22 septembre 2020 | International, Naval

Is the US Navy winning the war on maintenance delays?

WASHINGTON — The U.S. Navy, beset by maintenance delays, is making progress on getting its ships out of the shipyards on time, fleet officials say.

Over the past three years, the Navy is on track to more than double the percentage of ships getting out of maintenance on time, key to the service's efforts to make deployments more sustainable for its ships and sailors, Capt. Dave Wroe, U.S. Fleet Forces Command's deputy fleet readiness officer told Defense News in an email.

“On-time ship maintenance availability completion rates in private shipyards improved from 24% in FY18 to 37% in FY19,” Wroe said. “Current performance trends in FY20 are projected to be 65%.”

The improvement is a sign that the Navy may be turning the corner on a fight to restore readiness from its nadir in the early part of the last decade, when the Navy was running ragged filling unsustainable requirements for forces around the globe.

Getting ships through their maintenance cycles on time is the linchpin of what the Navy calls its “optimized fleet response plan,” which is the system through which the Navy generates deployable ships that are maintained, manned and trained.

Late last year and again in January, Chief of Naval Operations Adm. Michael Gilday told audiences that repeated delays in the shipyards was undermining the Navy's Optimized Fleet Response Plan, and turning that around was vital.

“We are getting 35 to 40 percent of our ships out of maintenance on time: that's unacceptable,” Gilday said at the USNI Defense Forum in December. “I can't sustain the fleet I have with that kind of track record.”

A recent Government Accountability Office report found that between 2015 and 2019, only 25 percent of the Navy's maintenance periods for ships and submarines.

Improvements

Getting out of that hole has been difficult for a number of reasons: High operational demand for Navy forces makes planning maintenance difficult, and inevitably when the ships go into maintenance after years of hard use, workers discover more work that needs to be done, creating delays. And those delays make executing OFRP difficult, Wroe said.

“OFRP provides the construct to best assess and optimize readiness production — down to a unit level — taking into account all the various competing factors to produced Navy readiness,” Wroe said. “Bottom line: OFRP helps mitigate fundamental points of friction, such as shipyard capacity and manning gaps at sea — but in itself doesn't solve key degraders like depot level maintenance delays and extensions.”

But some key factors in the delays have been identified and the Navy is working to mitigate them, Fleet Forces Commander Adm. Chris Grady said this week at this week's Fleet Maintenance and Modernization Symposium.

One area that has a tendency to drive delays is when workers discover things that need to be fixed, the fix may not cost much but the adjustment must go through an approval process that slows everything down. Those kinds of changes add up to about 70 percent of the so-called “growth work.”

Part of it is anticipating and building in ways to deal with growth work into every maintenance period, and the other part is making it easier to address small changes to the scope of the work, Grady said.

“When we began this initiative, cycle time for the small value changes averaged about 30 days,” he said “We're now at six and aim to bring it down further to only two days.”

Other things that have helped the problem has been bundling maintenance periods for ships, meaning that contractors bid on multiple ships to fix, and can plan hiring further out, Grady said. Additionally, improving base access for contractors has helped, as well.

“Last year, we averaged 110 days delayed per ship in private avails,” Grady said, using the short-hand term for “maintenance availability.”

“Things much better this year — even with COVID-19,” he continued. “We go from about one-third avails finishing on-time to two-thirds. That is great. But, again, each delay has real impact on our readiness, and we need to keep working together to do better.”

What happened?

Because the U.S. Navy is set up to meet standing presence requirements and missions around the world, it must cycle its ships through a system of tiered readiness.

That means ships go on deployment fully manned, trained and equipped. Then the ships come home, and after a period of sustained readiness where the ship can be redeployed, it goes into a reduced readiness status while undergoing maintenance. Following maintenance, the ship and crew goes into a training cycle for another deployment as an individual unit, then as a group, then returns to deployment.

The whole cycle takes 36 months: Rinse and repeat.

OFRP was designed in the 2013-2014 time-frame when the Navy was deploying well beyond its means, with carrier strike groups and amphibious ready groups going out for nine-to-10 months at a time.

The excess use wore hard on the ships and sailors who manned them and put more wear on the hulls than they were designed to sustain. That meant that when ships went in for maintenance they were more broken than they were supposed to be, and funding to fix them was hampered by spending cuts.

For nuclear ships — submarines and aircraft carriers — the funding cuts were a double whammy of work stoppages and furloughs that contributed to a wave of retirements in the yards, meaning the public yards were understaffed and had to hire and train new workers. Work took longer, throwing a wrench into an already complicated system of generating readiness.

All that added up to significant delays in getting ships through their maintenance cycles and contributed to astonishing delays in attack submarine maintenance especially.

What OFRP was meant to do was create a system whereby the Navy could meet combatant commander demands but not break the system. That meant that the Navy would generate as much readiness as it possibly could but that the demand would have to be limited to what the Navy could reasonably maintain, man, train and equip.

But getting to that system has been immensely difficult because of the deep hole the Navy dug meeting requirements that well outstripped funding and supply.

For example, there was a two year period when the service was forced to supply two carrier strike groups to the Arabian Gulf at all times, a requirement only canceled when automatic across-the-board spending cuts in 2013 made it impossible for the Navy to fund the two-carrier requirement.

Adding to the difficulty: some of OFRP's founding requirements were nigh impossible to pull off. One was that the all the ships in group would go into and come out of their maintenance availabilities on time and together. Another was that a group would go into the first phase of their training, the so-called basic phase right after coming out of maintenance, fully manned.

Both have been immensely difficult to pull off. But Fleet Forces, headed then by OFRP architect Adm. Phil Davidson, was given ample warning that those assumptions would be difficult to achieve.

Then-NAVSEA head Vice Adm. William Hilarides told USNI News in January 2015 that getting ships to come out of the yards simultaneously would be hard.

“The challenge to me is, let's say you want four destroyers in a battle group, all to come out at the same time in one port? That's a real challenge,” Hilarides told USNI News.

The current head of NAVSEA, who at the time was in charge of the Regional Maintenance Center enterprise, backed up his boss to USNI News, saying it would be particularly challenging in places with less infrastructure.

“Your big rub there is, the challenge of OFRP is ... all those ships [in a carrier strike group], they go through maintenance together, they go through training together and they deploy together,” said then-Rear Adm. William Galinis. "So, what our challenge is, is to be able to take all that work from all those ships and try to schedule it for roughly about the same time, and to get all that work done on time. So that's our challenge.

“Now, in a port like Norfolk or San Diego, we have big shipyards, a lot of people, a lot of ships. You can kind of absorb that type of workload. When you go to Mayport, they've got like 10 ships down there [and typically cannot work on more than one or two destroyers at a time.],” he told USNI.

Galinis said that Fleet Forces would have to be responsive to the shipyards because at least that way they could plan for delays.

“They know if they give us all this work at one time, it's going to go long anyway,” he told USNI. “So they'd rather be able to plan that and at least know when they're getting the ship back, as opposed to, ‘nope, we're not going to talk to you, you've got to go do it,' and then the ships go long because we don't have enough people to do the work.”

Fleet Forces Command has been reviewing its assumptions this year and is preparing to release a revised OFRP instruction, but the core is likely to remain the same. In any case, Wroe said in the email, it was always going to take a long time to dig out of the hole the Navy found itself in when OFRP was implemented fully in 2015.

“It was clear at the inception of OFRP, and remains clear today, that it will take the entire 2015-2025 period to recover readiness and establish stable readiness production,” Wroe said. “That makes sense when readiness production is planned over 9-years and large blocks of time have already been scheduled for depot maintenance periods.”

Ultimately, if the process of OFRP is funded correctly and ships can get out of maintenance on time, it's a sound way of moving forward, Fleet Forces Commander Grady told the audience this week.

“My bottom line here is that, as a process, OFRP works,” he said. “If we are looking where to improve upon it, each of these studies came to the same conclusion: the biggest inhibitor to fleet readiness is maintenance and modernization performance in the shipyards. We simply must get better, and I know you share my concern.”

https://www.defensenews.com/naval/2020/09/19/is-the-us-navy-winning-the-war-on-maintenance/

Sur le même sujet

  • U.S. Defense Programs To Watch

    8 juin 2021 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

    U.S. Defense Programs To Watch

  • Saab receives order from NATO for RBS 70 Bolide missiles

    27 décembre 2023 | International, Terrestre

    Saab receives order from NATO for RBS 70 Bolide missiles

    The order value amounts to SEK 350 million and deliveries will take place during 2027.

  • DoD unveils electromagnetic spectrum superiority strategy

    30 octobre 2020 | International, C4ISR

    DoD unveils electromagnetic spectrum superiority strategy

    Mark Pomerleau WASHINGTON — The U.S. Department of Defense released its highly anticipated electromagnetic spectrum superiority strategy Thursday, aimed at guiding how the department will develop capabilities as well as partner on and pursue readiness within the spectrum to gain an edge on sophisticated adversaries. In recent years, U.S. adversaries have sought high-tech methods to deny the electromagnetic spectrum, on which American forces often rely. These methods include jamming or spoofing communications, radars and munitions. “The Nation has entered an age of warfighting wherein U.S. dominance in air, land, sea, space, cyberspace, and the electromagnetic spectrum (EMS) is challenged by peer and near peer adversaries,” the strategy stated. “These challenges have exposed the cross-cutting reliance of U.S. Forces on the EMS, and are driving a change in how the DoD approaches activities in the EMS to maintain an all-domain advantage." "This jeopardizes the U.S. military's ability to sense, command, control, communicate, test, train, protect, and project force effectively. Without the capabilities to assert EMS superiority, the nation's economic and national security will be exposed to undue and significant risk.” The strategy lists five strategic goals, each delving deeper into subordinate objectives. They include: Develop superior EMS capabilities. Evolve to an agile and fully integrated EMS infrastructure. Pursue total force readiness in the EMS. Secure enduring partnerships for EMS advantage. Establish effective EMS governance. “The new strategy will have wide-ranging impacts across the DoD. It will shape the future of the department, influencing how the DoD makes decisions on how best to design, resource and implement EMS concepts as a new foundation for multidomain war fighting,” a defense official said Oct. 29 during a briefing to reporters on the strategy on background because the DoD would not let them speak on-the-record. The strategy pulls from previous concepts and initiatives such as the 2013 Electromagnetic Spectrum Strategy and the 2017 electronic warfare strategy. However, since those documents were devised, the operational environment has become more complex. “The primary focus is a holistic approach to electromagnetic spectrum management and electromagnetic warfare,” the official said regarding departures from previous strategies. In the past, the official said, some of those activities were siloed while the new strategy articulates freedom of action within the spectrum through a more holistic approach. The strategy also noted that the DoD is transitioning from its definition that electronic warfare is separate from spectrum management to a more unified approach of electromagnetic spectrum operations, or EMSO. The Joint Staff updated its doctrine document in May governing electronic warfare, shifting to EMSO. The official said some of the particular technologies the department is looking for include dynamic spectrum-sharing technologies that need to incorporate sensing, accessing, sharing and maneuvers, frequency agility, frequency diversity, tools that minimize an EMS footprint, tools to reduce vulnerability detection, and resiliency against radio frequency-enabled cyberattacks. “We're also emphasizing modular, open-systems approaches, software designed systems, [a] more platform-agnostic approach instead of defined platforms as well as being multifunction,” the official said. The strategy paints broad strokes for what's desired and required beneath each strategic goal. However, the Pentagon is still working on a formal implementation plan to ingrain them within the department and armed services. Within 180 days of being officially signed, the senior designated official, who is currently the vice chairman of the Joint Chiefs of Staff, will create a road map and implementation plan alongside the Electromagnetic Spectrum Operations Cross-Functional Team. A defense official said the way forward should be finalized by March 2021. That plan will have a series of tasks aligned to the five goals. What's more, the implementation team will identify risks to the department and outline trade-offs that must be made against other priorities within the Pentagon, the official said. “As part of the implementation plan, we are trying to set the conditions to make the appropriate trades that are going to be necessary with all the different priorities and the modernization efforts that are going to be required as part of this strategy execution,” the official said. https://www.c4isrnet.com/electronic-warfare/2020/10/29/dod-unveils-electromagnetic-spectrum-superiority-strategy/

Toutes les nouvelles