva Martinez, vice-president of ISS, told the Abbotsford Aerospace, Defence and Security Expo (ADSE) in August. As a supplier to Airbus, PAL is responsible for maintenance and material support of the new fleet, providing an integrated team of aircraft maintenance engineers (AMEs), warehouse and tool crib personnel, a technical library and a contractor field office at four main operating bases in Comox, B.C., Winnipeg, Man., Trenton, Ont., and Greenwood, N.S. Each base will require around 11 people. PAL will also establish and maintain a maintenance, repair and overhaul (MRO) facility in Winnipeg for heavy maintenance work. The shop will be co-located with its central warehouse, and will be home base for the mobile repair team. In total, PAL expects to hire around 28 people to staff the facility. As for material, PAL will provide ground support equipment, a 30-day supply of aircraft consumables at each base, personal protective equipment, and shipping and handling of all aircraft spare parts, said Martinez, an aerospace engineer who served 13 years in the Air Force. Through a joint venture with Airbus called AirPro, PAL will collaborate on the integration of all ISS services. “Our hiring target as it stands right now is 73,” she said. “As we work with Canada and Airbus to fully define the maintenance tasks, we could see an increase in the level of effort required...for AMEs.” That workload is based in part on RCAF plans to locate three CC-295W at each base. Two more will reside with the operational training unit in Comox while a final two will serve as floaters. “They will be moved around depending on the induction into heavy maintenance as well as the operational tempo,” said Martinez. Comox, which will include the RCAF's new search and rescue training centre, will stand up in 2019 to coincide with the arrival of the first aircraft, expected by the end of next year. The front, mid and rear fuselage sections have been delivered to Airbus's pre-final assembly line in Tablada, Spain, and the final aircraft is expected to roll out in the first quarter of 2019. Full article: https://www.skiesmag.com/news/pal-aerospace-seeks-iss-talent-for-rcaf-sar-operating-bases/

  • Annex B: Overview of long-term funding commitment to Canadian Armed Forces capabilities

    14 juillet 2020 | Local, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

    Annex B: Overview of long-term funding commitment to Canadian Armed Forces capabilities

    To ensure that the women and men of the Canadian Armed Forces have the capabilities required for Canada to be Strong at home, Secure in North America and Engaged in the world, this policy commits to significant long-term investment. This includes $33.8 billion for 52 critical new capital projects. In addition, the policy provides $74.2 billion for existing assets and previously planned equipment, infrastructure and information technology projects. As part of Strong, Secure, Engaged, these projects underwent a thorough costing review, which resulted in the provision of an additional $5.9 billion over 20 years on top of what had previously been budgeted for these projects, to better reflect their true costs. In total, this new vision for defence provides $108 billion for the development and acquisition of capital equipment over the next 20 years. All of these projects have been costed and the costing methodologies used were independently verified by five external accounting firms. Throughout the process, Defence also worked with costing experts from Deloitte who brought expertise gained from its involvement in recent defence reviews of close Canadian allies. This rigorous and unprecedented process ensures that the vision laid out in this policy is credible and realistic. Table 1 reflects the planned use of the accrual budget over the 20-year horizon of this policy. It is important to note that this table does not represent the total cost of all planned equipment acquisitions. For example, the first new Canadian Surface Combatant is not scheduled to be delivered until 2026, followed by the remaining 14 ships. As these ships have an expected service life of 30 years, much of the accrual costs will be incurred outside the 20 years reflected in the table. Furthermore, as these are 20-year estimates, there needs to be flexibility to adjust the accrual budget to reflect changes in major capital projects. The process to adjust or re-profile these estimates over time is through the investment planning process. Defence will publish the next Defence Investment Plan in 2018. The Defence Investment Plan will include all approved capital projects under the policy and will be updated every three years. This will help ensure that Parliament and Canadians can clearly understand future changes to the budget, and deliver on the Government's commitment to transparency, results, and accountability. Table 1: 20-year accrual and cash view of planned projects and new investments ($ billions) 20-year - Accrual basis 20-Year - Cash basis Capability Investments to fully fund and complete planned projects table 1 note1 New investment Strong, Secure, Engaged table 1 note2 Total planned projects and new investments Total planned projects and new investments Royal Canadian Navy 14.6 2.9 17.5 53.5 Canadian Army 10.1 8.8 18.9 23.2 Royal Canadian Air Force 26.4 20.1 46.4 64.4 Special Operations Forces 1.2 0.4 1.5 1.2 Joint/Emerging Domains 3.4 1.2 4.6 9.7 Infrastructure 4.5 0.4 4.9 12.0 Total Capabilities 60.1 33.8 93.9 164.0 Accrual Expenditure for Existing Equipment and Infrastructure table 1 note3 14.1 - 14.1 - 20 Year Total table 1 note4 74.2 33.8 108.0 164.0 Table 1 Note 1 Strong, Secure, Engaged commits $74.2 billion over 20 years to fully fund 281 projects that were planned, but for which Defence had insufficient funding to acquire. Adequate funding has now been allocated to deliver these core equipment projects. Return to table 1 note1referrer Table 1 Note 2 Strong, Secure, Engaged commits $33.8 billion over the next 20 years to 52 new equipment, infrastructure, and information technology projects for the Canadian Armed Forces. Return to table 1 note2referrer Table 1 Note 3 This amount ($14.1 billion), on an accrual basis, represents previously acquired equipment and infrastructure. As they are already in service, there is no future cash requirement to purchase these assets. Return to table 1 note3referrer Table 1 Note 4 Totals may not add up due to rounding. Return to table 1 note4referrer Below is an overview of capital funding commitments in Strong, Secure, Engaged, described in terms of investments in the Royal Canadian Navy, Canadian Army, Royal Canadian Air Force, Special Operations Forces, Joint Capabilities and Infrastructure. Investment in the Royal Canadian Navy The Government will provide $17.5 billion to fund equipment projects for the Royal Canadian Navy over the next 20 years. This includes: $2.9 billion over the next 20 years for two new equipment investments in the Royal Canadian Navy to replace obsolete components of current systems and improve the Royal Canadian Navy's ability to meet evolving underwater threats. $14.6 billion over the next 20 years to fully fund planned equipment projects. For example, this policy includes sufficient funding to acquire the full complement of 15 Canadian Surface Combatants. It is important to note that Table 1 only captures a 20-year view of the equipment investments committed to in this policy. As the first ship is not scheduled to be delivered until 2026 and the fleet is expected to be in service for 30 years, there will be significant expenditures outside this timeframe. Investment in the Canadian Army The Government will provide $18.9 billion for Canadian Army equipment projects over the next 20 years. This includes: $8.8 billion over the next 20 years for 20 new equipment projects. As examples, this investment will replace existing light and heavy trucks for use in domestic and expeditionary operations. We will also improve the Canadian Army's ability to operate in Canada's North with a new family of Arctic-capable land vehicles, as well as close critical capability gaps such as the Canadian Army's lack of ground-based air defence equipment, which will allow it to defeat threats posed by airborne weapons such as remotely piloted vehicles and aircraft used by potential adversaries. $10.1 billion over the next 20 years to fully fund planned equipment projects. For example, the upgrade of the Light Armoured Vehicle fleet will improve mobility and survivability. Investment in the Royal Canadian Air Force The Government will provide $46.4 billion to fund equipment projects for the Royal Canadian Air Force over the next 20 years. This includes: $20.1 billion over the next 20 years for 17 new equipment projects for the Royal Canadian Air Force. For example, this will deliver a Canadian Multi-Mission Aircraft to replace the CP-140 Aurora Long Range Patrol Aircraft, allowing us to maintain our technological advantage over potential adversaries. Under the Royal Canadian Air Force's responsibility for space capabilities, portions of new investment will expand the Canadian Armed Forces' ability to use space-based assets in support of operations. This includes projects for enhanced communications in the North. $26.4 billion to fully fund planned equipment projects. The new fighter program has been enhanced to ensure the Royal Canadian Air Force can acquire 88 new advanced fighters, which will allow us to deliver on NORAD and NATO commitments without compromise. Investment in Special Operations Forces The Government will provide $1.5 billion to fund equipment projects for Canada's Special Operations Forces over the next 20 years. This includes: $366 million over the next 20 years for four new projects. For example, integrated soldier system equipment will be modernized to enhance interoperability and maintain technological advantage against potential adversaries. $1.2 billion over the next 20 years to fully fund planned equipment projects. As an example, we will acquire an airborne intelligence surveillance and reconnaissance platform that will enhance the ability of our Special Operations Forces to improve their understanding of the operational environment. Investment in joint capabilities The Government will provide $4.6 billion for joint capability projects in domains such as cyber, intelligence as well as joint command and control over the next 20 years. This includes: $1.2 billion over the next 20 years for five new equipment projects and one information technology project. For example, the Combined Joint Intelligence Modernization project will provide a modern deployable intelligence centre for land-based operations, building on the lessons learned in recent operations. Additionally, the Secure Radio Modernization project will upgrade encryption capability of radios to maintain security and interoperability with our Five-Eyes partners. $3.4 billion over the next 20 years to fully fund planned equipment projects. For example, we will improve the capabilities of the Joint Deployable Headquarters and Signals Regiment. This will include the acquisition of portable structures to house the deployed headquarters and the equipment employed by its staff for command, control and communications. Investment in infrastructure The Government will provide $4.9 billion over the next 20 years to infrastructure projects across Canada in order to maintain the necessary portfolio of real property holdings. This includes: $446 million over the next 20 years for three new infrastructure projects. For example, this funding will enable the construction of new buildings to house the expanded and enhanced Canadian Armed Forces Joint Incident Response Unit. This will ensure that the unit is able to provide chemical, biological, radiological, and nuclear defence support to the Canadian Special Operations Forces Command. $4.5 billion to fully fund planned projects over the next 20 years. https://www.canada.ca/en/department-national-defence/corporate/reports-publications/canada-defence-policy/annex-b.html

  • ANALYSIS | The U.S. needs a few good allies. Does it still need Canada? | CBC News

    22 septembre 2024 | Local, Sécurité

    ANALYSIS | The U.S. needs a few good allies. Does it still need Canada? | CBC News

    Eight decades after the United States extended its security umbrella to cover Canada, the alliance is being undermined by Washington's growing exasperation with Ottawa's attitude toward defence spending.

Toutes les nouvelles