Back to news

June 4, 2020 | International, C4ISR, Security

Watchdog says Pentagon needs better planning for IP update 17 years after first attempt

A federal watchdog found that poor planning by the Department of Defense has blurred the department's understanding of the risks and costs associated with upgrading the system that routes internet traffic across the globe, known as Internet Protocol version 6 (IPv6).

According to a June 1 report from the Government Accountability Office, the Pentagon needs to improve its transition planning for the most recent effort, which began in April 2017. The DoD has tried twice previously to implement IPv6 in 2003 and 2010, but stopped those transitions after identifying security risks and lacking adequately trained personnel.

The problem for the DoD is that IPv4, the IP management system the DoD uses, is running out of address space. IPv4 only has room for 4.3 billion addresses. In contrast, IPv6, created in the 1990s, provides about 340,000,000,000,000,000,000,000,000,000,000,000,000 (undecillion) IP addresses. The Defense Department owns approximately 300 million IP addresses with about 59.8 million unused and planned for use by future DoD components. The department estimates it will run out of its unused IP addresses by 2030.

The department's IPv6 implementation plan from early 2019 listed 35 actions needed to switch over from IPv4. Eighteen of those steps were scheduled to be completed by March 2020. The report said six of the 18 tasks were completed on time.

Upgrading to IPv6 would increase connectivity, add security, improve the warfighter's connection and communications on the battlefield, and preserve interoperability with allied systems, the GAO wrote.

The watchdog found that the department was not compliant with several IPv6 transition requirements from the White House's Office of Management and Budget. The DoD hasn't completed a cost estimate, developed a risk analysis or finished an inventory of IP compliant devices, the report said. Pentagon officials told the GAO that they knew their time frame for the transition was “optimistic," adding that they thought the pace was reasonable "until they started performing the work,” the GAO wrote.

“Without an inventory, a cost estimate, or a risk analysis, DOD significantly reduced the probability that it could have developed a realistic transition schedule,” the GAO wrote. “Addressing these basic planning requirements would supply DOD with needed information that would enable the department to develop realistic, detailed, and informed transition plans and time frames.”

The Department did meet OMB's requirement to name an official to lead and coordinate the agency planning. But because the Pentagon failed to complete the other three OMB requirements. the move is at risk.

“Without an inventory, a cost estimate, or a risk analysis, DOD's plans have a high degree of uncertainty about the magnitude of work involved, the level of resources required, and the extent and nature of threats, including cybersecurity risks,” the GAO wrote.

Among the DoD's goals it did complete are several IPv6 training programs, information sharing opportunities and a program management office.

The GAO recommended that Defense Secretary Mark Esper direct the DoD chief information officer to complete an inventory of IP-compliant devices, develop a cost estimate and perform a risk analysis. The DoD agreed that it needed to develop a cost estimate and risk analysis but didn't concur that it needed to inventory devices, citing new guidance from OMB and calling an inventory “impractical” because of the department's size.

“The lack of an inventory is problematic due to the role that it should play in developing transition requirements,” the GAO wrote.

https://www.c4isrnet.com/it-networks/2020/06/02/watchdog-says-pentagon-needs-better-planning-for-ip-update-17-years-after-first-attempt/

On the same subject

  • Army Study Asks: How Much Modernization Can We Afford?

    June 10, 2020 | International, Aerospace, Naval, Land, C4ISR, Security

    Army Study Asks: How Much Modernization Can We Afford?

    The Army's drive to modernize by 2035 is too big for traditional five-year spending plans, acquisition chief Bruce Jette said. So he's reviving long-term economic forecasting used in the Cold War. By SYDNEY J. FREEDBERG JR.on June 09, 2020 at 12:37 PM WASHINGTON: The Army's acquisition chief says the service is sticking with its 34 top-priority programs – in the face of budget pressure from the pandemic. But most of those programs will only move from prototypes to mass production in the second half of the 2020s; then they stay in service for decades with repeated upgrades. So, assistant secretary Bruce Jette says, the Army needs to exploit new technologies like 3D printing and modular upgrades to reduce long-term costs – but also revive long-term economic forecasting techniques largely neglected since the Cold War. “At this point, we're remaining on schedule with the ‘31 plus 3,'” Jette said during an Association of the US Army webcast yesterday. (The Army divides the 34 programs this way because 31 of them, from intermediate-range missiles to smart rifles, are managed by Army Futures Command, but three of the most technologically challenging – hypersonic missiles and two types of missile defense lasers – belong to the independent Rapid Capabilities & Critical Technologies Office). But the service needs to do more planning: “A second thing in the background that we are doing is taking a look at a holistic model, an economic model of the Army.” “We are taking some steps to provide additional data in case there's a prioritization that does come down the road, due to changes in the budget profiles,” Jette said. “That business requires us to have this long-term full understanding of economics, which is what we're focused on trying to develop over the next year.” That study will help inform Army leaders if they have to make a hard choice on which of the 34 priority programs to put first – and, while Jette didn't say so aloud, which may be cut back or canceled entirely. Beyond 2026 The Pentagon normally builds its annual budget two years ahead of time. Congress is now considering the 2021 request, largely drafted in 2019. Those budgets include a less-detailed annex, called the Future Years Defense Program (FYDP) that outlines the five years ahead. Now, some of the Army's new weapons will enter service in that timeframe, in limited numbers, including new hypersonic and intermediate-range missiles in 2023. But many, including some of the most expensive, will take longer. So new armored vehicles won't enter service until 2028, new high-speed aircraft not until 2030. Actually building enough to equip a sizable combat force takes even longer. The Army aims to build a decisive counter to Russian aggression by 2028, but expect a force adequate to counter China only by 2035. “I have to have a much longer view of the battlespace, the economic battle space,” Jette said. “The objective [is] to lay a foundation upon which we can take a serious look at what the long-term implications of owning a piece of equipment,” he said. So “I'm working with the G-8 [the Army's deputy chief of staff for resourcing]. In fact, we just had a meeting on this last week to pull out some models that were actually used more in the Cold War, that we sort of let wane [during] Iraq and Afghanistan.... Next week I go up to West Point to have ORSA [Operations Research/Systems Analysis] cell up there that specifically is focused on economics.” New Tricks Now, the Army doesn't plan to simply repeat its Cold War past. The Reagan-era “Big Five” – the M1 Abrams and M2 Bradley armored vehicles, Apache and Black Hawk helicopters, and Patriot missile defense system – have been repeatedly upgraded since their inception. But these platforms are running out of room for more horsepower, armor protection, and firepower, and they were never designed to allow the constant upgrades required to keep pace with modern advances in electronics. The M1 Abrams, for instance, is literally hard-wired. “There are literally, in a tank, over a couple of tons of cabling, all tremendously expensive and all very, very structured,” said Jette, a former tanker himself. “So if you want to change something ... you have to re-cable large portions of it.” The Army must account not only for the up-front cost to research, develop, and build the new weapons, Jette emphasized, but also the much larger long-term bill to operate, maintain and upgrade them. “If we don't think about how it's going to be enhance-able, upgradable, and modified for different uses over a period of time,” he said, “we're missing things, because we do keep them for 30, 40 years. “For industry, if you have a good idea and a new component, how do we get them in a vehicle without having to replace half of the components?” he asked. That requires a new approach called modular open systems architecture that allows you to plug-and-play any new component as long as it meets certain technical standards. “By getting this much more open architecture in place on these vehicles,” he said, “we think that we're going to be able to keep them growing to the future over that 30 to 40 year period.” The Army is also eager to use digital designs, 3D printing, and other advanced manufacturing techniques so it can print out spare parts as needed, rather than stockpile vast quantities of everything it might need for every system. (Jette just visited the Army's 3-D printing hub at Rock Island Arsenal, he said enthusiastically). But this vision raises complex issues of not only managing the technical data but wrangling out the legal rights to use it. Many companies depend on the long-term revenue from selling spares and upgrades, and they're not It's a knotty intellectual property issue that Jette is keenly aware of, being a patent-holder and former small businessman himself. “I do understand ... what type of risk it is. I'll frankly admit that many of the people in the military who fundamentally only been in the military don't understand,” Jette said. “If the risk is totally on you, and it makes no economic sense, I recommend you not answering the RFP.” If too few companies respond to an official Request For Proposals, Jette said, that provides valuable feedback to the Army that maybe it's doing something wrong – feedback he can use in his own quest to educate the service. “Sometimes,” he said, “challenges to RFPs are a good way for you to help me to make sure that people understand that this is too much risk we're asking of industry.” https://breakingdefense.com/2020/06/army-study-asks-how-much-modernization-can-we-afford

  • Army numbers smallest since WWII — what units face cuts in 2024?

    December 28, 2023 | International, Security

    Army numbers smallest since WWII — what units face cuts in 2024?

    What steps will the Army take to avoid becoming hollow?

  • LOCKHEED MARTIN AND FINCANTIERI MARINETTE MARINE AWARDED CONTRACT TO BUILD LITTORAL COMBAT SHIP 29

    September 28, 2018 | International, Naval

    LOCKHEED MARTIN AND FINCANTIERI MARINETTE MARINE AWARDED CONTRACT TO BUILD LITTORAL COMBAT SHIP 29

    Construction will begin in first half of 2019 WASHINGTON, Sept. 27, 2018 – The U.S. Navy awarded the Lockheed Martin (NYSE: LMT) and Fincantieri Marinette Marine (FMM) team a fixed price incentive fee contract to build an additional Littoral Combat Ship (LCS). LCS 29 will be built in Marinette, Wisconsin, at FMM, the Midwest's only naval shipyard, and is the 15th Freedom-variant LCS ordered by the U.S. Navy to date. The team will leverage capital investment and improvement in the shipyard and efficiencies created with serial production to maintain high quality at an affordable cost. "We are excited to continue our partnership with the U.S. Navy and FMM to build and deliver increasingly capable ships to the fleet,” said Joe DePietro, vice president, Lockheed Martin Small Combatants and Ship Systems. "With the Freedom-variant in serial production, we continue to enhance efficiency, incorporate capability while maintaining ship and program affordability." Since the LCS program's inception, Freedom-variant LCS production has injected hundreds of millions of dollars into local economies throughout the Midwest. The program supports thousands of direct and indirect jobs throughout the United States, including more than 7,500 in Michigan and Wisconsin alone. The Lockheed Martin and FMM team is in full-rate production of the Freedom-variant, and has delivered seven ships to the U.S. Navy to date, including two this year – the future USS Sioux City and the future USS Wichita. There are seven ships in various stages of construction at Fincantieri Marinette Marine. Lockheed Martin's Freedom-variant LCS is highly maneuverable, lethal and adaptable. Originally designed to support focused missions such as mine warfare, anti-submarine warfare and surface warfare, the team continues to evolve capabilities based on rigorous Navy operational testing; sailor feedback and multiple successful fleet deployments. The Freedom-variant LCS integrates new technology and capability to affordably support current and future mission capability from deep water to the littorals. For additional information, visit: www.lockheedmartin.com/lcs. About Lockheed Martin Headquartered in Bethesda, Maryland, Lockheed Martin is a global security and aerospace company that employs approximately 100,000 people worldwide and is principally engaged in the research, design, development, manufacture, integration and sustainment of advanced technology systems, products and services. This year the company received three Edison Awards for ground-breaking innovations in autonomy, satellite technology and directed energy. About Fincantieri Marinette Marine Fincantieri is the leading western shipbuilder with a rich history dating back more than 230 years, and a track record of building more than 7,000 ships. Fincantieri Marine Group is the American subsidiary of Fincantieri, and operates three Great Lakes Shipyards: Fincantieri Marinette Marine, Fincantieri Bay Shipbuilding, and Fincantieri ACE Marine. Fincantieri Marine Group's more than 2,100 steelworkers, craftsman, engineers and technicians in the United States specialize in the design, construction and maintenance of merchant ships and government vessels, including for the United States Navy and Coast Guard. About Gibbs & Cox Gibbs & Cox, the nation's leading independent maritime solutions firm specializing in naval architecture, marine engineering and design, is headquartered in Arlington, Virginia. The company, founded in 1929, has provided designs for nearly 80 percent of the current U.S. Navy surface combatant fleet; approaching 7,000 naval and commercial ships have been built to Gibbs & Cox designs. https://news.lockheedmartin.com/2018-09-27-Lockheed-Martin-and-Fincantieri-Marinette-Marine-Awarded-Contract-to-Build-LCS-29

All news