June 16, 2020 | Local, Naval

Canada to pay $4.1B for Navy support ships in latest cost increase

The Canadian Press

OTTAWA — Canada's national shipbuilding plan was rocked by yet another cost increase on Monday as the federal government revealed it will pay $4.1 billion for two long-overdue support ships for the navy — an increase of $1.5 billion from initial estimates.

The revelation came as Ottawa officially awarded a contract for the full construction of the two new Protecteur-class joint support ships to Vancouver's Seaspan shipyards, which has already started work on the first of the vessels.

Seaspan was first tapped to build the two ships and several coast guard vessels in 2011, at which point the supply ships were expected to cost $2.6 billion. The figure was later revised to $3.4 billion before another $700 million was added Monday.

The first of the support ships was to have been delivered by 2019. The government says it now doesn't expect the first ship before 2023, with the second due in 2025. Seaspan has been under contract to work on some parts of the first ship since June 2018.

The Royal Canadian Navy has been without a full-time support ship since 2014 and is currently relying on a converted civilian vessel that is being leased from Quebec's Chantier Davie shipyard to fill the gap.

That ship, the MV Asterix, was at the heart of the failed prosecution of retired vice-admiral Mark Norman.

The Liberal government was playing down the cost increase to the support ships on Monday, with senior ministers touting the importance of the vessels to the Royal Canadian Navy and the jobs that the project is creating in Vancouver and elsewhere.

"These new ships will provide a necessary capability for our Royal Canadian Navy, while providing significant economic benefits and jobs to Canadians, including thousands of jobs created or sustained," Defence Minister Harjit Sajjan said in a statement.

Yet the cost increase is the latest to hit the shipbuilding plan, which has been plagued by delays and budget increases for years. The plan is intended to recapitalize the majority of Canada's naval and coast guard fleets.

The entire plan to buy new warships to replace the navy's frigates and destroyers, several Arctic patrol vessels, a polar icebreaker and four science vessels for the Canadian Coast Guard in addition to the two support ships was pegged in 2011 at $35 billion.

The warships alone are now expected to cost at least $65 billion while the rest of the projects have either seen similar budget increases or their budgets are under review. The delivery schedules for the projects have also been pushed back numerous times.

Defence analyst David Perry of the Canadian Global Affairs Institute noted the new cost for the support ships is almost exactly how much Parliament's budget watchdog estimated following an analysis in 2013.

The Conservative government at the time refuted the parliamentary budget officer's estimate, with then-public works minister Rona Ambrose saying appropriate safeguards had been put into place to protect taxpayers.

"There's not a lot of detail in this today so it's hard to do a line by line," Perry said. "But superficially at least, the PBO's report from 2013 — which I recall being pooh-poohed pretty extensively — has held up pretty well."

Ottawa has in recent years produced update cost estimates for most of the vessels being built through the federal shipbuilding plan. However, budgets for the polar icebreaker and an offshore science vessel for the coast guard are still under review.

This report by The Canadian Press was first published June 15, 2020.

https://www.kamloopsthisweek.com/news/canada-to-pay-4-1b-for-navy-support-ships-in-latest-cost-increase-1.24153254

On the same subject

  • AEW, next-gen helicopters among defence policy commitments for the RCAF - Skies Mag

    April 9, 2024 | Local, Aerospace

    AEW, next-gen helicopters among defence policy commitments for the RCAF - Skies Mag

    New airborne early warning (AEW) aircraft and funding for tactical helicopters to replace multi-role CH-146 Griffons, are among the key aerospace elements of an updated defence policy.

  • Canada to Acquire Three Interim Icebreakers

    June 26, 2018 | Local, Naval

    Canada to Acquire Three Interim Icebreakers

    From: Public Services and Procurement Canada News release Helping Keep Canada's Waters Safe June 22, 2018 – Gatineau (Quebec) – Public Services and Procurement Canada The Government of Canada is committed to providing the women and men of the Canadian Coast Guard with the equipment they need to keep Canadian waters safe, while supporting economic growth. On behalf of the Canadian Coast Guard, Public Services and Procurement Canada has issued an Advanced Contract Award Notice (ACAN) to Chantier Davie of Lévis, Quebec, for the acquisition and conversion of three medium commercial icebreakers. This ensures a fair, competitive process allowing any supplier with a comparable option to also submit a proposal before a contract is awarded. The ACAN confirms Canada's intention to enter into a contract with Chantier Davie. Other interested suppliers have 15 calendar days to signal their interest in bidding for this contract, by submitting a “statement of capabilities” that meets the requirements laid out in the ACAN. These ships would provide interim capability for the Canadian Coast Guard, while replacement vessels are being built under the National Shipbuilding Strategy. Icebreakers are essential to ensuring that Canadian ports remain open during Canada's ice seasons, ensuring goods such as fresh produce and fuel are delivered safely. Quotes “Our Government is committed to supporting the Coast Guard in carrying out its crucial work on behalf of all Canadians. We are one step closer to acquiring supplementary capacity that will support interim icebreaking capability in time for the upcoming icebreaking season.” The Honourable Carla Qualtrough Minister of Public Services and Procurement “The Canadian Coast Guard has unique requirements given Canada's wide range of challenging ice conditions in both our southern waters and the Arctic. We are making sure they have the equipment and tools they need to keep Canadian waters safe and commercial routes open during Canada's ice seasons.” The Honourable Lawrence MacAulay Minister of Agriculture Quick facts This acquisition will consist of purchasing a class of three existing Anchor Handling Tug Supply icebreakers. These ships will be used to backfill for Canadian Coast Guard vessels while they are undergoing maintenance, refit and vessel life extension. These ships will conduct critical icebreaking duties for the Southern wintertime program and are to be deployed as needed in support of Arctic summertime programs. The first ship will be put to immediate use for icebreaking during the upcoming 2018-2019 season. https://www.canada.ca/en/public-services-procurement/news/2018/06/canada-to-acquire-three-interim-icebreakers.html

  • Title Publication Date	Department	News type Teaser Minister Blair to visit Halifax, Nova Scotia to discuss Our North, Strong and Free and launch construction on the Canadian Surface Combatant fleet

    June 25, 2024 | Local, Land

    Title Publication Date Department News type Teaser Minister Blair to visit Halifax, Nova Scotia to discuss Our North, Strong and Free and launch construction on the Canadian Surface Combatant fleet

    The Honourable Bill Blair, Minister of National Defence, will visit Halifax from June 27 to June 28, 2024 to discuss Canada’s defence policy update, Our North, Strong and Free, launch construction on the Canadian Surface Combatant project

All news