May 14, 2020 | International, Aerospace

Some F-35 suppliers are having trouble delivering parts on schedule, and Turkey’s departure could make that worse

By:

WASHINGTON — Lockheed Martin's F-35 Joint Strike Fighter is on the verge of full-rate production, with a decision slated for early 2021. But a congressional watchdog group is concerned that as the company ramps up F-35 production, its suppliers are falling behind.

And those supply chain problems could get even worse as Turkish defense manufacturers are pushed out of the program, the Government Accountability Office said in a May 12 report.

According to the GAO, the number of F-35 parts delivered late skyrocketed from less than 2,000 in August 2017 to upward of 10,000 in July 2019.

The number of parts shortages per month also climbed from 875 in July 2018 to more than 8,000 in July 2019. More than 60 percent of that sum was concentrated among 20 suppliers, it said.

“To mitigate late deliveries and parts shortages — and deliver more aircraft on time — the airframe contractor has utilized methods such as reconfiguring the assembly line and moving planned work between different stations along the assembly line,” the GAO said.

“According to the program office, such steps can cause production to be less efficient, which, in turn, can increase the number of labor hours necessary to build each aircraft,” which then drives up cost, the GAO added.

Those problems could be compounded by Turkey's expulsion from the F-35 program, which was announced last year after the country moved forward with buying the Russian S-400 air defense system. Although Turkey financially contributed to the development of the F-35 as a partner in the program, the U.S. Defense Department has maintained that Turkey cannot buy or operate the F-35 until it gives up the S-400.

The Pentagon has also taken action to begin stripping Turkish industry from the aircraft's supply chain, a process that involves finding new companies to make 1,005 parts, some of which are sole-sourced by Turkish companies.

Ellen Lord, the Pentagon's undersecretary for acquisition and sustainment, had hoped to stop contracting with Turkish suppliers by March 2020, but in January she said that some contracts would extend through the year, according to Defense One.

While the Defense Department has found new suppliers to manufacture the parts currently made in Turkey, it is uncertain whether the price of those components will be more expensive. Furthermore, as of December 2019, the new production rates for 15 components were lagging behind that of the legacy Turkish producers.

“According to program officials, some of these new parts suppliers will not be producing at the rate required until next year, as roughly 10 percent are new to the F-35 program,” the GAO said.

“Airframe contractor representatives stated it would take over a year to stand up these new suppliers, with lead times dependent on several factors, such as part complexity, quantity, and the supplier's production maturity. In addition, these new suppliers are required to go through qualification and testing to ensure the design integrity for their parts.”

The F-35 Joint Program Office disagreed with the GAO's recommendation to provide certain information to Congress ahead of the full-rate production decision, including an evaluation of production risks and a readiness assessment of the suppliers that are replacing Turkish companies.

In its statement, the JPO said it is already providing an acceptable number of updates on the program's readiness for full-rate production.

Hard times for the F-35's engine supplier

Not all F-35 production trends reported by the GAO were bad for the aircraft. Since 2016, Lockheed has made progress in delivering a greater proportion of F-35s on schedule, with 117 of 134 F-35s delivered on time in 2019.

However, one of the biggest subsystems of the F-35 — the F135 engine produced by Pratt & Whitney — drifted in the opposite direction, with a whopping 91 percent of engines delivered behind schedule.

At one point in 2019, Pratt & Whitney stopped deliveries of the F135 for an unspecified period due to test failures, which also contributed to the reduction of on-time deliveries.

According to the Defense Contracts Management Agency, “there have been 18 engine test failures in 2019, which is eight more than in 2018, each requiring disassembly and rework,” the GAO wrote. “To address this issue, the engine contractor has developed new tooling for the assembly line and has established a team to identify characteristics leading to the test failures. Plans are also in place for additional training for employees.”

https://www.defensenews.com/air/2020/05/12/some-f-35-suppliers-are-having-trouble-delivering-parts-on-schedule-and-turkeys-departure-could-make-that-worse/

On the same subject

  • Romania eyes new maritime drone to counter Russia

    May 8, 2019 | International, Aerospace, Naval

    Romania eyes new maritime drone to counter Russia

    By: Joe Gould NATIONAL HARBOR — The Romanian Navy is exploring the purchase of a new drone for its expansion and modernization plans, the chief of the Romanian Naval Forces said Monday. Amid growing tensions with Russia on the Black Sea, the service is looking at a “totally new” unmanned aerial system for the maritime and riverine domain, Vice Adm. Alexandru Mirsu said at the Sea-Air-Space forum here. The capability would be used by Romania's Danube flotilla and for coastal surveillance, operated from the shoreline, Mirsu said. He did not provide a timeframe or a budget for the possible acquisition. Plans are underway to buy four new multipurpose corvettes as the core of the Romanian navy, and to modernize its Type 22 frigates. Also expected are purchases of new coastal missile batteries and three new submarines — all part of Romania's commitment to spending 2 percent of its gross domestic product on defense for the next decade. The idea is to expand Romania's presence in the Black Sea, the Mediterranean and elswhere as needed by allies, and to maintain a submarine program beyond 2030. Mirsu has previously said the submarines are needed to ensure Romania's operational capacities in the Black Sea, as the one Kilo-class submarine does not meet that need. Its Delfinul submarine was reportedly withdrawn from service and was being used for training purposes. Mirsu also pointed to “a new iron curtain” of Russian anti access/area denial (A2/AD) hubs in Kaliningrad, Sevastopol and Syria. He lauded major multinational exercises and NATO operations on the Black Sea for sending a message that the Black Sea is open, and an international body of water. Romania led NATO's Poseidon antisubmarine exercise on the Black Sea in March. Also notable, the Romanian-led Sea Shield in April involved 20 ships and crews from Romania, Bulgaria, Canada, Greece, the Netherlands and Turkey, all working with maritime patrol aircraft from the U.S. and Turkey. https://www.defensenews.com/digital-show-dailies/navy-league/2019/05/07/romania-eyes-new-maritime-drone-to-counter-russia

  • SCAF : Airbus implique les start-ups dans le projet en Allemagne

    December 10, 2020 | International, Aerospace

    SCAF : Airbus implique les start-ups dans le projet en Allemagne

    Airbus annonce la conclusion de la phase pilote de l'initiative « Innovations for FCAS » qui vise à impliquer les acteurs allemands non traditionnels de la défense - des start-ups, des petites et moyennes entreprises et des instituts de recherche dans le développement de l'avion de combat du futur (SCAF). Cette initiative lancée en avril 2020 a été financée par le ministère allemand de la Défense. Lors de la phase pilote, 18 PME et start-ups ont ainsi travaillé sur 14 projets en étroite collaboration avec Airbus pour obtenir des résultats concrets tels qu'un lanceur de véhicule sans pilote, un démonstrateur cloud de combat sécurisé ou encore un démonstrateur d'intelligence artificielle appliquée à l'analyse des fréquences radio. EasyBourse du 9 décembre 2020

  • Colombian Air Force to buy more T-6C training aircraft

    January 11, 2023 | International, Aerospace

    Colombian Air Force to buy more T-6C training aircraft

    The negotiations are part of an effort to acquire up to 24 of the trainers, unveiled by the Defense Ministry in December.

All news