28 juillet 2024 | International, Terrestre
22 septembre 2020 | International, Naval
WASHINGTON — The U.S. Navy, beset by maintenance delays, is making progress on getting its ships out of the shipyards on time, fleet officials say.
Over the past three years, the Navy is on track to more than double the percentage of ships getting out of maintenance on time, key to the service's efforts to make deployments more sustainable for its ships and sailors, Capt. Dave Wroe, U.S. Fleet Forces Command's deputy fleet readiness officer told Defense News in an email.
“On-time ship maintenance availability completion rates in private shipyards improved from 24% in FY18 to 37% in FY19,” Wroe said. “Current performance trends in FY20 are projected to be 65%.”
The improvement is a sign that the Navy may be turning the corner on a fight to restore readiness from its nadir in the early part of the last decade, when the Navy was running ragged filling unsustainable requirements for forces around the globe.
Getting ships through their maintenance cycles on time is the linchpin of what the Navy calls its “optimized fleet response plan,” which is the system through which the Navy generates deployable ships that are maintained, manned and trained.
Late last year and again in January, Chief of Naval Operations Adm. Michael Gilday told audiences that repeated delays in the shipyards was undermining the Navy's Optimized Fleet Response Plan, and turning that around was vital.
“We are getting 35 to 40 percent of our ships out of maintenance on time: that's unacceptable,” Gilday said at the USNI Defense Forum in December. “I can't sustain the fleet I have with that kind of track record.”
A recent Government Accountability Office report found that between 2015 and 2019, only 25 percent of the Navy's maintenance periods for ships and submarines.
Improvements
Getting out of that hole has been difficult for a number of reasons: High operational demand for Navy forces makes planning maintenance difficult, and inevitably when the ships go into maintenance after years of hard use, workers discover more work that needs to be done, creating delays. And those delays make executing OFRP difficult, Wroe said.
“OFRP provides the construct to best assess and optimize readiness production — down to a unit level — taking into account all the various competing factors to produced Navy readiness,” Wroe said. “Bottom line: OFRP helps mitigate fundamental points of friction, such as shipyard capacity and manning gaps at sea — but in itself doesn't solve key degraders like depot level maintenance delays and extensions.”
But some key factors in the delays have been identified and the Navy is working to mitigate them, Fleet Forces Commander Adm. Chris Grady said this week at this week's Fleet Maintenance and Modernization Symposium.
One area that has a tendency to drive delays is when workers discover things that need to be fixed, the fix may not cost much but the adjustment must go through an approval process that slows everything down. Those kinds of changes add up to about 70 percent of the so-called “growth work.”
Part of it is anticipating and building in ways to deal with growth work into every maintenance period, and the other part is making it easier to address small changes to the scope of the work, Grady said.
“When we began this initiative, cycle time for the small value changes averaged about 30 days,” he said “We're now at six and aim to bring it down further to only two days.”
Other things that have helped the problem has been bundling maintenance periods for ships, meaning that contractors bid on multiple ships to fix, and can plan hiring further out, Grady said. Additionally, improving base access for contractors has helped, as well.
“Last year, we averaged 110 days delayed per ship in private avails,” Grady said, using the short-hand term for “maintenance availability.”
“Things much better this year — even with COVID-19,” he continued. “We go from about one-third avails finishing on-time to two-thirds. That is great. But, again, each delay has real impact on our readiness, and we need to keep working together to do better.”
What happened?
Because the U.S. Navy is set up to meet standing presence requirements and missions around the world, it must cycle its ships through a system of tiered readiness.
That means ships go on deployment fully manned, trained and equipped. Then the ships come home, and after a period of sustained readiness where the ship can be redeployed, it goes into a reduced readiness status while undergoing maintenance. Following maintenance, the ship and crew goes into a training cycle for another deployment as an individual unit, then as a group, then returns to deployment.
The whole cycle takes 36 months: Rinse and repeat.
OFRP was designed in the 2013-2014 time-frame when the Navy was deploying well beyond its means, with carrier strike groups and amphibious ready groups going out for nine-to-10 months at a time.
The excess use wore hard on the ships and sailors who manned them and put more wear on the hulls than they were designed to sustain. That meant that when ships went in for maintenance they were more broken than they were supposed to be, and funding to fix them was hampered by spending cuts.
For nuclear ships — submarines and aircraft carriers — the funding cuts were a double whammy of work stoppages and furloughs that contributed to a wave of retirements in the yards, meaning the public yards were understaffed and had to hire and train new workers. Work took longer, throwing a wrench into an already complicated system of generating readiness.
All that added up to significant delays in getting ships through their maintenance cycles and contributed to astonishing delays in attack submarine maintenance especially.
What OFRP was meant to do was create a system whereby the Navy could meet combatant commander demands but not break the system. That meant that the Navy would generate as much readiness as it possibly could but that the demand would have to be limited to what the Navy could reasonably maintain, man, train and equip.
But getting to that system has been immensely difficult because of the deep hole the Navy dug meeting requirements that well outstripped funding and supply.
For example, there was a two year period when the service was forced to supply two carrier strike groups to the Arabian Gulf at all times, a requirement only canceled when automatic across-the-board spending cuts in 2013 made it impossible for the Navy to fund the two-carrier requirement.
Adding to the difficulty: some of OFRP's founding requirements were nigh impossible to pull off. One was that the all the ships in group would go into and come out of their maintenance availabilities on time and together. Another was that a group would go into the first phase of their training, the so-called basic phase right after coming out of maintenance, fully manned.
Both have been immensely difficult to pull off. But Fleet Forces, headed then by OFRP architect Adm. Phil Davidson, was given ample warning that those assumptions would be difficult to achieve.
Then-NAVSEA head Vice Adm. William Hilarides told USNI News in January 2015 that getting ships to come out of the yards simultaneously would be hard.
“The challenge to me is, let's say you want four destroyers in a battle group, all to come out at the same time in one port? That's a real challenge,” Hilarides told USNI News.
The current head of NAVSEA, who at the time was in charge of the Regional Maintenance Center enterprise, backed up his boss to USNI News, saying it would be particularly challenging in places with less infrastructure.
“Your big rub there is, the challenge of OFRP is ... all those ships [in a carrier strike group], they go through maintenance together, they go through training together and they deploy together,” said then-Rear Adm. William Galinis. "So, what our challenge is, is to be able to take all that work from all those ships and try to schedule it for roughly about the same time, and to get all that work done on time. So that's our challenge.
“Now, in a port like Norfolk or San Diego, we have big shipyards, a lot of people, a lot of ships. You can kind of absorb that type of workload. When you go to Mayport, they've got like 10 ships down there [and typically cannot work on more than one or two destroyers at a time.],” he told USNI.
Galinis said that Fleet Forces would have to be responsive to the shipyards because at least that way they could plan for delays.
“They know if they give us all this work at one time, it's going to go long anyway,” he told USNI. “So they'd rather be able to plan that and at least know when they're getting the ship back, as opposed to, ‘nope, we're not going to talk to you, you've got to go do it,' and then the ships go long because we don't have enough people to do the work.”
Fleet Forces Command has been reviewing its assumptions this year and is preparing to release a revised OFRP instruction, but the core is likely to remain the same. In any case, Wroe said in the email, it was always going to take a long time to dig out of the hole the Navy found itself in when OFRP was implemented fully in 2015.
“It was clear at the inception of OFRP, and remains clear today, that it will take the entire 2015-2025 period to recover readiness and establish stable readiness production,” Wroe said. “That makes sense when readiness production is planned over 9-years and large blocks of time have already been scheduled for depot maintenance periods.”
Ultimately, if the process of OFRP is funded correctly and ships can get out of maintenance on time, it's a sound way of moving forward, Fleet Forces Commander Grady told the audience this week.
“My bottom line here is that, as a process, OFRP works,” he said. “If we are looking where to improve upon it, each of these studies came to the same conclusion: the biggest inhibitor to fleet readiness is maintenance and modernization performance in the shipyards. We simply must get better, and I know you share my concern.”
https://www.defensenews.com/naval/2020/09/19/is-the-us-navy-winning-the-war-on-maintenance/
28 juillet 2024 | International, Terrestre
4 février 2020 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité
AIR FORCE The following eight firm-fixed price, indefinite-delivery/indefinite-quantity, multiple award task order contracts (MATOC) -- each with a not to exceed price of $90,000,000 -- have been awarded to the following: Doyon Management Services, Federal Way, Washington (FA4626-20-D-0010); Geranios Enterprises Inc., Great Falls, Montana (FA4626-20-D-0011); Guy Tabacco Construction Co., Black Eagle, Montana (FA4626-20-D-0012); James Talcott Construction, Great Falls, Montana (FA4626-20-D-0013); JE Hurley Inc., Colorado Springs, Colorado (FA4626-20-D-0014); NorthCon Inc., Hayden, Idaho (FA4626-20-D-0015); Sealaska Construction Solutions LLC., Seattle, Washington (FA4626-20-D-0016); and Wadsworth Builders Co. Inc., Great Falls, Montana (FA4626-20-D-0017). This MATOC contract is a design-build, bid-build construction acquisition based on a general statement of work further defined with each individual task order. Work to be performed under the MATOC will be the general construction category, to include maintenance, repair, alteration, mechanical, electrical, heating/air conditioning, demolition, painting and earthwork. Work will be performed at Malmstrom Air Force Base, Montana, and is to be completed as specified in each individual task order by Feb. 2, 2027. This award is the result of a competitive solicitation to total small businesses, 8(a) small business, and HUBZone small businesses; 16 offers were received. Fiscal 2020 operations and maintenance funds in the amount of $4,000 ($500 each) are being obligated at the time of award. The 341st Contracting Squadron, Malmstrom Air Force Base, Montana, is the contracting activity. Rolls-Royce Corp., Indianapolis, Indiana, has been awarded a $57,360,519 delivery order modification (FA8504-20-F-0007-P00002) to previously awarded contract FA8504-17-D-0002 for C-130J propulsion long term sustainment. This order provides funding for Option Three and Power By The Hour flying hours. The work is expected to be completed Feb. 1, 2021. Fiscal 2020 operations and maintenance funds in the amount of $57,360,519 are being obligated at the time of award. The total cumulative face value of the contract is $57,360,519. The Air Force Life Cycle Management Center, Robins Air Force Base, Georgia, is the contracting activity. Merrill Corp., Clearfield, Utah, has been awarded a firm-fixed price requirement type contract in the amount of $21,477,000 for the overhaul of duct assembly. Work will be performed in Clearfield, Utah, and is expected to be complete by Feb. 2, 2025. This award is the result of a sole-source acquisition. Fiscal 2020-2025 procurement funds will be used. The base award is estimated at $4,020,084; Option One is $4,000,467; Option Two is $4,346,985; Option Three is $4,641,164; and Option Four is $4,468,298. Tinker Air Force Base, Oklahoma, is the contracting activity (FA8119-20-D-0001). The Boeing Co., St. Louis, Missouri, has been awarded a firm-fixed-price requirement type contract in the amount of $7,907,471 for the repair of KC-135 cowling and fan ducts. Work will be performed in St. Louis, Missouri, and is expected to be complete by Feb. 2, 2025. This award is the result of a sole-source acquisition. Fiscal 2020-2025 procurement funds will be used. The base award (three year amount) is estimated at $4,941,509. Option One is $1,444,206; Option Two is $1,521,756. Tinker Air Force Base, Oklahoma, is the contracting activity (FA8119-20-D-0002). NAVY Manson Construction Co., Seattle, Washington, is awarded an $89,370,000 firm-fixed-price contract that provides for design-bid-build services for the construction of Seawolf Class Service Pier Extension, Naval Base Kitsap Bangor. The total cumulative face value of the contract including the award of four options will be $89,370,000. This contract award does not involve foreign military sales. The work to be performed provides for the construction of a 520 foot by 68-foot single level, reinforced concrete, general-purpose submarine berthing pier extension to the existing pier, with pier-side utilities, communication systems and two-580-square-foot concrete floating camels. The pier extension includes engineered pile and caps to support the pier deck, a fixed crane, equipment pads, mobile cranes and utility buildings. The project also configures and adds to the existing wave screen attenuation system and modifies the existing small craft berthing at the service pier. Additionally, the project constructs a low-rise compressor building on the pier for new tool air compressors and breathing air compressors and alters an existing building to accommodate new and existing lift stations, sewage equipment, storm drainage, industrial wastewater services and provides a new emergency generator. Work will be performed in Silverdale, Washington, and is expected to be completed by July 2022. The solicitation was competitively procured via Federal Business Opportunities with five offers received. Fiscal 2020 military construction funds for $89,370,000 are obligated on this award. The Naval Facilities Engineering Command, Northwest, Silverdale, Washington, is the contracting activity (N44255-20-C-2002). Rockwell Collins Simulation and Training Solutions, Cedar Rapids, Iowa, was awarded a $20,337,451 modification (P00016) to a previously awarded firm-fixed-price contract (N61340-17-C-0014). This modification procures updates to the Delta Software System Configuration #3 software baseline to include the visual system and cyber security on tactics and flight trainer devices. Additionally, this modification provides technology refresh and aircraft concurrency updates on tactics devices, aircraft concurrency and aerial refueling updates on the flight devices, tactics and flight device training and associated technical data in support of the E-2D Hawkeye Integrated Training System. Work will be performed in Point Mugu, California, and is expected to be completed in June 2022. Fiscal 2018 aircraft procurement (Navy) funds in the amount of $2,016,274; fiscal 2019 aircraft procurement (Navy) funds in the amount of $13,061,234; and fiscal 2020 aircraft procurement (Navy) funds in the amount of $5,259,943 will be obligated at time of award, $2,016,274 of which will expire at the end of the current fiscal year. The Naval Air Warfare Training Systems Division, Orlando, Florida, is the contracting activity. (Awarded Jan. 31, 2020) Raytheon Co., Integrated Defense Systems, Marlborough, Massachusetts, is awarded a $9,107,841 cost-plus-fixed-fee undefinitized contract action under a previously awarded basic ordering agreement N00024-19-G-5107 to repair and test the USS Sampson (DDG 102) SPY-1D(V) transmitter suite. This order covers repair, refurbishment, reassembly and testing of the AEGIS Weapon System (AWS) AN/SPY-1D(V) Transmitter Group in support of USS Sampson (DDG 102) as well as associated testing support. Work will be performed in Andover, Massachusetts (65%); Keyport, Washington (16%); Moorestown, New Jersey (10%); and Marlborough, Massachusetts (9%), and is expected to be completed by September 2021. Fiscal 2020 operations and maintenance (Navy) funding for $4,108,940 will be obligated at the time of award and expire at the end of the current fiscal year. This order was not competitively procured in accordance with 10 U.S. Code 2304(c)(1) (only one responsible source and no other supplies or services will satisfy agency requirements). The Naval Sea Systems Command, Washington, District of Columbia, is the contracting activity (N00024-20-F-5105). Zenetex LLC, Herndon, Virginia, was awarded a $7,521,702 cost-plus-fixed-fee contract to provide contractor support services (CSS) to temporarily augment government personnel to assist in the acquisition, management and sustainment of Navy training systems. CSS support includes corporate operations, research and technology, program management, logistics, engineering, instructional systems and test and evaluation support services for various training systems managed by the Naval Air Warfare Center Training Systems Division. Work will be performed in Orlando, Florida, and is expected to be completed in May 2020. Fiscal 2019 aircraft procurement (Navy) funds in the amount of $432,783; fiscal 2019 other procurement (Navy) funds in the amount of $138,112; fiscal 2019 research, development, test and evaluation (Navy) funds in the amount of $278,344; fiscal 2020 aircraft procurement (Navy) funds in the amount of $1,002,318; fiscal 2020 other procurement (Navy) funds in the amount of $357,920; fiscal 2020 operations and maintenance (Navy) funds in the amount of $507,119; fiscal 2020 research, development, test and evaluation (Navy) funds in the amount of $101,022; working capital (Navy) funds in the amount of $1,204,302; and Foreign Military Sales funds in the amount of $520,643 will be obligated at time of award, $785,463 of which will expire at the end of the current fiscal year. This contract was not competitively procured pursuant to Federal Acquisition Regulation 6.302-1. The Naval Air Warfare Center Training Systems Division, Orlando, Florida, is the contracting activity (N61340-20-C-0009). (Awarded Jan. 31, 2020) ARMY H2 Direct LLC,* Gulf Breeze, Florida, was awarded a $39,000,000 firm-fixed-price contract for personnel, equipment, supplies, facilities, transportation, tools, materials, supervision and other items and non-personal services necessary to provide information technology management support services. Bids were solicited via the internet with eight received. Work locations and funding will be determined with each order, with an estimated completion date of Feb. 28, 2025. The 418th Contracting Support Brigade, Fort Hood, Texas, is the contracting activity (W91151-20-D-0009). Cray Inc., Seattle, Washington, was awarded a $26,480,000 firm-fixed-price contract for Department of Defense high performance computing modernization. Bids were solicited via the internet with three received. Work will be performed in Stennis Space Center, Mississippi, with an estimated completion date of Aug. 1, 2025. Fiscal 2020 other procurement, Army funds in the amount of $26,480,000 were obligated at the time of the award. U.S. Army Corps of Engineers, Huntsville, Alabama, is the contracting activity (W912DY-20-F-0126). Sustainable System Solutions LLC,* Herndon, Virginia, was awarded a $9,563,615 cost-plus-fixed-fee contract to provide the design, development, integration, testing and fielding of test capabilities systems and/or related test infrastructure among ranges within the Department of Defense test and evaluation community. Bids were solicited via the internet with four received. Work locations and funding will be determined with each order, with an estimated completion date of Feb. 2, 2030. U.S. Army Contracting Command, Orlando, Florida, is the contracting activity (W900KK-20-D-0003). Escal Institute Advanced Tech, North Bethesda, Maryland, was awarded an $8,805,373 firm-fixed-price contract to provide training and certifications to verify and validate student proficiency in cybersecurity roles. Bids were solicited via the internet with four received. Work locations and funding will be determined with each order, with an estimated completion date of Feb. 2, 2021. Fort Gordon, Georgia, is the contracting activity (W911S0-20-F-0111). U.S. SPECIAL OPERATIONS COMMAND The Boeing Co., Ridley Park, Pennsylvania, was awarded an $18,186,000 firm-fixed-price type delivery order (H92241-20-F-0020) under basic ordering agreement W91215-16-G-0001 to procure the long lead components and parts in support of MH-47G rotary wing aircraft. This action is required to satisfy an urgent need to sustain U.S. Special Operations Forces (SOF) heavy assault, rotary wing aircraft and to mitigate the impact of the MH-47G aircraft availability in light of increased SOF operational demands. Contract funds will not expire at the end of the current fiscal year. Fiscal 2020 aircraft procurement, Army funds in the amount of $18,186,000 were obligated at the time of award. The majority of the work will be performed in Ridley Park. U.S. Special Operations Command, Tampa, Florida, is the contracting activity. *Small business https://www.defense.gov/Newsroom/Contracts/Contract/Article/2073298/source/GovDelivery/
5 février 2024 | International, Naval
The support program will see Thales use data technology, including AI and virtual reality, to provide more proactive and predictive maintenance.