Faulty $5 Parts Cause 18-Month, $1 Billion Delay to Navy, Air Force Nuclear Upgrades

Defects found in a $5 electrical component will delay the Navy and Air Force nuclear warhead refurbishment program by 18 months and cost more than $1 billion to fix, a National Nuclear Security Administration official said during a congressional hearing Wednesday.

The faulty components are small commercially available capacitors that were to be used in upgrades to the Navy's W88 nuclear warheads. These weapons are deployed on the Trident II D5 submarine-launched ballistic missile systems. Similar capacitors are needed to upgrade the Air Force's B61-12 gravity bomb, Charles Verdon, deputy administrator for defense programs at the National Nuclear Security Administration, told members of the House Armed Services subcommittee on strategic forces during the unclassified portion of Wednesday's hearing.

When engineers evaluated available parts, they ran tests to determine if the off-the-shelf capacitors were compatible with the systems due for upgrades, Verdon said. Initial results suggested the components would work in the short-term.

“Early tests on the capacitors now in question and subsequent tests including component, major assembly and full-up integrated system flight tests demonstrated that these components meet requirement today. Industry best practices were used to stress the components beyond their design planned usage as a way to establish confidence that they will continue to work over the necessary lifetime of the warhead,” Verdon said. “During stress testing, a few of these commercially available capacitors did not meet the reliability requirements.”

The problem is, these parts used in the warhead upgrades must survive for decades, up to 30 years after production, Verdon said. However, the quality of each capacitor production lot varied, which led to the stress testing failure. Instead of using the capacitors and risking readiness in the future, Verdon said his agency decided to delay the upgrade work, initially scheduled to begin in December.

Replacement capacitors are being produced but will cost about $75 per unit, compared with the $5 per unit cost of the off-the-shelf capacitors that failed stress testing.

“The use of commercial-off-the-shelf electric components needs to be improved to reduce future COTS-related risk,” Verdon said.

The Navy is working with U.S. Strategic Command to understand how the 18-month delay will affect near-term deployments, Vice Adm. Johnny Wolfe, the director of strategic systems programs for the Navy, told the panel.

“Currently, today, based on what we're doing with STRATCOM, we will meet the requirements as we move forward,” Wolfe said.

The Navy and STRATCOM are developing a mitigation plan which includes is reevaluating how to turn around the submarine-based nuclear missile stockpile and how to schedule warheads for upgrades in the future, Wolfe said. More details on the Navy's plan to be discussed in a classified hearing.

“If you look at the age of these systems and the technology we're using, these are tough, tough issues to solve, and it's critical technology that we're learning as we modernize these,” Wolfe said.

Rep. Jim Cooper (D-Tenn.), chair of the strategic forces subcommittee, said he held the hearing because he wanted more information on what NNSA was doing to avoid more delays. He called the recapitalization “both necessary and hugely expensive” in his written opening statement.

“Maintaining Congress and the public's confidence in these programs, and their effective execution, is imperative,” he wrote.

https://news.usni.org/2019/09/25/faulty-5-parts-cause-18-month-1-billion-delay-to-navy-air-force-nuclear-upgrades

Sur le même sujet

  • Lockheed eyes 5G trials following delivery of test bed to Marine Corps

    31 août 2023 | International, Naval

    Lockheed eyes 5G trials following delivery of test bed to Marine Corps

    The delivery to Camp Pendleton in California marks a step forward for the Open Systems Interoperable and Reconfigurable Infrastructure Solution, or OSIRIS.

  • Everyone's an Expert: How to Empower Your Employees for Cybersecurity Success

    1 mai 2024 | International, Sécurité

    Everyone's an Expert: How to Empower Your Employees for Cybersecurity Success

    Master the art of choosing a security awareness training (SAT) solution that can drive meaningful changes for you and your organization.

  • General Electric beats Rolls-Royce to power Turkey’s indigenous fighter jet

    2 novembre 2018 | International, Aérospatial

    General Electric beats Rolls-Royce to power Turkey’s indigenous fighter jet

    By: Burak Ege Bekdil ANKARA, Turkey — Turkey's aerospace authorities have chosen General Electric's F110 family of engines to power the prototype and an initial batch of what will become Turkey's first indigenous fighter jet, the TF-X. A senior procurement official confirmed the choice, saying that the twin-engine TF-X will be powered by the F110-GE-129 or the F110-GE-132 engine. “This is a stopgap solution until we have built our indigenous engine for the TF-X,” the official said. Under the deal, the first prototype of the TF-X and an unknown number of initial batches would be powered by the F110 engine. Turkey then plans to switch to an engine to be developed by TRMotor, a national engine consortium. But some aerospace sources say the F110 may not be the ideal engine for a fifth=generation fighter. “If the Turks go for the GE option, they will have to compromise on the stealth capabilities of the TF-X,” a Paris-based defense specialist said. Earlier this year, Turkey and Rolls-Royce came close to a strategic cooperation deal for the development and co-production of an engine for the TF-X. The British company and the Turkish government signed a letter of intent to finalize negotiations on the engine program by July 31, but the plan did not come to fruition. Turkish officials say the idea behind the GE deal is to rely on foreign technology to eventually in the long term build an indigenous engine to power the TF-X. Turkey wants to build the TF-X with know-how from BAE Systems. In January 2017, Britain and Turkey signed a deal worth more than £100 million (U.S. $128 million) to develop the Turkish fighter jet. Turkey hopes to have the first test flights of the aircraft in 2023. https://www.defensenews.com/industry/2018/10/31/general-electric-beats-rolls-royce-to-power-turkeys-indigenous-fighter-jet/

Toutes les nouvelles