20 mars 2020 | International, Aérospatial

UK Declared F-35 Operational Despite Issues, Auditors Say

Tony Osborne

The UK declared the F-35 operational even though the fleet was suffering from availability, infrastructure, logistics and security issues, auditors have revealed.

The UK National Audit Office (NAO) found that the December 2018 initial operating capability (IOC) from land bases was granted with 67 exceptions, with almost one-third of those still yet to be resolved more than a year later. It is not clear on how many criteria IOC (Land) was judged.

In its report studying how new capabilities are delivered into front-line operations, the NAO reported that in the run-up to the milestone there had been delays in the provision of synthetic training facilities. This impacted the availability of pilots and maintainers, while operational availability of the aircraft “hampered the ability to deliver training.”

The report appears to confirm the reasons behind a 34-day flying break by the UK-based fleet in the late summer of 2018 reported by Aerospace DAILY.

Plans to use simulators for training have been frustrated by “technical difficulties and delays in security vetting.”

The NAO said the UK Ministry of Defense is able to use exemptions when bringing a new capability into service. Capabilities that do not meet specifications but are deemed good enough would be given an exemption. The NAO also says that IOC acceptance criteria for the F-35 was not finalized “until several years” after business case approval in the second half of 2017.

Exemptions arose from “not being able to demonstrate deployability through a planned exercise,” because of aircraft availability, a reliance on contractors for mission support because of a lack of trained Royal Air Force personnel, and a lack of access to mission support training facilities in the U.S. Another challenge was an inability to program aircraft with UK mission data independently of the U.S. This has since been addressed with the opening of the Australian, Canadian and United Kingdom Reprogramming Laboratory (ACURL) at Eglin AFB, Florida, which was declared operational in February.

The NAO notes that some 20 of the exemptions had still not been resolved as of last month. But the NAO says the Royal Air Force and Royal Navy have made progress in the areas of training personnel and logistics.

The UK now has 15 F-35Bs based in the country flying with front-line unit 617 Sqdn. and with 207 Sqdn, a training unit. Since their arrival to the UK, the aircraft have been deployed to Cyprus and flown operational missions in the Middle East. They also recently took part in a Tier 1 Red Flag exercise with Five Eyes partners Australia and the U.S.

A Lockheed Martin spokesman said that while it was for the customer to answer questions concerning IOC, “the F-35 program globally continues to mature, and Lockheed Martin has made significant steps in terms of reliability and aircraft availability, with the global fleet averaging greater than 65% mission-capable rates and operational units consistently performing near 75%.”

Questions to the UK Ministry of Defense had not been answered at the time of publication.

https://aviationweek.com/defense-space/budget-policy-operations/uk-declared-f-35-operational-despite-issues-auditors-say

Sur le même sujet

  • Contract Awards by US Department of Defense - May 11, 2020

    12 mai 2020 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

    Contract Awards by US Department of Defense - May 11, 2020

    AIR FORCE Unisys Corp., Reston, Virginia, has been awarded a $630,000,000 single-award, indefinite-delivery/indefinite-quantity contract for technology application development and sustainment (TADS) supporting the Air Force weather enterprise. Orders under the TADS contract will support development, delivery and sustainment of an integrated system of weather enterprise hardware and software dedicated to providing accurate, consistent, relevant and timely environmental intelligence. Work will be performed at Offutt Air Force Base, Nebraska; and Omaha, Nebraska, and is expected to be completed by Oct. 15, 2025. This award is the result of a competitive acquisition and six proposals were received. Fiscal 2020 operations and maintenance funds in the amount of $2,182,983 are being obligated at the time of award. The 55th Contracting Squadron, Offutt AFB, Nebraska, is the contracting activity (FA4600-20-D-0002). ApiJECT Systems America Inc., Stamford, Connecticut, has been awarded a not-to-exceed $138,000,000 firm-fixed-price, undefinitized contract action (UCA) for COVID-19 response “Project Jumpstart” and “Project Rapid,” which will dramatically expand production capability for domestically manufactured blow-fill-seal injection devices. Work will be performed throughout the U.S. and is expected to be completed by May 8, 2022. This award is the result of a sole-source acquisition. Fiscal 2020 Air Force other procurement funds in the amount of $69,000,000 are being obligated at the time of UCA issuance and remaining funding will be added at definitization. The Air Force Life Cycle Management Center, Hanscom Air Force Base, Massachusetts, is the contracting activity (FA8726-20-C-0022). (Awarded May 8, 2020) Raytheon Corp., Marlborough, Massachusetts, has been awarded a $20,232,337 firm-fixed-price modification (P00113) to contract FA8705-14-C-0001 to exercise 23 fixed spares for Production Year Two, Option Contract Line Item Number 0008, for a Global Aircrew Strategic Network Terminal. Work will be performed in Largo, Florida, and is expected to be completed by July 2022. Fiscal 2020 other procurement funds in the full amount are being obligated at the time of award. This modification brings the total cumulative value of the contract to $488,205,869. Air Force Materiel Command, Hanscom Air Force Base, Massachusetts, is the contracting activity. ARMY Chemring Sensors and Electronic Systems Inc., Dulles, Virginia, was awarded a $200,218,380 modification (P00009) to contract W909MY-18-D-0014 to develop, integrate and produce and deliver Husky Mounted Detection System kits, spare parts, maintenance and training. Bids were solicited via the internet with one received. Work locations and funding will be determined with each order, with an estimated completion date of Aug. 15, 2022. U.S. Army Contracting Command, Aberdeen Proving Ground, Maryland, is the contracting activity. NAVY BAE Systems Land & Armaments L.P., Minneapolis, Minnesota, is awarded a $42,842,169 firm-fixed-price modification to previously awarded contract N00024-20-C-5380 for MK 41 Vertical Launching System (VLS) canister production and ancillary hardware. This modification combines purchases for the Navy (68%); and the governments of Japan (11%); Australia (6%); Norway (6%); Netherlands (6%); and Turkey (3%), under the Foreign Military Sales (FMS) program. Work will be performed in Minneapolis, Minnesota (10%); and Aberdeen, South Dakota (90%). This option exercise provides for the manufacture and delivery of MK 13 Mod 0, MK 21 (Mod 2 and 3), MK 21 Mod 1 and MK 29 Mod 0 canisters, ancillary hardware and MK 13 Mod 0 canister renews. The VLS canisters serve as the missile shipping containers and launch tubes when loaded into VLS Modules. Work is expected to be complete by July 2023. Fiscal 2020 weapons procurement (Navy); fiscal 2019 and 2020 defense-wide procurement; and FMS funds in the amount of $42,842,169 will be obligated at time of award and will not expire at the end of the current fiscal year. The Naval Sea Systems Command, Washington Navy Yard, Washington, D.C., is the contracting activity. Cape Environmental Management Inc.,* Honolulu, Hawaii, is awarded an $11,674,808 cost-plus-award-fee task order N62473-20-F-4678 under a single-award small business environmental remedial action contract for removal actions and environmental restoration activities at installation restoration and munition response sites at Marine Corps Air Station Miramar, San Diego, California. Work will be performed in San Diego, California, and provides for site maintenance activities at Installation Restoration Site (IRS) 21, time critical removal action at IRS 20 and non-time critical removal action at Munitions Response Site 5. Work is expected to be complete by May 2023. Fiscal 2020 operations and maintenance (Navy) contract funds in the amount of $11,674,808 are obligated on this award and will expire at the end of the current fiscal year. One proposal was received for this task order. The Naval Facilities Engineering Command, Southwest, San Diego, California, is the contracting activity (N62742-16-D-1807). WASHINGTON HEADQUARTERS SERVICES General Dynamics Information Technology, Falls Church, Virginia, has been awarded a $7,417,730 firm-fixed-price contract. This contract provides case analysts, defense security officers, and program management support for the Office of Military Commissions hearings. Work performance will take place at U.S. Naval Station Guantanamo Bay, Cuba. Fiscal 2020 operations and maintenance funds in the amount of $7,417,730 are being awarded. The expected completion date is May 10, 2023. Washington Headquarters Services, Arlington, Virginia, is the contracting activity (HQ0034-20-C-0082). *Small business https://www.defense.gov/Newsroom/Contracts/Contract/Article/2183554/source/GovDelivery/

  • Army readies to select tactical truck builders

    19 octobre 2022 | International, Terrestre

    Army readies to select tactical truck builders

    The Army will soon decide who will build prototypes for a competition for the service's future Common Tactical Truck.

  • Eurofighter submits updated proposal to HX programme

    5 février 2020 | International, Aérospatial

    Eurofighter submits updated proposal to HX programme

    January 31, 2020 - Eurofighter has offered Finland the chance to join Europe's largest combat aircraft programme in an updated proposal to the HX fighter acquisition programme. The proposal has been submitted by the UK Government with the support of the Governments of Germany, Italy and Spain, the nations which are represented in the Eurofighter industry consortium. It offers Finland sovereign control of its defence capability and security of supply as well as a combat proven, swing-role aircraft which will form the backbone of European defence for decades to come. The detailed proposal updates on the original offer made to the HX fighter acquisition programme to replace the Finnish Air Force's F-18 Hornet aircraft. John Rossall, Campaign Director at BAE Systems which is working alongside the UK Government on the offer to Finland, said: We are delighted to present our updated proposal to Finland on behalf of the Eurofighter consortium. Our proposal is an invitation to Finland to join leading nations in Europe with a shared defence objective. By choosing Eurofighter, the Finnish Air Force would not only be acquiring the most advanced, multi-role aircraft on the market, it would be choosing everything Finland needs to operate, maintain and control its own aircraft in peacetime and in times of crisis. In January, Eurofighter took part in the HX Challenge Flight Evaluation Trials, led by the Finnish Defence Forces in Tampere. The trials saw two Royal Air Force jets perform over a five-day period to demonstrate many of the capabilities which form the offering of the Eurofighter consortium, which teams BAE Systems alongside leading European defence contractors Airbus and Leonardo. Ahead of the trials, representatives of the Governments of the UK, Germany, Italy and Spain confirmed their commitment to a capability roadmap which will keep Eurofighter in the frontline of European defence for decades to come. View source version on Eurofighter: https://www.eurofighter.com/news-and-events/2020/01/eurofighter-submits-updated-proposal-to-hx-programme

Toutes les nouvelles