20 mars 2020 | International, Aérospatial

UK Declared F-35 Operational Despite Issues, Auditors Say

Tony Osborne

The UK declared the F-35 operational even though the fleet was suffering from availability, infrastructure, logistics and security issues, auditors have revealed.

The UK National Audit Office (NAO) found that the December 2018 initial operating capability (IOC) from land bases was granted with 67 exceptions, with almost one-third of those still yet to be resolved more than a year later. It is not clear on how many criteria IOC (Land) was judged.

In its report studying how new capabilities are delivered into front-line operations, the NAO reported that in the run-up to the milestone there had been delays in the provision of synthetic training facilities. This impacted the availability of pilots and maintainers, while operational availability of the aircraft “hampered the ability to deliver training.”

The report appears to confirm the reasons behind a 34-day flying break by the UK-based fleet in the late summer of 2018 reported by Aerospace DAILY.

Plans to use simulators for training have been frustrated by “technical difficulties and delays in security vetting.”

The NAO said the UK Ministry of Defense is able to use exemptions when bringing a new capability into service. Capabilities that do not meet specifications but are deemed good enough would be given an exemption. The NAO also says that IOC acceptance criteria for the F-35 was not finalized “until several years” after business case approval in the second half of 2017.

Exemptions arose from “not being able to demonstrate deployability through a planned exercise,” because of aircraft availability, a reliance on contractors for mission support because of a lack of trained Royal Air Force personnel, and a lack of access to mission support training facilities in the U.S. Another challenge was an inability to program aircraft with UK mission data independently of the U.S. This has since been addressed with the opening of the Australian, Canadian and United Kingdom Reprogramming Laboratory (ACURL) at Eglin AFB, Florida, which was declared operational in February.

The NAO notes that some 20 of the exemptions had still not been resolved as of last month. But the NAO says the Royal Air Force and Royal Navy have made progress in the areas of training personnel and logistics.

The UK now has 15 F-35Bs based in the country flying with front-line unit 617 Sqdn. and with 207 Sqdn, a training unit. Since their arrival to the UK, the aircraft have been deployed to Cyprus and flown operational missions in the Middle East. They also recently took part in a Tier 1 Red Flag exercise with Five Eyes partners Australia and the U.S.

A Lockheed Martin spokesman said that while it was for the customer to answer questions concerning IOC, “the F-35 program globally continues to mature, and Lockheed Martin has made significant steps in terms of reliability and aircraft availability, with the global fleet averaging greater than 65% mission-capable rates and operational units consistently performing near 75%.”

Questions to the UK Ministry of Defense had not been answered at the time of publication.

https://aviationweek.com/defense-space/budget-policy-operations/uk-declared-f-35-operational-despite-issues-auditors-say

Sur le même sujet

  • Finnish officials begin sifting through final HX fighter offers

    4 mai 2021 | International, Aérospatial

    Finnish officials begin sifting through final HX fighter offers

    The government in Helsinki received finals offers from five vendors for the multibillion-dollar HX fighter competition, kicking off an evaluation phase slated to run through the remainder of 2021.

  • Navy Issues Final RFP for FFG(X) Next-Generation Frigate

    21 juin 2019 | International, Naval

    Navy Issues Final RFP for FFG(X) Next-Generation Frigate

    By: Megan Eckstein The Navy released the final request for proposals for its next guided-missile frigate (FFG(X)) today, outlining the program that will get the U.S. Navy into the business of operating high-end small combatants. The service is counting on the new frigate to help the fleet operate in a distributed manner in a contested maritime environment. To that end, the final solicitation for bids for the FFG(X) program highlights a particular interest in what industry can offer in range; margins for weight, cooling, electrical and arrangeable deck area, to allow the ship to bring in new technologies as they develop; acoustic signature management; undersea surveillance; and over-the-horizon capabilities. After previous iterations of the frigate were ditched as the Navy's view of what capability it wanted evolved, the current FFG(X) effort sought to bring in industry early to ensure that requirements were in line with what technologies were currently feasible at the right price point. Those ongoing discussions led the Navy to settle on a ship that would have at least 32 vertical launching system (VLS) cells, an Aegis-based combat system, the Cooperative Engagement Capability datalink so the frigate could share targeting data with other ships and aircraft, and advanced anti-submarine warfare and electronic warfare systems. The service announced earlier this year the frigate would include as government-furnished equipment: A fixed-face Raytheon Enterprise Air Surveillance Radar (EASR) that will serve as the primary air search radar. At least 32 Mark 41 Vertical Launch System cells that could field Standard Missile 2 Block IIICs or RIM-162 Evolved SeaSparrow Missiles (ESSM) and a planned vertically launched anti-submarine warfare weapon. COMBATSS-21 Combat Management System based on the Aegis Combat System. Cooperative Engagement Capability (CEC) datalink that would allow the frigate to share targeting information with other ships and aircraft. Space, weight and cooling for 8 to 16 Over-the-Horizon Anti-Ship Cruise Missiles An aviation detachment that includes an MH-60R Seahawk helicopter and an MQ-8C Firescout Unmanned Aerial Vehicle. AN/SQQ-89(V)15 Surface Ship Anti-Submarine Warfare (ASW) Combat System AN/SQS-62 Variable Depth Sonar. SLQ-32(V)6 Surface Electronic Warfare Improvement Program (SEWIP) Block 2 electronic warfare suite with allowances to include SEWIP Block 3 Lite in the future. Space, weight and cooling reservation for a 150-kilowatt laser. Further highlighting the focus on allowing the ships to be upgraded as technology evolves, the solicitation asks that bids include a “description of the flexibility in the design to accommodate efficient warfare systems upgrades by explaining equipment removal and upgrade paths with an emphasis on avoiding hull cuts or the need for dry docking,” as well as provisions for upgrading hull-mounted and towed undersea warfare sensors. Five industry teams have been involved in early design maturation efforts, which both helped industry refine their plans to be more in line with what the Navy wanted, and allowed the Navy to refine its idea of how much this new class might cost. Earlier this year, USNI News reported that costs were coming down as a result of the design maturation contracts. “$950 (million) was the threshold; $800 million is the objective,” frigate program manager with Program Executive Office Unmanned and Small Combatants Regan Campbell said in January at the Surface Navy Association symposium. “We started closer to the $950; we are trending to very close to the $800 now. We have taken some very significant costs out,” she said of the second through 10th ship of the class. The Navy intends to buy at least 20 frigates, though the first contract will only cover the first 10. After the first contract, the Navy could continue with the same builder or re-compete the program to potentially bring in a second builder, if it wanted to accelerate frigate production to keep in line with its drive to reach a 355-ship fleet and leadership acknowledgement that it will need more small combatants and fewer high-end destroyers going forward. After the release of today's final RFP, interested bidders will have until Aug. 22 to submit their technical proposals to the Navy and until Sept. 26 to submit their pricing proposal. A winner will be selected in Fiscal Year 2020 to build the frigate. Of the five companies that participated in the design maturation phase, four are expected to submit bids to the RFP. Austal USA, who builds the Independence-variant Littoral Combat Ship; Fincantieri Marine, which builds the Italian FREMM multipurpose frigate; General Dynamics Bath Iron Works, who will partner with Spanish F100-builder Navantia; and Ingalls Shipbuilding, who has declined to discuss its design, all worked with the Navy to take their existing parent designs and mature them to become in line with the Navy's vision for its guided-missile frigate. Lockheed Martin, which builds the Freedom-variant LCS, was part of that effort as well but announced it would not continue on with the frigate competition. Despite the earlier design work that the Navy funded, the frigate competition is open to any bidder who has a parent design to base the frigate offering on. https://news.usni.org/2019/06/20/navy-issues-final-rfp-for-ffgx-next-generation-frigate

  • EU defense ambitions trickle down to industry, but is it good for business?

    13 août 2018 | International, Aérospatial, Naval, Terrestre, C4ISR

    EU defense ambitions trickle down to industry, but is it good for business?

    By: Martin Banks BRUSSELS — After two decades in which spending was often cut or stagnant, Europe is gearing up to spend big on defense. European Union nations, now unfettered by Britain's decision to leave the organization, have achieved a 70-year-old ambition to integrate their defenses, launching a pact among 25 EU governments to jointly fund, develop and deploy armed forces. The pact, called Permanent Structured Cooperation, or PESCO, is meant as a show of unity and a tangible step in EU integration, particularly after Brexit. Earlier this year, Brussels also launched a major incentive for EU member states to cooperate on military procurement with a European Defence Fund, or EDF, worth €5 billion (U.S. $5.8 billion) per year, the first time the EU has put serious money on the table for this purpose. The EU has already approved one aspect of the fund, the European Defence Industrial Development Programme, or EDIDP, intended to foster cross-border cooperation between companies. But this huge upsurge in EU defense efforts begs the question: Are these various initiatives doing anything to bolster Europe's defense industry? Full Article: https://www.defensenews.com/top-100/2018/08/09/eu-defense-ambitions-trickle-down-to-industry-but-is-it-good-for-business/

Toutes les nouvelles