3 juillet 2019 | International, Aérospatial

United Technologies’ F-35 Engines Chronically Late, Pentagon Says

By

United Technologies Corp.'s Pratt & Whitney unit is chronically late delivering engines for the Pentagon's costliest program, the F-35, raising questions about whether the company is ready for a surge to full-rate production scheduled for next year.

Pratt remains under a previously unreported “Corrective Action Request” from the Defense Contract Management Agency that cites “poor delivery performance” on its current batch of engines for the fighter jet, including for the most complicated version used by the Marine Corps and the U.K. for vertical takeoffs and landings.

The agency's action is likely to be watched not only by the Pentagon and international buyers of the F-35 but also by shareholders and investors assessing United Technologies' planned merger with Raytheon Co., which would fortify the combined company's standing as one of the top U.S. defense contractors. The F-35 engines would be one of the new company's top revenue producers.

United Technologies Corp.'s Pratt & Whitney unit is chronically late delivering engines for the Pentagon's costliest program, the F-35, raising questions about whether the company is ready for a surge to full-rate production scheduled for next year.

Pratt remains under a previously unreported “Corrective Action Request” from the Defense Contract Management Agency that cites “poor delivery performance” on its current batch of engines for the fighter jet, including for the most complicated version used by the Marine Corps and the U.K. for vertical takeoffs and landings.

The agency's action is likely to be watched not only by the Pentagon and international buyers of the F-35 but also by shareholders and investors assessing United Technologies' planned merger with Raytheon Co., which would fortify the combined company's standing as one of the top U.S. defense contractors. The F-35 engines would be one of the new company's top revenue producers.

The company, which is the sole supplier of engines for the fighter built by Lockheed Martin Corp., must demonstrate by year-end that it has delivered on promised improvements to solve the problems that led to the agency's formal request in December, spokesman Mark Woodbury said in a statement outlining the issues.

Full Production

The $428 billion F-35 program is scheduled for approval next year to enter full-rate production, the most lucrative phase of a weapons program for contractors. The decision is contingent on an assessment during the aircraft's current round of intensive combat testing that it's effective and can be maintained.

Of the $428 billion, as much as $66 billion is to be spent on at least 2,470 engines -- designated the F135 -- for U.S. jets, including $53.4 billion in procurement, according to the Defense Department's latest Selected Acquisition Report on the F-35.

Pentagon budget documents indicate the engine program is valued at about $2 billion annually for Pratt, according to Bloomberg Intelligence analyst Douglas Rothacker.

John Thomas, a spokesman for Pratt, said in an emailed statement that “we take seriously our responsibility to meet F135 production commitments. The corrective action plan submitted earlier this year lays out how we are doing that. Over the past year, we have invested more than $200 million for additional capacity, and currently have over 100 Pratt & Whitney employees deployed to our supplier facilities in support of production obligations.”

Revenue Potential

Pratt & Whitney President Bob Leduc underscored the engine's revenue potential to analysts June 17 at the Paris Air Show.

United Technologies Corp.'s Pratt & Whitney unit is chronically late delivering engines for the Pentagon's costliest program, the F-35, raising questions about whether the company is ready for a surge to full-rate production scheduled for next year.

Pratt remains under a previously unreported “Corrective Action Request” from the Defense Contract Management Agency that cites “poor delivery performance” on its current batch of engines for the fighter jet, including for the most complicated version used by the Marine Corps and the U.K. for vertical takeoffs and landings.

The agency's action is likely to be watched not only by the Pentagon and international buyers of the F-35 but also by shareholders and investors assessing United Technologies' planned merger with Raytheon Co., which would fortify the combined company's standing as one of the top U.S. defense contractors. The F-35 engines would be one of the new company's top revenue producers.

The company, which is the sole supplier of engines for the fighter built by Lockheed Martin Corp., must demonstrate by year-end that it has delivered on promised improvements to solve the problems that led to the agency's formal request in December, spokesman Mark Woodbury said in a statement outlining the issues.

Full Production

The $428 billion F-35 program is scheduled for approval next year to enter full-rate production, the most lucrative phase of a weapons program for contractors. The decision is contingent on an assessment during the aircraft's current round of intensive combat testing that it's effective and can be maintained.

Of the $428 billion, as much as $66 billion is to be spent on at least 2,470 engines -- designated the F135 -- for U.S. jets, including $53.4 billion in procurement, according to the Defense Department's latest Selected Acquisition Report on the F-35.

Pentagon budget documents indicate the engine program is valued at about $2 billion annually for Pratt, according to Bloomberg Intelligence analyst Douglas Rothacker.

John Thomas, a spokesman for Pratt, said in an emailed statement that “we take seriously our responsibility to meet F135 production commitments. The corrective action plan submitted earlier this year lays out how we are doing that. Over the past year, we have invested more than $200 million for additional capacity, and currently have over 100 Pratt & Whitney employees deployed to our supplier facilities in support of production obligations.”

Revenue Potential

Pratt & Whitney President Bob Leduc underscored the engine's revenue potential to analysts June 17 at the Paris Air Show.

“So another way to think about the F135 is a year ago we made about eight engines a month,” he said. “Right now we are between 13 and 14 engines a month. But when you think about the F135, it's 16 engines a month for the next 30 years. There will be over 4,000 of these airplanes when it's all said and done,” including foreign sales.

The primary issues resulting in late engine deliveries “have been related to supply-chain capacity, material shortages” and production issues, according to the contract management agency.

“Engine test failures due to high vibrations and foreign object debris continues to plague” production, the agency said in an internal quarterly assessment for January through March. Deliveries of the Marine Corps model engines “have been consistently late,” it said.

As of early June, Pratt & Whitney was contractually required to deliver 108 engines in the latest production contract, the program's 11th. Of the 90 delivered, 88 were “late by an average of 40 days,” Woodbury said in his statement. The Pentagon is close to finalizing the award of the 12th and largest F-35 contract to date with Lockheed and Pratt.

Spotty Record

The current delays add to Pratt & Whitney's spotty track record. Even as deliveries increased to 81 in 2018 from 48 in 2012, 86% of those were delivered late, up from 48% in late 2017, according to an April report from the Government Accountability Office.

Asked whether the contract management agency has confidence Pratt will be ready for a full-production decision, Woodbury said the agency is monitoring milestones in Pratt's corrective action plan and needs to see progress before making that judgment.

The agency's assessment said that in light of Pratt & Whitney's track record it believes the company “will encounter issues keeping up with demand for any future low-rate and full-rate production contract” that increases quantities.

— With assistance by Rick Clough

https://www.bloomberg.com/news/articles/2019-07-02/united-technologies-pratt-slow-on-f-35-engines-pentagon-says

Sur le même sujet

  • These Baltic nations could build Europe’s next ground drone

    3 août 2018 | International, Terrestre

    These Baltic nations could build Europe’s next ground drone

    By: Aaron Mehta WASHINGTON — As European Union nations look to step up their defense-industrial projects, a trio of states on the Baltic Sea are looking to make a breakthrough in unmanned ground systems. Estonia, Latvia and Finland are pushing to develop land-based drones under the EU's Permanent Structure Cooperation framework, or PESCO, the nations announced Thursday. Between €30-40 million (U.S. $35-47 million) has been earmarked for use from the European Defence Fund to work on the project, while each of the three countries will contribute additional funds. The start date for the planned project is the first half of 2019. Launched in late 2017, PESCO seeks to help develop European-wide defense industries. Groups of nations can pitch the EU on different developments in order to secure initial funding from pooled resources. Although in its early stages, PESCO has been the topic of American concernover the potential of protectionist actions taken by the European defense market that could lock out American firms. EU nations are now looking to carve out market areas that could benefit their domestic defense-industrial bases, something acknowledged directly by Kusti Salm, director of the Estonian Defense Ministry's Defence Investments Department. Full article: https://www.defensenews.com/global/europe/2018/08/02/these-baltic-nations-could-build-europes-next-ground-drone

  • Updating software in flight? The Air Force may be close.

    17 septembre 2020 | International, Aérospatial

    Updating software in flight? The Air Force may be close.

    Andrew Eversden WASHINGTON — The U.S. Air Force will soon announce that the service can update an aircraft's software while in flight, the Air Force's chief software officer said Tuesday. Nicolas Chaillan, the service's software czar, hinted at the announcement during a wide-ranging interview on a webcast hosted by C4ISRNET, but he declined to share which aircraft could handle the upgrade before the formal announcement is made. The update is part of a larger push by the Air Force to modernize its software practices. However, Chaillan described the news as a “gamechanger” and offered insight into the challenges associated with updating software during flights. “We need to decouple the flight controls, the [open mission systems], all the air worthiness piece of the software from the rest of the mission [and] capability of [that] software so we can update those more frequently without disrupting or putting lives at risk when it comes to the flying piece of the jet or the system,” Chaillan said. A formal announcement could follow in coming days. The Air Force is embracing agile development and DevSecOps in several of its programs to accelerate development time and deploy tools faster. Critical to this effort has been two Air Force environments — Cloud One and Platform One. Platform One, which was recently deemed an enterprise solution by the Department of Defense, is a software development platform that hosts a broad range of DoD components, including the Joint Artificial Intelligence Center. The JAIC moved to the Air Force platform as it awaits the results of an ongoing court battle between Amazon Web Services and Microsoft over the Joint Enterprise Defense Infrastructure, or JEDI cloud. Chaillan said the F-35 program is also planning to move to Platform One soon. He added that he wants the platform to serve as a “software factory as a service.” In the next 12 to 18 months, Chaillan said that he sees the service continuing to add artificial intelligence and machine learning into its systems at scale. Both Cloud One and Platform One will be critical to the development of those systems. Cloud One, a multi-cloud environment with Microsoft and AWS, will also be looking to add new vendors “down the road,” Chaillan said. The Air Force's decision to go the multi-award route over the single award structure like JEDI made sense because of the advancement of cloud technology taken by the Air Force, Chaillan said. “When JEDI started, it did make sense to have a single award because cloud is very hard and very complex and it did makes sense to start there. Would I do that now? Probably not. I think technology changed,” Chaillan said. https://www.c4isrnet.com/battlefield-tech/it-networks/2020/09/15/updating-software-in-flight-the-air-force-may-be-close/

  • GA-ASI Mojave Lights Up the Yuma Desert in Live-Fire Demonstration

    24 avril 2024 | International, Aérospatial

    GA-ASI Mojave Lights Up the Yuma Desert in Live-Fire Demonstration

    GA-ASI partnered with Dillon Aero to mount two of Dillon’s DAP-6 Gun Pod Systems onto the Mojave aircraft. Mojave performed seven passes across two flights during the demonstration, expending around...

Toutes les nouvelles