UK Declared F-35 Operational Despite Issues, Auditors Say

Tony Osborne

The UK declared the F-35 operational even though the fleet was suffering from availability, infrastructure, logistics and security issues, auditors have revealed.

The UK National Audit Office (NAO) found that the December 2018 initial operating capability (IOC) from land bases was granted with 67 exceptions, with almost one-third of those still yet to be resolved more than a year later. It is not clear on how many criteria IOC (Land) was judged.

In its report studying how new capabilities are delivered into front-line operations, the NAO reported that in the run-up to the milestone there had been delays in the provision of synthetic training facilities. This impacted the availability of pilots and maintainers, while operational availability of the aircraft “hampered the ability to deliver training.”

The report appears to confirm the reasons behind a 34-day flying break by the UK-based fleet in the late summer of 2018 reported by Aerospace DAILY.

Plans to use simulators for training have been frustrated by “technical difficulties and delays in security vetting.”

The NAO said the UK Ministry of Defense is able to use exemptions when bringing a new capability into service. Capabilities that do not meet specifications but are deemed good enough would be given an exemption. The NAO also says that IOC acceptance criteria for the F-35 was not finalized “until several years” after business case approval in the second half of 2017.

Exemptions arose from “not being able to demonstrate deployability through a planned exercise,” because of aircraft availability, a reliance on contractors for mission support because of a lack of trained Royal Air Force personnel, and a lack of access to mission support training facilities in the U.S. Another challenge was an inability to program aircraft with UK mission data independently of the U.S. This has since been addressed with the opening of the Australian, Canadian and United Kingdom Reprogramming Laboratory (ACURL) at Eglin AFB, Florida, which was declared operational in February.

The NAO notes that some 20 of the exemptions had still not been resolved as of last month. But the NAO says the Royal Air Force and Royal Navy have made progress in the areas of training personnel and logistics.

The UK now has 15 F-35Bs based in the country flying with front-line unit 617 Sqdn. and with 207 Sqdn, a training unit. Since their arrival to the UK, the aircraft have been deployed to Cyprus and flown operational missions in the Middle East. They also recently took part in a Tier 1 Red Flag exercise with Five Eyes partners Australia and the U.S.

A Lockheed Martin spokesman said that while it was for the customer to answer questions concerning IOC, “the F-35 program globally continues to mature, and Lockheed Martin has made significant steps in terms of reliability and aircraft availability, with the global fleet averaging greater than 65% mission-capable rates and operational units consistently performing near 75%.”

Questions to the UK Ministry of Defense had not been answered at the time of publication.

https://aviationweek.com/defense-space/budget-policy-operations/uk-declared-f-35-operational-despite-issues-auditors-say

On the same subject

  • Le missile Air-Air très longue portée russe R37M entrera bientôt en service

    October 1, 2018 | International, Aerospace

    Le missile Air-Air très longue portée russe R37M entrera bientôt en service

    FABRICE WOLF Avec plus de 4000 avions de combat modernes de tout type, l'OTAN dispose de la plus formidable force aérienne au monde, très supérieure aux forces russes (1300 appareils) et chinoises (1500 appareils). Consciente qu'elle ne pourra jamais rivaliser numériquement avec cette force, la Russie a développé une stratégie de défense aérienne multi-couches reposant sur des systèmes de défense anti-aérienne à longue, moyenne et courte portée, intégrée dans un réseau global et coordonnant ses actions avec l'importante flotte de chasseurs russes de plus de 800 appareils Su27-30-35 et MIG-29, et les 130 intercepteurs MIG-31. Ainsi organisée, la défense anti-aérienne russe représente un challenge important pour les forces aériennes occidentales, qui doivent utiliser des avions de brouillage ou des appareils furtifs pour espérer garder la supériorité aérienne. Pour articuler cette puissance aérienne, qui représente aujourd'hui 80% de la puissance de feu de l'Alliance selon le British Defense Comittee, l'OTAN déploie un nombre important d'appareils de veille aérienne AWACS, de surveillance électronique, et une flotte massive d'avions ravitailleurs. Le missile à longue portée hypersonique R37M a été développé pour engager et abattre ces appareils, avec une portée supérieure à 300 km et une vitesse supérieure à Mach6. Destiné à équiper les intercepteurs rapides MIG-31 et les chasseurs lourds furtifs Su-57, le R37M permettra de repousser les appareils de soutien de l'OTAN très loin de la zone d'engagement, limitant de fait très sensiblement leurs performances. Un appareil qui, comme le F-35 américain, n'a qu'un rayon d'action de 1000 km, sera ainsi largement contraint s'il doit se ravitailler à 500 km de ses objectifs. En outre, les forces russes auront la possibilité de mener des « raids tactiques », des incursions rapides destinées à porter le danger au plus profond du dispositif adverse, suivi d'un retour rapide dans la zone de supériorité alliée. Au delà des AWACS et ravitailleurs, le nouveau missile menacera donc l'ensemble des appareils lourds de l'alliance atlantique, incluant les avions de transport en charge du train logistique transatlantique indispensable, ainsi que les appareils de patrouille maritime, surtout ceux évoluant à moyenne altitude comme le P8 Poséidon, très exposés dès qu'ils évolueront à moins de 2000 km d'une base aérienne russe. Les mêmes causes ayant les même conséquences, la Chine a elle-aussi développé un missile à très longue portée, estimée à 400 km, et destiné à abattre les appareils de soutien occidentaux. Le nouveau missile, dont la nomenclature est encore floue, a déjà été aperçu sous les ailes des J-11 et des J-16 de l'Armée Populaire de Libération. Ce type de missile n'a pas d'équivalent en Occident. En effet, les forces aériennes chinoises et russes dépendent beaucoup moins des appareils de soutien que leurs homologues occidentaux. En revanche, les états-majors de l'OTAN ont privilégié des missiles d'une portée inferieure, de l'ordre de 150 km, mais très efficaces contre les agiles chasseurs adverses, comme le missile européen Meteor. L'entrée en service du R37M devra donc engendrer une rapide évolution des doctrines aériennes de l'OTAN, comme dans la conception des appareils lourds, qui devront nécessairement être équipés de systèmes d'autodéfense performants capables de détecter, brouiller et leurrer de tels missiles. https://analysedefense.fr/blogs/articles/le-missile-air-air-tres-longue-portee-russe-r37m-entrera-bientot-en-service

  • Army preps for competition limited to Bell and Sikorsky for long-range assault helicopter

    December 11, 2020 | International, Aerospace, Land

    Army preps for competition limited to Bell and Sikorsky for long-range assault helicopter

    By: Jen Judson WASHINGTON — The Army is taking its final steps before starting a competition to acquire a Future Long Range Assault Aircraft, and has done so by issuing an intent to solicit bids using means “other than full and open competition,” according to a Dec. 9 post on on the government contracts website Beta.Sam.Gov. This step means that unless a surprise vendor can meet all of the Army's technical and production requirements for FLRAA in the next two weeks, the future aircraft will be supplied by either Bell or Lockheed Martin's Sikorsky. Bell and a Sikorsky-Boeing team have been pitted against one another for years to build and fly technology demonstrators to inform requirements ahead of the FLRAA competition and both are part of a competitive demonstration and risk reduction phase. Bell's V-280 Valor tiltrotor had it's first flight nearly three years ago and Sikorsky and Boeing's SB-1 Defiant coaxial helicopter flew for the first time in March 2019. The draft request for proposals is expected to be released by the end of the year with a final solicitations expected in fiscal 2021. Modernizing its vertical lift fleet is the Army's third highest priority behind Long-Range Precision Fires and Next-Generation Combat Vehicle development. The Army intends to field both a FLRAA and Future Attack Reconnaissance Aircraft by roughly FY30. Bell and Lockheed Martin are also competing against each other in the FARA competition. Bell's offering is the 360 Invictus and Lockheed's entry is the Raider X. In the case of FLRAA, the winner must build eight production aircraft for the first unit equipped by FY30. The plan is to award a contract to a winner in FY22. The winner will proceed to deliver a preliminary design review roughly eight months following the award. According to the pre-solicitation, “the Army has determined through extensive market research, including a July 2020 sources sought, that only two sources exist in the market space that have the capability and capacity of developing, manufacturing, testing and delivering both prototype and initial production FLRAA in the time allocated to achieve the Army's goal of an FUE in FY 2030.” The Army stated that Bell and Sikorsky are those two sources, but notes that “any other responsible, qualified sources, ... that can develop and produce the FLRAA weapon system to achieve First Unit Equipped (FUE) no later than 2030 are encouraged to full identify their interest and capabilities in accordance with the requirements,” within 15 days after publication of the pre-solicitation. Such a vendor would need to deliver a preliminary design review in FY22, start building prototype aircraft in the third quarter of FY23 and eight production aircraft by 2030. Vendors must also prove they are able to build 24 aircraft per year at full-rate production. Those aircraft must be able to fly at 2,000 feet pressure altitude in 85 degree heat with a full payload that consists of 12 troops at 290 lbs each and four crew at 281 lbs each. When the draft RFP drops, it is likely to contain a schedule to deliver air vehicle prototypes and mission systems. The Army was debating between two schedule options to deliver prototypes by roughly mid-2026. The FLRAA program has strong support from Congress. This year's annual defense policy bill authorized $5 million in increased investment in FLRAA advanced component development and prototyping on top of the Army's nearly $648 million request. The FY21 spending bill has yet to go through conference committee, but both the House and Senate proposed additional funding for FLRAA. The House Appropriations Committee proposed a $20 million increase while the Senate Appropriations Defense Subcommittee proposed a $79 million addition. Lawmakers added $76 million in funding to FLRAA's top line in FY20 to drive down technical risk and speed up delivery through the competitive demonstration and risk reduction effort. In FY20, Congress cut $34 million from the Army's other future vertical lift effort — the FARA program — which threatened the service's ability to provide some of its government-furnished equipment to competitors chosen to build and fly prototypes. The Army is supplying its new Improved Turbine Engine Program engine, a 20mm gun, an integrated munitions launcher and its modular open-systems architecture. The Army has since shored up that funding, according to service aviation leadership. https://www.defensenews.com/land/2020/12/10/army-preps-for-competition-limited-to-bell-and-sikorsky-for-long-range-assault-helicopter/

  • USAF Inches Closer To KC-46 Vision System Decision

    September 16, 2020 | International, Aerospace

    USAF Inches Closer To KC-46 Vision System Decision

    Lee Hudson The head of the U.S. Air Force's mobility fleet needs more data from Boeing on the KC-46 Remote Vision System (RVS) upgrade plan to determine if an interim fix is worth taking the maintenance downtime. Boeing is upgrading the RVS to version 1.5, which is now renamed the enhanced RVS that the company promises will deliver sharper imaging, Air Mobility Command chief Gen. Jacqueline Van Ovost told reporters Sept. 14. “But the proof is in the pudding when it comes to whether or not it actually would provide additional operational capability or additional safety,” she said. Van Ovost and the head of the Pentagon's operational test and evaluation office met with Boeing on Sept. 4 for KC-46 briefings. Toward the end of September, Van Ovost expects a briefing on why the Pentagon should implement enhanced RVS at no cost to the Air Force. Air Force Research Laboratory personnel will participate in the discussion on whether the service should pursue enhanced RVS or wait until 2.0 comes online, she said. Boeing began flight testing the enhanced RVS in June, which includes numerous software changes and a few hardware updates. If the government opts not to deploy the upgrade, the fixes identified for RVS 1.5 will flow into the 2.0 version that is slated for fielding in the second half of 2023. “If the Air Force decides to deploy initial RVS enhancements we could provide aircraft with those during the second half of 2021 (calendar year),” Mike Hafer, KC-46 global sales and marketing at Boeing, said in a Sept. 15 statement. “The full suite of state-of-the-art enhancements, commonly known as RVS 2.0, should be installed in tankers we deliver starting in late 2023 or early in 2024.” https://aviationweek.com/shows-events/afa-air-space-cyber-conference/usaf-inches-closer-kc-46-vision-system-decision

All news