June 16, 2020 | Local, Naval

Canada to pay $4.1B for Navy support ships in latest cost increase

The Canadian Press

OTTAWA — Canada's national shipbuilding plan was rocked by yet another cost increase on Monday as the federal government revealed it will pay $4.1 billion for two long-overdue support ships for the navy — an increase of $1.5 billion from initial estimates.

The revelation came as Ottawa officially awarded a contract for the full construction of the two new Protecteur-class joint support ships to Vancouver's Seaspan shipyards, which has already started work on the first of the vessels.

Seaspan was first tapped to build the two ships and several coast guard vessels in 2011, at which point the supply ships were expected to cost $2.6 billion. The figure was later revised to $3.4 billion before another $700 million was added Monday.

The first of the support ships was to have been delivered by 2019. The government says it now doesn't expect the first ship before 2023, with the second due in 2025. Seaspan has been under contract to work on some parts of the first ship since June 2018.

The Royal Canadian Navy has been without a full-time support ship since 2014 and is currently relying on a converted civilian vessel that is being leased from Quebec's Chantier Davie shipyard to fill the gap.

That ship, the MV Asterix, was at the heart of the failed prosecution of retired vice-admiral Mark Norman.

The Liberal government was playing down the cost increase to the support ships on Monday, with senior ministers touting the importance of the vessels to the Royal Canadian Navy and the jobs that the project is creating in Vancouver and elsewhere.

"These new ships will provide a necessary capability for our Royal Canadian Navy, while providing significant economic benefits and jobs to Canadians, including thousands of jobs created or sustained," Defence Minister Harjit Sajjan said in a statement.

Yet the cost increase is the latest to hit the shipbuilding plan, which has been plagued by delays and budget increases for years. The plan is intended to recapitalize the majority of Canada's naval and coast guard fleets.

The entire plan to buy new warships to replace the navy's frigates and destroyers, several Arctic patrol vessels, a polar icebreaker and four science vessels for the Canadian Coast Guard in addition to the two support ships was pegged in 2011 at $35 billion.

The warships alone are now expected to cost at least $65 billion while the rest of the projects have either seen similar budget increases or their budgets are under review. The delivery schedules for the projects have also been pushed back numerous times.

Defence analyst David Perry of the Canadian Global Affairs Institute noted the new cost for the support ships is almost exactly how much Parliament's budget watchdog estimated following an analysis in 2013.

The Conservative government at the time refuted the parliamentary budget officer's estimate, with then-public works minister Rona Ambrose saying appropriate safeguards had been put into place to protect taxpayers.

"There's not a lot of detail in this today so it's hard to do a line by line," Perry said. "But superficially at least, the PBO's report from 2013 — which I recall being pooh-poohed pretty extensively — has held up pretty well."

Ottawa has in recent years produced update cost estimates for most of the vessels being built through the federal shipbuilding plan. However, budgets for the polar icebreaker and an offshore science vessel for the coast guard are still under review.

This report by The Canadian Press was first published June 15, 2020.

https://www.kamloopsthisweek.com/news/canada-to-pay-4-1b-for-navy-support-ships-in-latest-cost-increase-1.24153254

On the same subject

  • Procurement chief at National Defence to step down

    April 1, 2024 | Local, Land

    Procurement chief at National Defence to step down

    Troy Crosby, Assistant Deputy Minister for Materiel, retires after launching Canadian Surface Combatant and F-35 jet programs

  • The Canadian Space Agency Announces the FAST 2019 Opportunity

    August 6, 2019 | Local, Aerospace

    The Canadian Space Agency Announces the FAST 2019 Opportunity

    CSA FAST Program. Credit: Canadian Space Agency. Facebook Twitter Stumbleupon LinkedIn Today the Canadian Space Agency announced the Flights and Fieldwork for the Advancement of Science and Technology (FAST) 2019 opportunity. According to the Canadian Space Agency the FAST program supports “research projects of Canadian universities and post-secondary institutions that will contribute to the development of new scientific knowledge and space technologies, while making it possible for students to acquire hands-on experience in space-like missions.” The last FAST program awards were in 2017 where $6.2 million was awarded for 31 projects. In this FAST program announcement the expected budget is $3.5 million going to approximately 19 awards. The maximum duration for the grants is three years. For FAST 2019 the grants will be awarded in two categories; Category A: Maximum grant of $300,000 for a maximum duration of three years for an end-to-end space-like mission project that includes the development or improvement of a technology, use of the technology during a flight or field or research site deployment, and data collection and analysis; the maximum amount available per year is $150,000. Those familiar with the program and interested in applying for Category A should be aware that FAST 2019 appears to be a merging of FAST 2017 Category A and B with the resulting median award of $300,000 being the new ceiling for grants. Category B: Maximum grant of $100,000 for two or three years, for a small space-related research project; the maximum amount available per year is $50,000. Category B is what Category C was in FAST 2017. The application deadline is October 18, 2019, 1:00 pm ET. http://spaceq.ca/the-canadian-space-agency-announces-the-fast-2019-opportunity/

  • Federal government considering delaying acceptance of bids for new fighter jets

    May 6, 2020 | Local, Aerospace

    Federal government considering delaying acceptance of bids for new fighter jets

    David Pugliese • Ottawa Citizen Publishing date: 21 hours ago • 3 minute read The federal government is looking at once again delaying acceptance of bids on new fighter jets. The bids were originally supposed to be submitted in May 2019 but that was pushed back to March 30 this year. That deadline, in turn, was pushed back to June 30 at the request of the aerospace industry, Public Services and Procurement Canada announced in February. But now the department is once again evaluating a request from industry to further extend that deadline for the proposals, Procurement Canada spokesman Marc-André Charbonneau confirmed in an email to this newspaper. “We remain committed to providing members of the Royal Canadian Air Force with the fighter aircraft they need to do their jobs, and ensuring the best possible value for Canadians,” he added. “This procurement is a once in a generation opportunity to support the growth of Canada's aerospace and defence industries for decades to come.” If that happens it is unclear on how the current timetable for buying the fighter jets, to replace the CF-18 aircraft, might be affected. A winning bidder was to have been chosen in 2022. The first aircraft would have been delivered by 2025, according to the government's schedule. Industry representatives say they expect the bid submissions to be pushed back at least until the end of the summer. The federal government is focused on dealing with its response to the novel coronavirus pandemic and Public Services and Procurement Canada is deeply involved in setting up procurements of protective gear and medical supplies. It has also been difficult for companies to collect and provide the necessary classified information to the federal government that is needed for the bids. Much of that has to be delivered directly to government officials and cannot be transmitted over the internet because of the sensitivity of the information. The fighter jet competition was launched on Dec. 12, 2017 and at this point three aircraft are to be considered. Those include the F-35, the Super Hornet, and the Gripen. The program is expected to cost around $19 billion and will see the purchase of 88 new jets. Information about how Canada intends to evaluate the jets is limited. But Public Services and Procurement Canada has noted that technical merit will make up the bulk of the assessment at 60 per cent. Cost and economic benefits companies can provide to Canada will each be worth 20 per cent. But Canada won't conduct a fly-off between fighter jets competing to become the country's new warplane nor conduct testing to see how such aircraft perform under cold weather conditions, Public Services and Procurement Canada confirmed earlier this year. Concerns have been raised by Lockheed Martin's rivals that the competition has been designed to favour the F-35. This newspaper reported last year the requirements for the new jets put emphasis on strategic attack and striking at ground targets during foreign missions. That criteria is seen to benefit the F-35. In addition, the federal government changed criteria on how it would assess industrial benefits after the U.S. government threatened to pull the F-35 from the competition. The Conservative government had previously selected the F-35 as the air force's new jet but backed away from that plan after concerns about the technology and growing cost. During the 2015 election campaign, Justin Trudeau vowed that his government would not purchase the F-35. But at the same time, Trudeau stated his government would hold an open competition for the fighter purchase. The Liberal government backed away from its promise to freeze out the F-35 and the aircraft is now seen as a front-runner in the competition as it has many supporters in the Royal Canadian Air Force. Many of Canada's allies plan to operate the plane. Canada is a partner in the F-35 program and has contributed funding for the aircraft's development over the years. It has already made its latest payment on that program. https://ottawacitizen.com/news/national/defence-watch/federal-government-considering-delaying-acceptance-of-bids-for-new-fighter-jets/wcm/2c331c83-e437-45d8-8d1c-9be59ccb7dc3/

All news