16 juin 2020 | Local, Naval

Canada to pay $4.1B for Navy support ships in latest cost increase

The Canadian Press

OTTAWA — Canada's national shipbuilding plan was rocked by yet another cost increase on Monday as the federal government revealed it will pay $4.1 billion for two long-overdue support ships for the navy — an increase of $1.5 billion from initial estimates.

The revelation came as Ottawa officially awarded a contract for the full construction of the two new Protecteur-class joint support ships to Vancouver's Seaspan shipyards, which has already started work on the first of the vessels.

Seaspan was first tapped to build the two ships and several coast guard vessels in 2011, at which point the supply ships were expected to cost $2.6 billion. The figure was later revised to $3.4 billion before another $700 million was added Monday.

The first of the support ships was to have been delivered by 2019. The government says it now doesn't expect the first ship before 2023, with the second due in 2025. Seaspan has been under contract to work on some parts of the first ship since June 2018.

The Royal Canadian Navy has been without a full-time support ship since 2014 and is currently relying on a converted civilian vessel that is being leased from Quebec's Chantier Davie shipyard to fill the gap.

That ship, the MV Asterix, was at the heart of the failed prosecution of retired vice-admiral Mark Norman.

The Liberal government was playing down the cost increase to the support ships on Monday, with senior ministers touting the importance of the vessels to the Royal Canadian Navy and the jobs that the project is creating in Vancouver and elsewhere.

"These new ships will provide a necessary capability for our Royal Canadian Navy, while providing significant economic benefits and jobs to Canadians, including thousands of jobs created or sustained," Defence Minister Harjit Sajjan said in a statement.

Yet the cost increase is the latest to hit the shipbuilding plan, which has been plagued by delays and budget increases for years. The plan is intended to recapitalize the majority of Canada's naval and coast guard fleets.

The entire plan to buy new warships to replace the navy's frigates and destroyers, several Arctic patrol vessels, a polar icebreaker and four science vessels for the Canadian Coast Guard in addition to the two support ships was pegged in 2011 at $35 billion.

The warships alone are now expected to cost at least $65 billion while the rest of the projects have either seen similar budget increases or their budgets are under review. The delivery schedules for the projects have also been pushed back numerous times.

Defence analyst David Perry of the Canadian Global Affairs Institute noted the new cost for the support ships is almost exactly how much Parliament's budget watchdog estimated following an analysis in 2013.

The Conservative government at the time refuted the parliamentary budget officer's estimate, with then-public works minister Rona Ambrose saying appropriate safeguards had been put into place to protect taxpayers.

"There's not a lot of detail in this today so it's hard to do a line by line," Perry said. "But superficially at least, the PBO's report from 2013 — which I recall being pooh-poohed pretty extensively — has held up pretty well."

Ottawa has in recent years produced update cost estimates for most of the vessels being built through the federal shipbuilding plan. However, budgets for the polar icebreaker and an offshore science vessel for the coast guard are still under review.

This report by The Canadian Press was first published June 15, 2020.

https://www.kamloopsthisweek.com/news/canada-to-pay-4-1b-for-navy-support-ships-in-latest-cost-increase-1.24153254

Sur le même sujet

  • Orbit Fab ships first satellite refueling ports to Space Force

    23 mars 2024 | Local, Aérospatial

    Orbit Fab ships first satellite refueling ports to Space Force

    The company's RAFTI port is designed to be installed on satellites to allow them to receive propellant either in space or on the ground before launch.

  • Marine careers on tour: HMC Ships Goose Bay and Harry DeWolf take part in expo roadshow

    4 septembre 2024 | Local, Naval

    Marine careers on tour: HMC Ships Goose Bay and Harry DeWolf take part in expo roadshow

    The Royal Canadian Navy (RCN) in partnership with other Government of Canada organizations and the Canadian Marine Careers Foundation is hosting the second annual Marine Careers Expo (MCE) this fall to connect with Canadians and showcase marine career opportunities at sea and ashore.

  • Norway’s experience with F-35 fighter jets offers lesson for Canada

    23 novembre 2018 | Local, Aérospatial

    Norway’s experience with F-35 fighter jets offers lesson for Canada

    By Levon Sevunts, Radio Canada International As the federal government embarks on a much delayed and criticized quest to find a replacement for its ageing fleet of CF-18 Hornet fighter jets, Norway's saga with the acquisition of F-35 stealth fighters offers Canada a valuable lesson. The search for a replacement for CF-18 got a new urgency Tuesday after a blistering report by Canada's auditor general, who lambasted the Liberal government's handling of the file that could have serious implications for Ottawa's ability to fulfill its NATO and NORAD obligations. Just like Ottawa, Oslo was one of the first NATO countries to show interest in the new stealth multirole fighters developed by U.S. defence giant Lockheed Martin. In June 2009, the Norwegian Parliament decided that the F-35A Lightning II would replace its current fleet of F-16 fighter jets. Unlike Ottawa, despite strong internal opposition, Oslo saw things through. By 2025, Norway hopes to have a fleet of 52 F-35s.​ No-show at Trident Juncture demonstration Norwegian authorities were hoping to showcase their newest and most expensive defence acquisition in the country's history at a massive display of NATO's military might during the official launch of Trident Juncture 2018 exercise on Oct. 30. But much to the chagrin of dozens of journalists, NATO officials and dignitaries that had assembled on the shores of the Trondheim Fjord in central Norway to watch the display of land, sea and air power, the Norwegian F-35s never showed up. Lt.-Col. Stale Nymoen, commander of the 332 Squadron of the Royal Norwegian Air Force and one of the first Norwegian pilots to learn to fly the F-35s, said strong crosswinds at the Ørland Air Base forced officials to cancel the planned overflight. The cancellation of the overflight on an otherwise perfect autumn day had nothing to do with the jet's capabilities, Nymoen said. “Seen from my perspective, it's one of the best fighter aircraft out there,” Nymoen told a roomful of journalists during a briefing at the Ørland Air Base in central Norway earlier this month. But it has taken even experienced pilots like him years to learn to fly the new fighter jets and, just as importantly, unlearn old habits, Nymoen said. Learning to crawl before walking Norway received its first four F-35s in January of 2017. But all of them were stationed at the Luke Air Force Base in Phoenix, Arizona, where Norwegian, U.S. and Italian pilots trained on the new aircraft. It wasn't until November of 2017 that the stealth fighter jets actually arrived for service in Norway, at the Ørland Air Base, which is going through a massive infrastructure upgrade to house the new planes. Operating and flying them in Norway with its harsh North Atlantic and Arctic climate is a whole new experience, Nymoen said. “What is different from Luke when we train to operate the aircraft here is temperatures, winter, icy and slippery runways, winds,” Nymoen said. “Those are conditions that we don't necessarily get to train for when we're training in the United States.” And the Norwegian air force is taking a very cautious approach to avoid any accidents, he said. “We have to learn to crawl before we can walk, and we have to learn to walk before we can run,” Nymoen said. The first squadron of F-35s is expected to reach initial operational capability in 2019 and full operational capability only in 2025, eight years after the aircraft were delivered to Norway. This timeline would also apply to Canada, if Lockheed Martin were to emerge as the winner of the competition to buy 98 advanced aircraft for the Royal Canadian Air Force announced by the Liberal government last December. The list of eligible suppliers identified by the federal government also includes France's Dassault Aviation, Sweden's SAAB, the U.K.'s Airbus Defense and Space, and the U.S. defence and aerospace giant Boeing. If the federal government manages to stick to its timetable, a contract award is anticipated in 2022 and the first replacement aircraft delivered in 2025. This means that the current fleet of Canadian CF-18s and the 18 additional second-hand Australian F-18s the federal government is buying as a stopgap measure will have to operate until at least 2030, experts say. http://www.rcinet.ca/en/2018/11/21/norway-f-35-fighter-jets-offers-lesson-for-canada

Toutes les nouvelles