14 mai 2020 | International, Aérospatial

Some F-35 suppliers are having trouble delivering parts on schedule, and Turkey’s departure could make that worse

By:

WASHINGTON — Lockheed Martin's F-35 Joint Strike Fighter is on the verge of full-rate production, with a decision slated for early 2021. But a congressional watchdog group is concerned that as the company ramps up F-35 production, its suppliers are falling behind.

And those supply chain problems could get even worse as Turkish defense manufacturers are pushed out of the program, the Government Accountability Office said in a May 12 report.

According to the GAO, the number of F-35 parts delivered late skyrocketed from less than 2,000 in August 2017 to upward of 10,000 in July 2019.

The number of parts shortages per month also climbed from 875 in July 2018 to more than 8,000 in July 2019. More than 60 percent of that sum was concentrated among 20 suppliers, it said.

“To mitigate late deliveries and parts shortages — and deliver more aircraft on time — the airframe contractor has utilized methods such as reconfiguring the assembly line and moving planned work between different stations along the assembly line,” the GAO said.

“According to the program office, such steps can cause production to be less efficient, which, in turn, can increase the number of labor hours necessary to build each aircraft,” which then drives up cost, the GAO added.

Those problems could be compounded by Turkey's expulsion from the F-35 program, which was announced last year after the country moved forward with buying the Russian S-400 air defense system. Although Turkey financially contributed to the development of the F-35 as a partner in the program, the U.S. Defense Department has maintained that Turkey cannot buy or operate the F-35 until it gives up the S-400.

The Pentagon has also taken action to begin stripping Turkish industry from the aircraft's supply chain, a process that involves finding new companies to make 1,005 parts, some of which are sole-sourced by Turkish companies.

Ellen Lord, the Pentagon's undersecretary for acquisition and sustainment, had hoped to stop contracting with Turkish suppliers by March 2020, but in January she said that some contracts would extend through the year, according to Defense One.

While the Defense Department has found new suppliers to manufacture the parts currently made in Turkey, it is uncertain whether the price of those components will be more expensive. Furthermore, as of December 2019, the new production rates for 15 components were lagging behind that of the legacy Turkish producers.

“According to program officials, some of these new parts suppliers will not be producing at the rate required until next year, as roughly 10 percent are new to the F-35 program,” the GAO said.

“Airframe contractor representatives stated it would take over a year to stand up these new suppliers, with lead times dependent on several factors, such as part complexity, quantity, and the supplier's production maturity. In addition, these new suppliers are required to go through qualification and testing to ensure the design integrity for their parts.”

The F-35 Joint Program Office disagreed with the GAO's recommendation to provide certain information to Congress ahead of the full-rate production decision, including an evaluation of production risks and a readiness assessment of the suppliers that are replacing Turkish companies.

In its statement, the JPO said it is already providing an acceptable number of updates on the program's readiness for full-rate production.

Hard times for the F-35's engine supplier

Not all F-35 production trends reported by the GAO were bad for the aircraft. Since 2016, Lockheed has made progress in delivering a greater proportion of F-35s on schedule, with 117 of 134 F-35s delivered on time in 2019.

However, one of the biggest subsystems of the F-35 — the F135 engine produced by Pratt & Whitney — drifted in the opposite direction, with a whopping 91 percent of engines delivered behind schedule.

At one point in 2019, Pratt & Whitney stopped deliveries of the F135 for an unspecified period due to test failures, which also contributed to the reduction of on-time deliveries.

According to the Defense Contracts Management Agency, “there have been 18 engine test failures in 2019, which is eight more than in 2018, each requiring disassembly and rework,” the GAO wrote. “To address this issue, the engine contractor has developed new tooling for the assembly line and has established a team to identify characteristics leading to the test failures. Plans are also in place for additional training for employees.”

https://www.defensenews.com/air/2020/05/12/some-f-35-suppliers-are-having-trouble-delivering-parts-on-schedule-and-turkeys-departure-could-make-that-worse/

Sur le même sujet

  • Australia selects Boeing Apache as next armed reconnaissance helicopter

    20 janvier 2021 | International, Aérospatial

    Australia selects Boeing Apache as next armed reconnaissance helicopter

    By: Nigel Pittaway MELBOURNE, Australia — Australia has selected Boeing's AH-64E Apache Guardian as it's next armed reconnaissance helicopter, replacing its Airbus Helicopters Tiger fleet under the Land 4503 program estimated to be worth AU$4-5 billion (U.S. $3–3.8 billion). The selection of the Apache follows the release of a request for information in July 2019 and was announced by Australian Defence Minister Linda Reynolds on Friday. The RFI called for 29 helicopters, with 24 to be based at a single location with two operational armed recon helo squadrons, and a five for training Army pilots and battle captains at the Australian Army Aviation Training Centre at Oakey, Queensland. The two operational Tiger squadrons are currently based in Darwin in the Northern Territory as part of the 1st Aviation Regiment. The RFI also stipulated an initial operational capability, represented by 12 helicopters, in 2026; and final operational capability with all 29 aircraft two years later. In addition to Boeing, Bell responded to the RFI with its AH-1Z Viper, and Airbus Helicopters with an updated Tiger. “The Apache Guardian is the most lethal, most survivable and lowest-risk option, meeting all of [the Department of] Defence's capability, through-life support, security and certification requirements,” Reynolds said. “By pursuing a proven and low-risk system offered by the Apache, [the Department of] Defence will avoid the ongoing cost and schedule risk typically associated with developmental platforms.” The Tiger was introduced to service in December 2004 but suffered poor availability rates and high ownership costs early in its career, before a remediation plan was implemented by the Department of Defence and industry around 2016. Reynolds said the issues with the Tiger fleet and other Australian military rotary-wing projects had informed the strategy to seek a proven and mature replacement. The decision to acquire the Apache was made under the Australian government's “Smart Buyer” policy, which allows for sole-source selection without a competition if there is a clear preference for a particular platform. A spokesman for Australia's Department of Defence said the government will now consider the acquisition of mission sensors and mission-relevant equipment, including the AN/APG-78 Longbow fire control radar, but no specific configuration or numbers of radars have been revealed. The spokesman said the department will continue to consider options to improve upon the Apache that maximize opportunities for the local defense industry, including warehousing services, training development, engineering services and maintenance, and repair and overhaul. “Additionally, early detailed transition planning will be conducted to ensure effective management of the skilled workforce, across [the Department of] Defence and industry, as [the Department of] Defence transitions the Tiger to the Apache,” the spokesman said. Boeing said the AH-64E provides Australia with a fully integrated, battle-proven capability and will continue to expand its industry capability and supply chain in Australia. “Apache is supported by an active production line and a U.S. Army modernization plan through to the late 2040s, thereby ensuring the platform remains the leading attack and reconnaissance capability through to 2050 and beyond,” a company spokesperson said. https://www.defensenews.com/global/asia-pacific/2021/01/19/australia-selects-boeing-apache-as-next-armed-reconnaissance-helicopter

  • Joby’s air taxis to help US Air Force usher in electric aviation era

    25 septembre 2023 | International, Aérospatial

    Joby’s air taxis to help US Air Force usher in electric aviation era

    The vehicles will first be flown remotely to shuttle cargo around Edwards Air Force Base, followed by human pilots and passengers next year.

  • Watchkeeper life ends in new wave of UK defence cuts - Army Technology

    21 novembre 2024 | International, Terrestre

    Watchkeeper life ends in new wave of UK defence cuts - Army Technology

    The UK Defence Secretary, John Healey, has cut the enduring Watchkeeper tactical UAV programme along with several other programmes.

Toutes les nouvelles