14 mai 2020 | International, Aérospatial

Some F-35 suppliers are having trouble delivering parts on schedule, and Turkey’s departure could make that worse

By:

WASHINGTON — Lockheed Martin's F-35 Joint Strike Fighter is on the verge of full-rate production, with a decision slated for early 2021. But a congressional watchdog group is concerned that as the company ramps up F-35 production, its suppliers are falling behind.

And those supply chain problems could get even worse as Turkish defense manufacturers are pushed out of the program, the Government Accountability Office said in a May 12 report.

According to the GAO, the number of F-35 parts delivered late skyrocketed from less than 2,000 in August 2017 to upward of 10,000 in July 2019.

The number of parts shortages per month also climbed from 875 in July 2018 to more than 8,000 in July 2019. More than 60 percent of that sum was concentrated among 20 suppliers, it said.

“To mitigate late deliveries and parts shortages — and deliver more aircraft on time — the airframe contractor has utilized methods such as reconfiguring the assembly line and moving planned work between different stations along the assembly line,” the GAO said.

“According to the program office, such steps can cause production to be less efficient, which, in turn, can increase the number of labor hours necessary to build each aircraft,” which then drives up cost, the GAO added.

Those problems could be compounded by Turkey's expulsion from the F-35 program, which was announced last year after the country moved forward with buying the Russian S-400 air defense system. Although Turkey financially contributed to the development of the F-35 as a partner in the program, the U.S. Defense Department has maintained that Turkey cannot buy or operate the F-35 until it gives up the S-400.

The Pentagon has also taken action to begin stripping Turkish industry from the aircraft's supply chain, a process that involves finding new companies to make 1,005 parts, some of which are sole-sourced by Turkish companies.

Ellen Lord, the Pentagon's undersecretary for acquisition and sustainment, had hoped to stop contracting with Turkish suppliers by March 2020, but in January she said that some contracts would extend through the year, according to Defense One.

While the Defense Department has found new suppliers to manufacture the parts currently made in Turkey, it is uncertain whether the price of those components will be more expensive. Furthermore, as of December 2019, the new production rates for 15 components were lagging behind that of the legacy Turkish producers.

“According to program officials, some of these new parts suppliers will not be producing at the rate required until next year, as roughly 10 percent are new to the F-35 program,” the GAO said.

“Airframe contractor representatives stated it would take over a year to stand up these new suppliers, with lead times dependent on several factors, such as part complexity, quantity, and the supplier's production maturity. In addition, these new suppliers are required to go through qualification and testing to ensure the design integrity for their parts.”

The F-35 Joint Program Office disagreed with the GAO's recommendation to provide certain information to Congress ahead of the full-rate production decision, including an evaluation of production risks and a readiness assessment of the suppliers that are replacing Turkish companies.

In its statement, the JPO said it is already providing an acceptable number of updates on the program's readiness for full-rate production.

Hard times for the F-35's engine supplier

Not all F-35 production trends reported by the GAO were bad for the aircraft. Since 2016, Lockheed has made progress in delivering a greater proportion of F-35s on schedule, with 117 of 134 F-35s delivered on time in 2019.

However, one of the biggest subsystems of the F-35 — the F135 engine produced by Pratt & Whitney — drifted in the opposite direction, with a whopping 91 percent of engines delivered behind schedule.

At one point in 2019, Pratt & Whitney stopped deliveries of the F135 for an unspecified period due to test failures, which also contributed to the reduction of on-time deliveries.

According to the Defense Contracts Management Agency, “there have been 18 engine test failures in 2019, which is eight more than in 2018, each requiring disassembly and rework,” the GAO wrote. “To address this issue, the engine contractor has developed new tooling for the assembly line and has established a team to identify characteristics leading to the test failures. Plans are also in place for additional training for employees.”

https://www.defensenews.com/air/2020/05/12/some-f-35-suppliers-are-having-trouble-delivering-parts-on-schedule-and-turkeys-departure-could-make-that-worse/

Sur le même sujet

  • Comment les drones collaboratifs vont bouleverser le marché des avions de combat ?

    18 octobre 2022 | International, Aérospatial

    Comment les drones collaboratifs vont bouleverser le marché des avions de combat ?

    Depuis son arrivé sur le marché international des avions de combat il y a une quinzaine d'années, le F-35 Lighting II de Lockheed-Martin s'est largement taillé la part du lion lors des compétitions internationales, avec des commandes fermes émanant de pas moins de 14 forces aériennes en dehors des Etats-Unis. Et la dynamique ne semble pas vouloir se tarir, avec de nombreux autres pays, donc 5 pays européens (Allemagne, Espagne, Grèce, Republique Tchèque et Roumanie) ayant annoncé leur intention de s'en équiper à court ou moyen terme. Dans de nombreux cas, l'appareil américain s'est imposé au terme d'une compétition l'opposant à d'autres chasseurs américains et européens, notamment le Rafale français, le Gripen suédois, le Typhoon européen ou encore le Super Hornet de Boeing. Lors de chacune d'elles, le Lighting II fut déclaré vainqueur, notamment du fait de sa conception plus récente, mais également de sa furtivité, sachant également que le poids politique et militaire des Etats-Unis jouèrent à plein dans de nombreux cas.

  • The Army wants to build a better signals intelligence force

    23 juillet 2018 | International, C4ISR

    The Army wants to build a better signals intelligence force

    By: Mark Pomerleau The Army's top intelligence official signed the service's new signals intelligence strategy July 16, a move that defense leaders believe leaves the Army better situated to better fight despite electronic warfare and cyber attacks. The new strategy ensures "our readiness to provide timely and relevant SIGINT-support [and meet] the commander's information needs in a large scale combat operation against a sophisticated adversary,” Lt. Gen. Scott Berrier, said July 18 during an event on Capitol Hill hosted by the Association of Old Crows. Officials say the integration of SIGINT, electronic warfare and cyber is critical from a material, organization and doctrinal perspective. “Not only will our four lines of effort improve our SIGINT corps' capabilities and relevance in the face of rapid changes in the global security environment, it will also enable our electronic warfare and cyberspace effort to meet new challenges,” Berrier said. The four initiatives in the new strategy include: - Organizing and building the Army SIGINT force, - Educating the force, - Equipping the force, and - Developing doctrine. The new strategy increases the Army's ability to collect intelligence against peer adversaries, such as China and Russia, and provides a firm foundation for successful electronic warfare and cyber operations, Berrier said. A key component of the convergence includes the new Terrestrial Layer System (TLS), a SIGINT/EW system projected to be fielded on vehicles and used by new military intelligence-electronic warfare (MI-EW) companies the Army is working to stand up. The Army wants SIGINT, electronic warfare and cyber systems on the same platforms in the air and ground domain, Maj. Gen. Robert Walters, commander of the Intelligence Center of Excellence, said at the event. These systems, Berrier said, should be able to not only sense the environment but employ some type of action such as electronic attack or cyber capability. Why converge? Officials have stressed repeatedly in the last year the need for colleagues in similar disciplines throughout the Army to stay in touch and reap the mutually beneficial equities on behalf of commanders in the field. Lt. Gen. Stephen Fogarty, the head of Army Cyber Command, said commanders shouldn't have to have something explained to them by the EW guy, the SIGINT guy and then the cyber guy. “What we decided is there's a better way, we have to pull it all together” for the commander, he said at the event. “We're going to have to work together because we all operate in the same space. And so do we really need three separate tools to plan operations in the spectrum? My argument would be no.” From an organizational perspective, the 29 series electronic warfare personnel will have deep knowledge in both cyber and electromagnetic spectrum operations. On the materiel side, especially with programs like the Terrestrial Layer System, the cyber and intel community are meeting regularly to integrate their requirements, officials said. In addition, Maj. Gen. John Morrison, commander of the Cyber Center of Excellence, told reporters in June that the Intelligence Center of Excellence is working with the Cyber Center to help ensure integrated formation and integrated capabilities. https://www.c4isrnet.com/intel-geoint/2018/07/19/the-army-wants-to-build-a-better-signals-intelligence-force/

  • Israel, Pressed By US, Blocks First Big Chinese Deal

    27 mai 2020 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

    Israel, Pressed By US, Blocks First Big Chinese Deal

    By ARIE EGOZIon May 26, 2020 at 5:26 PM TEL AVIV: The strict U.S warning to Israel to limit ties with China has its first result as the Chinese failed to win a tender for the construction of the giant desalination plant in central Israel. The Palmahim site is in close proximity to Israel's missile test and satellite launch facility. The Soreq 2 facility, with the capability to process 200 million cubic meters of water per year, is expected to be the largest of its kind in the world, increasing the state's desalination capacity by about 35%. The new desalination plant joins five facilities already operating in Israel. Two weeks after US Secretary of State Mike Pompeo met with Prime Minister Benjamin Netanyahu and warned against further Chinese involvement in projects in Israel the Chinese company lost and an Israeli company, IDE. That may lead to a confrontation with the Chinese. Two weeks ago, Netanyahu told Pompeo that the issue was under discussion by the Foreign Investment Committee at the Treasury. The US fears Chinese investments could create dependencies on China's companies and countries, and is working to prevent them. The next challenge: the Chinese and the power companies. In coming days, a decision will be made whether to award the Chinese government company China Harbor's bid for the power plant of Ramat Hovav, part of the huge reform of Israel's once government-owned electricity sector. “The fact that the (Pompeo) visit takes place in these problematic times proves its urgency ” an Israeli source told BD. Pompeo came to Israel with a very strict message – stop all Chinese investment in Israel, either in high tech companies or infrastructure. Israeli officials said the message relayed during Pompeo's visit included a very specific political warning – Israel must stop any action that strengthens the Chinese Communist Party, even if that means canceling planned projects. For context, think of the numerous times President Trump has called the coronavirus the Chinese virus and blamed China for supposedly hiding the truth about the virus' origins. https://breakingdefense.com/2020/05/israel-pressed-by-us-blocks-first-big-chinese-deal/

Toutes les nouvelles