July 3, 2019 | International, Aerospace

United Technologies’ F-35 Engines Chronically Late, Pentagon Says

By

United Technologies Corp.'s Pratt & Whitney unit is chronically late delivering engines for the Pentagon's costliest program, the F-35, raising questions about whether the company is ready for a surge to full-rate production scheduled for next year.

Pratt remains under a previously unreported “Corrective Action Request” from the Defense Contract Management Agency that cites “poor delivery performance” on its current batch of engines for the fighter jet, including for the most complicated version used by the Marine Corps and the U.K. for vertical takeoffs and landings.

The agency's action is likely to be watched not only by the Pentagon and international buyers of the F-35 but also by shareholders and investors assessing United Technologies' planned merger with Raytheon Co., which would fortify the combined company's standing as one of the top U.S. defense contractors. The F-35 engines would be one of the new company's top revenue producers.

United Technologies Corp.'s Pratt & Whitney unit is chronically late delivering engines for the Pentagon's costliest program, the F-35, raising questions about whether the company is ready for a surge to full-rate production scheduled for next year.

Pratt remains under a previously unreported “Corrective Action Request” from the Defense Contract Management Agency that cites “poor delivery performance” on its current batch of engines for the fighter jet, including for the most complicated version used by the Marine Corps and the U.K. for vertical takeoffs and landings.

The agency's action is likely to be watched not only by the Pentagon and international buyers of the F-35 but also by shareholders and investors assessing United Technologies' planned merger with Raytheon Co., which would fortify the combined company's standing as one of the top U.S. defense contractors. The F-35 engines would be one of the new company's top revenue producers.

The company, which is the sole supplier of engines for the fighter built by Lockheed Martin Corp., must demonstrate by year-end that it has delivered on promised improvements to solve the problems that led to the agency's formal request in December, spokesman Mark Woodbury said in a statement outlining the issues.

Full Production

The $428 billion F-35 program is scheduled for approval next year to enter full-rate production, the most lucrative phase of a weapons program for contractors. The decision is contingent on an assessment during the aircraft's current round of intensive combat testing that it's effective and can be maintained.

Of the $428 billion, as much as $66 billion is to be spent on at least 2,470 engines -- designated the F135 -- for U.S. jets, including $53.4 billion in procurement, according to the Defense Department's latest Selected Acquisition Report on the F-35.

Pentagon budget documents indicate the engine program is valued at about $2 billion annually for Pratt, according to Bloomberg Intelligence analyst Douglas Rothacker.

John Thomas, a spokesman for Pratt, said in an emailed statement that “we take seriously our responsibility to meet F135 production commitments. The corrective action plan submitted earlier this year lays out how we are doing that. Over the past year, we have invested more than $200 million for additional capacity, and currently have over 100 Pratt & Whitney employees deployed to our supplier facilities in support of production obligations.”

Revenue Potential

Pratt & Whitney President Bob Leduc underscored the engine's revenue potential to analysts June 17 at the Paris Air Show.

United Technologies Corp.'s Pratt & Whitney unit is chronically late delivering engines for the Pentagon's costliest program, the F-35, raising questions about whether the company is ready for a surge to full-rate production scheduled for next year.

Pratt remains under a previously unreported “Corrective Action Request” from the Defense Contract Management Agency that cites “poor delivery performance” on its current batch of engines for the fighter jet, including for the most complicated version used by the Marine Corps and the U.K. for vertical takeoffs and landings.

The agency's action is likely to be watched not only by the Pentagon and international buyers of the F-35 but also by shareholders and investors assessing United Technologies' planned merger with Raytheon Co., which would fortify the combined company's standing as one of the top U.S. defense contractors. The F-35 engines would be one of the new company's top revenue producers.

The company, which is the sole supplier of engines for the fighter built by Lockheed Martin Corp., must demonstrate by year-end that it has delivered on promised improvements to solve the problems that led to the agency's formal request in December, spokesman Mark Woodbury said in a statement outlining the issues.

Full Production

The $428 billion F-35 program is scheduled for approval next year to enter full-rate production, the most lucrative phase of a weapons program for contractors. The decision is contingent on an assessment during the aircraft's current round of intensive combat testing that it's effective and can be maintained.

Of the $428 billion, as much as $66 billion is to be spent on at least 2,470 engines -- designated the F135 -- for U.S. jets, including $53.4 billion in procurement, according to the Defense Department's latest Selected Acquisition Report on the F-35.

Pentagon budget documents indicate the engine program is valued at about $2 billion annually for Pratt, according to Bloomberg Intelligence analyst Douglas Rothacker.

John Thomas, a spokesman for Pratt, said in an emailed statement that “we take seriously our responsibility to meet F135 production commitments. The corrective action plan submitted earlier this year lays out how we are doing that. Over the past year, we have invested more than $200 million for additional capacity, and currently have over 100 Pratt & Whitney employees deployed to our supplier facilities in support of production obligations.”

Revenue Potential

Pratt & Whitney President Bob Leduc underscored the engine's revenue potential to analysts June 17 at the Paris Air Show.

“So another way to think about the F135 is a year ago we made about eight engines a month,” he said. “Right now we are between 13 and 14 engines a month. But when you think about the F135, it's 16 engines a month for the next 30 years. There will be over 4,000 of these airplanes when it's all said and done,” including foreign sales.

The primary issues resulting in late engine deliveries “have been related to supply-chain capacity, material shortages” and production issues, according to the contract management agency.

“Engine test failures due to high vibrations and foreign object debris continues to plague” production, the agency said in an internal quarterly assessment for January through March. Deliveries of the Marine Corps model engines “have been consistently late,” it said.

As of early June, Pratt & Whitney was contractually required to deliver 108 engines in the latest production contract, the program's 11th. Of the 90 delivered, 88 were “late by an average of 40 days,” Woodbury said in his statement. The Pentagon is close to finalizing the award of the 12th and largest F-35 contract to date with Lockheed and Pratt.

Spotty Record

The current delays add to Pratt & Whitney's spotty track record. Even as deliveries increased to 81 in 2018 from 48 in 2012, 86% of those were delivered late, up from 48% in late 2017, according to an April report from the Government Accountability Office.

Asked whether the contract management agency has confidence Pratt will be ready for a full-production decision, Woodbury said the agency is monitoring milestones in Pratt's corrective action plan and needs to see progress before making that judgment.

The agency's assessment said that in light of Pratt & Whitney's track record it believes the company “will encounter issues keeping up with demand for any future low-rate and full-rate production contract” that increases quantities.

— With assistance by Rick Clough

https://www.bloomberg.com/news/articles/2019-07-02/united-technologies-pratt-slow-on-f-35-engines-pentagon-says

On the same subject

  • Contract Awards by US Department of Defense - October 17, 2018

    October 18, 2018 | International, Aerospace, Naval, Land, C4ISR, Security

    Contract Awards by US Department of Defense - October 17, 2018

    NAVY Northrop Grumman Systems Corp., doing business as Northrop Grumman Mission Systems Sector, Bethpage, New York, is awarded a $697,029,788 indefinite-delivery/indefinite-quantity contract for system upgrades for the EA-18G system configuration sets, Airborne Electronic Attack and Electronic Warfare systems and final upgrades for the EA-6B system for the Navy and the government of Australia under the Foreign Military Sales program. Work will be performed in Pt. Mugu, California (50 percent); Baltimore, Maryland (29 percent); Bethpage, New York (20 percent); and Rolling Meadows, Illinois (1 percent), and is expected to be completed in October 2023. Fiscal 2019 operations and maintenance (Navy) funds in amount of $996,902 are being obligated at time of award, all of which will expire at the end of the current fiscal year. This contract was not competitively procured pursuant to Federal Acquisition Regulation 6.302-1. The Naval Air Warfare Center Weapons Division, Point Mugu, California, is the contracting activity (N68936-19-D-0007). LGS Innovations LLC, Westminster, Colorado, is awarded a $15,528,008 indefinite-delivery/indefinite-quantity, cost-plus-fixed-fee, firm-fixed-price contract for engineering services, materials, training, and testing to support integration and operation of information operations payloads into unmanned aerial vehicles used by the U.S. Special Operations Command and the Navy. This two-year contract includes a three-year option which, if exercised, would bring the cumulative value of this contract to an estimated $34,996,905. Work will be performed across three geographic zones in the areas of Westminster, Colorado (40 percent); Florham Park, New Jersey (40 percent); and Jessup, Maryland (20 percent). The work is expected to be completed Oct. 16, 2020. If the option is exercised, the period of performance would extend through Oct. 16, 2023. No funds will be obligated at the time of award. Funding will be obligated via task/delivery orders using anticipated types of funding to include: operations and maintenance (Navy); other procurement (Navy); and research, development, test and evaluation (Navy). Contract funds will not expire at the end of the current fiscal year. This sole-source procurement is issued using other than full and open competition in accordance with Federal Acquisition Regulation Subpart 6.302-1 and 10 U.S. Code 2304(c)(1) - only one responsible source. The Space and Naval Warfare Systems Center Pacific, San Diego, California, is the contracting activity (N66001-19-D-3401). Wiley Wilson Burns and McDonnell JV, Alexandria, Virginia, is awarded $15,000,000 firm-fixed-price modification under a previously awarded indefinite-quantity architect-engineering contract (N40080-15-D-0452) to exercise option four for engineering and design services for general and administrative facilities within the Naval Facilities Engineering Command. The total contract amount after exercise of this option will be is $75,000,000. No task orders are being issued at this time. Work will be performed at various administrative facilities within the Naval Facilities Engineering Command Washington area of responsibility, including but not limited to, Maryland (45 percent); Washington, District of Columbia (30 percent); and Virginia (20 percent). Work may also be performed in the remainder of the U.S. (5 percent), and is expected to be completed in October 2019. No funds will be obligated at time of award; funds will be obligated on individual task orders as they are issued. Task orders will be primarily funded by fiscal 2019 operations and maintenance (Navy and Marine Corps); and fiscal 2019 Navy working capital funds. The Naval Facilities Engineering Command, Washington, Washington, District of Columbia, is the contracting activity. Rockwell Collins Inc. Government Systems Division, Cedar Rapids, Iowa, is awarded a $7,062,238 five-year long-term contract for repair of 22 various navigation and communication items that are a part of the KC-130J, H-1, E-2C, P-3, common systems and other aircraft. Work will be performed at contractor facilities in Atlanta, Georgia; Cedar Rapids, Iowa; Calexico, California; and Wichita, Kansas. The percentage of work at each of those locations cannot be determined at this time, and work is expected to be completed by October 2023. Working capital (Navy) funds will be obligated as individual task orders are issued and funds will not expire at the end of the current fiscal year. One firm was solicited for this non-competitive requirement under authority 10 U.S. Code 2304 (c)(1) and Federal Acquisition Regulation 6.302-1. The requirement was posted to the Federal Business Opportunities website and the Navy Electronic Commerce Online website, with one offer received. Naval Supply Systems Command Weapon Systems Support, Philadelphia, Pennsylvania, is the contracting activity (N00383-19-D-PS01). General Electric Co., Lynn, Massachusetts, was awarded $7,041,528 for modification P00012 to a previously awarded firm-fixed-price contract (N00019-17-C-0047) for the procurement of 24 F414-GE-400 engine devices for Lot 42 F/A-18 aircraft. Work will be performed in Evendale, Ohio, and is expected to be completed in February 2019. Fiscal 2018 aircraft procurement (Navy) funds in the amount $7,041,528 will be obligated at time of award, none of which will expire at the end of the current fiscal year. The Naval Air Systems Command, Patuxent River, Maryland, is the contracting activity. (Awarded Oct. 15, 2018) AIR FORCE The Boeing Co., Layton, Utah, has been awarded a $55,567,613 undefinitized, firm-price incentive-fee contract, for Intercontinental Ballistic Missile Cryptography Upgrade Increment II production. This contract provides for the government's minimum requirement of the production of 75 message processor drawers; 8 digital components; and program management support. Work will be performed in Huntsville, Alabama; and Huntington Beach, California, and is expected to be completed by Feb. 11, 2019. This award is the result of a sole-source acquisition and one offer was received. Fiscal 2018 missile procurement funds in the amount of $17,864,050 are being obligated at the time of award. Intercontinental Ballistic Missile Contracting Division, Hill Air Force Base, Utah, is the contracting activity (FA8204-19-C-0001). ARMY TGS USA,* McLean, Virginia, was awarded a $39,543,009 firm-fixed-price Foreign Military Sales (Iraq) contract for Toyota Land Cruisers and spare parts. Bids were solicited via the internet with three received. Work locations and funding will be determined with each order, with an estimated completion date of Oct. 16, 2018. U.S. Army Contracting Command, Warren, Michigan, is the contracting activity (W56HZV-19-D-0010). DEFENSE LOGISTICS AGENCY UPDATE: US Eco Products Corp., Haverhill, Massachusetts (SPE8EC-19-D-0030), has been added as an awardee to the multiple-award contract for commercial snow removal equipment, issued against solicitation SPE8EC-17-R-0009, announced May 5, 2017. *Small Business https://dod.defense.gov/News/Contracts/Contract-View/Article/1664968/source/GovDelivery/

  • South Korea and Spain seek deal to swap trainer jets for airlifters

    November 7, 2018 | International, Aerospace

    South Korea and Spain seek deal to swap trainer jets for airlifters

    By: Jeff Jeong SEOUL — South Korean and Spanish defense officials are to discuss a possible trade of trainer and transport aircraft, according to arms procurement officials and industry sources in the Asian nation. The deal may involve about 50 basic and advanced trainer jets built by Korea Aerospace Industries, or KAI, and four to six Airbus A400M airlifters, they said. “South Korea and Spain plan to hold a joint defense industry committee in Madrid this month to discuss bilateral issues,” said an official with the Defense Acquisition Program Administration, speaking on condition of anonymity. “The swap deal is not an official agenda item on the table, but the sides are open to discussing it.” The proposal was made by Spain during the Farnborough International Airshow in the U.K. last July, as the Spanish Air Force seeks to replace its older trainer fleet of Chilean ENAER T-35C Pillan jets, according to an industry source privy to the potential swap deal. “Spain ordered 27 A400M transport aircraft from Airbus but has decided not to use 13 of them, so the Spanish defense authorities have got approval from Airbus to sell the surplus products to other countries,” the source said. “Spain wants to sell four to six A400Ms to South Korea, and it buys 34 KT-1 basic trainer aircraft and 20 more T-50 supersonic trainer jets for advanced pilot training if possible.” If the deal is reached, Spain is willing to sell the A400M plane at 15 percent of the per-unit price of some $27 million, he said, adding the total value of the swap deal could be approximately $890 million. The envisaged deal could be a breakthrough for KAI to sell more of its trainer aircraft after its recent defeat in a U.S. Air Force trainer competition. “Any swap deal is delegated to the DAPA and its Spanish counterpart, and we're waiting on the results,” a KAI spokesman said. Airbus would not discuss the prospect of such a deal. Industry sources believe the proposed deal could meet the South Korean Air Force's need of acquiring larger airlifters for longer-range missions. During an Oct. 19 parliamentary inspection of the Air Force, the service revealed a plan to procure four more large transport aircraft in addition to its existing fleet of CN-235 and C-130 planes. “We have a plan to deploy larger transport aircraft to increase our capacity of rapid force deployment, emergency relief, peacekeeping and other operations over long distances,” Air Force Chief of Staff Gen. Lee Wang-keun said in a report to lawmakers. Preliminary research on the requirements of the larger airlifter acquisition will be conducted between 2019 and 2020 before a request for proposal is issued for full operational capability by 2022, according to Air Force officials. The A400M Atlas is regarded as a strong candidate for the airlift procurement program, as the C-17 Globemaster III production line run by Boeing is shut down. The A400M can carry 116 fully equipped troops and up to 66 stretchers accompanied by 25 medical personnel. Email: jeff@defensenews.com https://www.defensenews.com/air/2018/11/05/south-korea-and-spain-seek-deal-to-swap-trainer-jets-for-airlifters

  • Germany announces deal to repair tanks for Ukraine at hub in Poland

    April 21, 2023 | International, Land

    Germany announces deal to repair tanks for Ukraine at hub in Poland

    Germany, Poland and Ukraine signed an agreement on Friday for a hub to repair Leopard tanks used in Ukraine to fight Russian forces, Germany's Defence Minister Boris Pistorius said at a meeting of allies at the Ramstein air base.

All news