Irving to receive $58 million for 'minimal' changes to new Coast Guard ships

DAVID PUGLIESE, OTTAWA CITIZEN

Irving is receiving $58 million from taxpayers to make what the federal government calls minimal changes to an existing ship design so it can be used by the Canadian Coast Guard.

Irving is in the midst of building a fleet of six Arctic and Offshore Patrol Ships (AOPS) for the Royal Canadian Navy and will add two more in the production line for the coast guard. The addition of two ships for the coast guard, announced by the federal government in May, was supposed to be cost-effective as the design of the vessel was completed and the ships were in the process of being built.

But documents recently tabled in Parliament show the government entered into a $58-million contract with Irving for engineering design work on the AOPS that would ensure the coast guard's vessels “can meet regulatory and operational requirements.”

The coast guard has determined that only minimal modifications are required to the ships to meet its needs as well as any regulatory requirements, according to documents provided to Parliament as the result of a question from Conservative MP Lianne Rood.

“The modifications have been assessed as minimal as none of the identified modifications will impact major elements of the AOPS design and construction,” Bernadette Jordan, the minister of Fisheries, Oceans, and the Canadian Coast Guard, stated in her written response.

But critics are questioning why taxpayers are spending $58 million if the changes are so limited.

“That's a very expensive tweak,” said Aaron Wudrick, the federal director of the Canadian Taxpayers Federation. “We'd like see some clarity from the government on what could possibly justify such an increase in the price tag.”

Each AOPS is estimated to cost around $400 million. The coast guard originally looked at the AOPS in 2017-2018 but decided against acquiring the ship, industry representatives noted.

But the Liberal government announced in May 2019 that two AOPS would be bought for the coast guard. One of the benefits of the purchase is to prevent layoffs at Irving as there is expected to be a gap between when the shipyard finishes the navy's AOPS and when it starts working on replacements for the navy's frigates.

Tom Ormsby, director of communications for Irving, said the first step for the firm is to fully review the AOPS design and then confirm any modifications that are needed to be made for the coast guard.

“Once modifications have been agreed to, these changes must then be worked through and implemented into the design,” he noted. “While not making major changes that a first-in-class design would require, the Canadian Coast Guard has a different and critical mission, including the need for scientific laboratories for sampling and research, so each vessel is being tailored to suit the Canadian Coast Guard's unique and important role.”

The government only pays for actual costs incurred, he added.

Irving will also receive an additional $18.8 million to purchase some initial equipment for the vessels as well as reimbursement for project management.

The contract to Irving on the design changes was signed Nov. 1, 2019 and is to end March 31, 2021. Areas of change include modifications to the bridge layout and accommodations to meet Transport Canada requirements for a non-military crew, as well as changes to some areas to accommodate coast guard equipment and modifications to the deck, Jordan noted in her response to Parliament. The main portions of the ship, including the hull and propulsion systems, will remain unchanged, she added.

The AOPS program was launched by the Conservative government with a minimum of five ships for the navy. The Liberal government approved the construction of a sixth AOPS for the navy and two for the coast guard

But retired Liberal senator Colin Kenny, who served on the Senate defence committee, questions the value of the AOPS for either the navy or coast guard. Kenny noted he is also concerned about the engineering contract. “These changes shouldn't cost $58 million,” Kenny said. “I think it's questionable as to why we are even buying these ships.”

In 2017 the Senate Defence Committee raised concerns about the capabilities of the AOPS.

Among the issues identified by the committee was the slow speed of the AOPS and its limited ability to operate in ice-covered waters. “These limitations are troubling and raise the question of whether the taxpayers are receiving value for the monies spent,” the Senate report said.

The Department of National Defence expects the delivery of the first AOPS by the end of March although it acknowledges there is a possibility that may not happen. The delivery of the vessel has already been delayed a number of times.

The navy expects its last AOPS to be delivered by 2024. After the navy vessels are built, construction will begin on the AOPS for the coast guard, the federal government has said.

https://ottawacitizen.com/news/national/defence-watch/irving-to-receive-58-million-for-minimal-changes-to-new-coast-guard-ships

Sur le même sujet

  • Canadian Army feeling squeeze of more demands, fewer soldiers

    28 décembre 2022 | Local, Terrestre

    Canadian Army feeling squeeze of more demands, fewer soldiers

    Lt.-Gen. Joe Paul says the Army shrunk by 1,200 soldiers last year as departures outpaced recruiting ⁠ — and that it could lose hundreds more unless the situation changes.

  • Joint Support Ship cost up by $1.1 billion - taxpayers will now spend $3.4 billion on project

    11 juin 2018 | Local, Naval

    Joint Support Ship cost up by $1.1 billion - taxpayers will now spend $3.4 billion on project

    DAVID PUGLIESE, OTTAWA CITIZEN Taxpayers will have to spend $1.1 billion extra on new navy supply ships that are going to be built starting this summer, the Liberal government now acknowledges. Previously the cost of building the two ships at Seaspan shipyards in Vancouver, BC had been pegged at $2.3 billion. But the government ordered a review of that cost figure and in an email to Postmedia, Procurement Minister Carla Qualtrough's office now confirms the cost for the Joint Support Ships, or JSS, is set at $3.4 billion. Pat Finn, the head of procurement at the Department of National Defence, said the new price tag came as the government decided to do an additional analysis of the project and include other items it had not previously included. In some cases equipment for the ship has been purchased so there are better costs available on those items, Finn said in an interview Monday. Also taken into account was new infrastructure and the delays with the program, which, in turn, drove up the price as the cost of material increased over the years. “The build period has changed quite dramatically,” Finn acknowledged. At one point, the first ship was supposed to arrive in 2012. That has been changed a number of times with the government later hoping for a 2018 delivery and then a 2019 arrival for the first vessel. The Department of National Defence is now hoping for the delivery of the first ship in 2022 or 2023. Construction will begin at Seaspan this summer of some initial portions of the vessels, Finn said. The government hopes starting construction on the supply ships in the summer will head off any potential layoffs of skilled employees at Seaspan. Finn said of the $3.4 billion figure, the actual cost of building the two ships accounts for a little more than 60 per cent. Finn said the new costing model for the JSS is more akin to the one used by the parliamentary budget office. That office had an even higher estimate for JSS when it concluded in 2013 that the final tally for taxpayers would be $4.13 billion. The Joint Support Ships are critical for the navy as they provide fuel and supplies for warships at sea. But the Royal Canadian Navy retired its last two aging supply ships years ago. One was damaged beyond repair in a fire. The other was removed from service because of excessive corrosion. The Canadian military had been relying on the Spanish and Chilean navies to provide supply vessels for short periods of time to help fuel up Canadian warships at sea. Because of the delays in the JSS program, the previous Conservative government entered into agreement with Davie Shipyards in Quebec to lease a commercial vessel that had been converted into a refueling and supply ship. That ship, the MV Asterix, is at the heart of federal government's case against Vice Admiral Mark Norman. Norman has been accused by the RCMP of warning Davie in the fall of 2015 that Liberal cabinet ministers wanted to derail the Asterix project. Word of the Liberal plan leaked out to the news media and the resulting embarrassment forced the Trudeau government to back down on its plans and the conversion of Asterix proceeded. Norman was put under investigation and Prime Minister Justin Trudeau predicted on two occasions the officer would ultimately end up in court. In March, the RCMP charged Norman with a single count of breach of trust. A date for the trial has not yet been set. Norman denies the charge and has said he looks forward to clearing his name. Asterix is considered a rare achievement in Canadian military procurement in that it was delivered on time and on budget. The supply ship is now at sea with Royal Canadian Navy and is headed to a major military exercise to begin later this month. http://ottawacitizen.com/news/national/defence-watch/joint-support-ship-cost-up-by-1-1-billion-taxpayers-will-now-spend-3-4-billion-on-project

  • Canadian, French military planes ‘came into contact’ at Guam air base - National | Globalnews.ca

    24 juillet 2023 | Local, Aérospatial

    Canadian, French military planes ‘came into contact’ at Guam air base - National | Globalnews.ca

    The Department of National Defence told Global News the incident occurred Friday on the ramp at Anderson Air Force Base "in which the two aircraft came into contact."

Toutes les nouvelles