The new Air Force One just racked up its first cost overrun

By: Valerie Insinna

WASHINGTON — Boeing will have to pay $168 million out of pocket to cover increased costs on the VC-25B Air Force One replacement program, the company said Wednesday.

Boeing attributed the overrun to “engineering inefficiencies” caused by the impact of COVID-19, but Chief Financial Officer Greg Smith said the program remains on schedule with a projected delivery of the first VC-25B in 2024.

However, Boeing's quarterly report to the Security and Exchange Commission noted future risk to the program's cost and schedule as a result of the engineering challenges. “We believe these inefficiencies will result in staffing challenges, schedule inefficiencies and higher costs in the upcoming phases of the program,” the company stated in the report.

It was not immediately clear how work on the VC-25B program had been disrupted.

“That charge was really associated with COVID-19,” Smith told reporters in an April 29 phone call. “As we have folks working virtually — particularly on the engineering side — as well as that's gone, we certainly experienced some inefficiencies that has caused us to re-evaluate our estimates to complete those efforts. And that's essentially what you saw today in our results and the charge associated with that.”

Smith added that although the program team has done a “good job” of managing the program in the face of changes caused by the novel coronavirus pandemic and is “executing very well on many fronts,” Boeing could not mitigate the added cost to the program this financial quarter.

Air Force acquisition executive Will Roper said he spoke with Boeing Defense CEO Leanne Caret last night about the problem, but because the issue was “late breaking,” he referred detailed questions to the program office.

On Wednesday night, the Air Force released a statement that — like Boeing — attributed the cost increase to “engineering inefficiencies.”

Just two weeks ago, Roper praised the progress of the program, which used virtual tools to complete its critical design review in March and wrap up a modification readiness review in April. At the time, the program was on schedule with no disruptions due to COVID-19, he said then.

The Air Force One replacement drew considerable attention in 2016 after then-President-elect Donald Trump tweeted that the program was too expensive and should be cancelled unless the cost—then projected as more than $4 billion—came down. In 2018, the Air Force awarded Boeing a $3.9 billion fixed-price contract to modify two 747s into the VC-25B configuration.

" There has not been an increase to the $3.90B firm-fixed price contract with Boeing or the $5.3B VC-25B total acquisition cost," said Air Force spokeswoman Ann Stefanek.

Although the total price of the program is estimated to hit $5.3 billion once ancillary costs such as new hangars and revised technical manuals are included, the fixed-price ceiling on the $3.9 billion deal ensures that Boeing will have to pay for any cost growth incurred while building the two new Air Force Ones.

In February, Boeing began making structural changes to two Boeing 747s at its facility in San Antonio, Texas — paving the way for those jets to become VC-25Bs. The jets will also receive upgrades including enhanced electrical power, specialized communication systems, a medical facility, a customized executive interior and autonomous ground operations capabilities.

“As planned in the baseline schedule, the next phase of modification is on course to begin in June 2020,” Stefanek said.

https://www.defensenews.com/air/2020/04/29/the-new-air-force-one-just-racked-up-its-first-cost-overrun/

Sur le même sujet

  • Terma North America under contract with Lockheed Martin on the C-130J

    28 février 2020 | International, Aérospatial

    Terma North America under contract with Lockheed Martin on the C-130J

    Atlanta, February 26, 2020 - Lockheed Martin has awarded a $15M firm-fixed price contract to Terma North America to provide the ALQ-213A Defensive Aids Controller (DAC) and Range-Less Electronic Warfare Training (REWT) for the USAF HC-130J. The program allows integration of the Defensive System Suite to the HC-130J and provides the aircrew with the capability to perform realistic EW training while flying their mission. This provides a more flexible, cost-effective EW training compared to training on EW ranges. Terma has been providing EW Embedded Training systems for various military aircraft over the past 15 years with great success. REWT is latest version of advanced realistic EW training systems from Terma. Further the ALQ-213A based integration will provide the aircrew enhanced control of the HC-130J defensive systems and provisions that allow the addition of future systems to the Defensive Systems Suite. Lockheed Martin will be the prime contractor and will certify the Defensive Systems Suite capability on the HC-130J. “This program will provide the warfighters with capabilities that have long been sought after. The company leverages legacy products to ensure the safe return of pilots everywhere, so it's important that Terma deliver to the mutual mission of protecting those who use our products. It's important to focus on the overarching goal – to keep our warfighters out of harm's way, even when they fly into a potentially hostile environment,” said Lars Tolstrup, Business Development Director, Terma. Terma North America has provided the ALQ-213A DAC in the past for several international C-130J aircraft, where special defensive systems integration was required, under contracts with Lockheed Martin in Marietta. The company's primary focuses are providing advanced System Level Capabilities, hardware, integration, and sustainment to protect the warfighter. Because of the company legacy on these aircraft, Terma North America is honored to continue to provide hardware to the USAF C-130J fleet. Terma North America, Inc. Operating in the aeronautics, defense, and security sector, Terma North America supports customers and partners all over the world. Headquartered in Crystal City, Virginia, operating from two additional main offices in Georgia, Atlanta and Warner Robins, which hosts a production/repair facility. Terma NA also maintains remote locations, such as Crane, Indiana and Ft. Worth, Texas, where US team members work directly with customers on a regular basis. Terma Group Terma North America is part of the Denmark based high-tech Terma Group that develops products and systems for defense and non-defense security applications; including command and control systems, radar systems, self-protection systems for aircraft, space technology, and aerostructures for the aircraft industry. Follow us on www.terma.com Instagram Twitter Linkedin Youtube Media contact: Kasper Rasmussen T:+45 2022 6091 E:kar@terma.com View source version on Terma: https://www.terma.com/press/news-2020/terma-north-america-under-contract-with-lockheed-martin-on-the-c-130j/

  • New bill would establish AUKUS submarine training program

    17 juin 2022 | International, Naval

    New bill would establish AUKUS submarine training program

    A new training program would enroll young Australian naval officers in U.S. nuclear propulsion and submarine officer schoolhouses, and then send them to sea on a U.S. boat, ahead of Australia developing and fielding its own nuclear-powered sub.

  • Les atouts des Rafale Marine pour l'opération Chammal

    7 décembre 2020 | International, Aérospatial

    Les atouts des Rafale Marine pour l'opération Chammal

    Le Dassault Rafale Marine déploiera la GBU-16 de 500kg à l'occasion de ce cinquième mandat de l'opération Chammal. CINQUIEME MANDAT Dans un mois et demi, le groupe aérien embarqué du porte-avions Charles-de-Gaulle sera à nouveau mobilisé au profit de l'opération Chammal, offrant une capacité appréciable, avec une vingtaine d'avions de combat Dassault Rafale Marine (quatre fois plus que d'habitude sur la base H5 avec l'Armée de l'Air et de l'Espace, (AAE) et E-2C Hawkeye. Ces Rafale Marine assurent le cinquième mandat sur place depuis 2014 : quatre ont été menés depuis le Charles de Gaulle et le cinquième à terre, durant l'arrêt technique majeur du porte-avions. Bombe GBU Cette fois, les chasseurs embarqués vont déployer une série d'atouts nouveaux. Ce sera le cas dans le domaine munitionnaire, ils pourront emporter la bombe GBU-16 de 500 kg offrant ainsi un spectre plus large qu'avant, à base de 250 kg (GBU-12, AASM) ou 1000 kg (GBU-24). Cette avancée est symptomatique du travail permanent de la chasse embarquée pour trouver les munitions les plus adaptées aux réalités opérationnelles. Rappelons que ses SEM avaient, en leur temps, déployé la GBU-49 sur le thé'tre afghan avant qu'elle n'apparaisse sur Mirage 2000D. De même, les ATL-2 disposent des GBU-12, GBU-51, GBU-58. Ciblage pour le missile MBDA Meteor Les Rafale Marine vont aussi pour la première fois déployer la nacelle de ciblage Talios le missile air-air à longue portée Meteor. L'AAE, qui vient de déployer ses premiers Rafale F3R en Jordanie, doit aussi, a priori avant la Marine, mettre en service le Talios sur ce thé'tre irako-syrien. Le Meteor de MBDA est, évidemment, dans le contexte troublé de la Méditerranée orientale, un game changer que les pays alliés pourront voir de près, notamment les Grecs, futurs clients du Rafale. https://www.air-cosmos.com/article/les-atouts-des-rafale-marine-pour-lopration-chammal-23945

Toutes les nouvelles