Turkey in talks with South Korea to salvage Altay tank program

By:

ANKARA, Turkey — Turkish procurement and military officials as well as teams from a private manufacturer have been negotiating with a South Korean company to recover a program riddled with delays for the production of the country's first indigenous new-generation main battle tank.

“This program has faced major delays due to failed access to significant components like the engine, transmission and armor,” a procurement official told Defense News. “I am not in a position to give a date for the start of serial production. All I know is we are trying hard to get it moved ahead.”

In 2019, Turkish President Recep Tayyip Erdogan's office included the Altay tank as part of the military's 2020 inventory in a government document. In an October 2019 speech, Ethem Sancak — a senior shareholder in BMC, which makes the Altay — said the tank would be fielded within 24 months.

It now appears that prediction was too optimistic. The presidential office's 2021 investment program, released earlier this month, does not even mention the Altay, let alone the tank entering service.

According to a source with knowledge of the Altay program, BMC has been in talks with Hyundai Rotem to solve problems surrounding missing foreign technology for the Altay, which Turkish officials often portray as a fully national, indigenous Turkish tank. The South Korean company previously built public transportation and Bosporus crossing systems in Istanbul, Ankara and Adana as well as light rail systems in Istanbul and Izmir.

“We are hoping our talks will eventually sort out the problems regarding the power pack — [the engine and transmission — that] we will use in the serial production cycle,” the source told Defense News. “We are probably talking about another couple of months of talks before we know which way we are headed.”

He added that BMC is in indirect talks, through Hyundai Rotem, with two South Korean defense technology concerns: engine-maker Doosan and S&T Dynamics, which produces automatic transmissions.

“Ideally a Doosan-S&T power pack will power the Altay if we can iron out differences and licensing issues,” he said.

South Korea has experienced similar problems with its program for the mass production of the K2 Black Panther tank. Its deployment by the Army faced delays due to problems concerning the engine and transmission.

The first 100 units were built with a Doosan 1,500-horsepower engine and an S&T Dynamics automatic transmission. Under a second contract, tanks began to be delivered in late 2016. But after S&T Dynamics' transmission failed durability tests, South Korea's Defense Acquisition Program Administration announced the second batch would have a “hybrid” power pack consisting of the locally developed engine and the German RENK transmission system.

“How the Turks can make use of a proven engine and a failed transmission remains to be seen,” said a London-based Turkey expert, who spoke on condition of anonymity.

Turkey had hoped to power the Altay with the German MTU engine and RENK transmission, but talks with German manufacturers over the past couple of years failed due to a federal arms embargo on Turkey. Germany is one of a number of European governments that have limited exports to Turkey over its involvement in the Syrian civil war.

A similar problem concerns the Altay's planned armor. Turkey was hoping a French armor solution would be continue to be available following an initial batch of 40 units. But recent political tension between the two countries over hydrocarbon explorations off Cyprus has put this in jeopardy.

The source with knowledge of the Altay program said the armor will now be locally produced under a public-private partnership.

The Altay program dates back to the mid-1990s, but it wasn't until November 2018 that the Turkish government awarded the tank's multibillion-dollar contract to BMC. In a competition, the firm defeated Otokar, which had already produced four Altay prototypes under a government contract.

The contract involves the production of an initial batch of 250 units, life-cycle logistical support, and the establishment by the contractor of a tank systems technology center and its operation. As part of the contract, BMC will design, develop and produce a tank with an unmanned fire control unit.

The contract said the first Altay tank is to roll off the assembly line within 18 months. Opposition parties in parliament have slammed the government over delays, but procurement officials claim the 18-month clause will apply after the first unit's production begins.

The Altay program is broken into two phases: T1 and T2. T1 covers the first 250 units, and T2 involves the advanced version of the tank. Turkey also plans to eventually produce 1,000 Altays, to be followed by an unmanned version.

The deal has proved politically controversy, particularly after the Erdogan administration leased for free a military-owned tank and turret factory by the Marmara Sea to BMC for a period of 25 years.

The move prompted cries of nepotism, as BMC shareholder Sancak was a senior member of Erdogan's Justice and Development Party at the time.

Ozgur Eksi, an independent defense analyst, questioned the choice of assigning a factory by the sea for tank production. “In the event of war, the Altay factory could be an easy target for the enemy fire,” he said. “This program could have been much better planned from a strategic point of view.”

Nevertheless, Eksi added, “there is a political determination to get the Altays into the Army's inventory. Sooner or later, production will start.”

https://www.defensenews.com/industry/2020/11/19/turkey-in-talks-with-south-korea-to-salvage-altay-tank-program/

On the same subject

  • Lockheed CEO: Boeing’s F-15X won’t disrupt F-35 program

    January 30, 2019 | International, Aerospace

    Lockheed CEO: Boeing’s F-15X won’t disrupt F-35 program

    By: Valerie Insinna WASHINGTON — Lockheed Martin has been given assurances by top Pentagon leaders that the F-35 program will not be negatively impacted by a potential U.S. Air Force buy of Boeing's F-15X, Lockheed CEO Marillyn Hewson said Tuesday. “If they choose to have an order of the F-15, it won't be at the expense of F-35 quantities,” she told investors during an earnings call. “I'm hearing that directly from leadership in the Pentagon, and I think that's an important point for me to make. It's not just our suspicion, but I've been told that directly.” The U.S. Air Force is expected to roll out a plan to begin buying new F-15s in its upcoming fiscal 2020 budget release. In December, Bloomberg reported the service intends to purchase 12 new F-15X aircraft in 2020 for $1.2 billion. On Friday, Gen. Dave Goldfein, the Air Force's chief of staff, confirmed to Defense News that the service will procure new F-15s if the budget grows enough to allow it, but that the F-35 program of record would remain the same with no slowdown to the buy rate. “I'm not backing an inch off of the F-35” Goldfein said. “The F-35 buy that we're on continues to remain on track. And I'm not interested in taking a nickel out of it when it comes to buying anything else in the fighter portfolio.” Goldfein added that the Air Force wants to increase fighter procurement to 72 aircraft a year. The Air Force has about 230 F-15 "C" and "D" models currently in service, and the F-15X will replace the portion of the fleet owned by the Air National Guard, according to Bloomberg. The new F-15 model will have new radar and electronic warfare equipment, the ability to carry more weapons, and include other improvements originally designed for Saudi Arabia's and Qatar's F-15s. If the service maintained a rate of one F-15X a month, it would be free to boost its F-35 production rate to 60 aircraft a year — a number that Air Force officials had cited as key for production ramp up. However, the FY19 budget forecast showed that the service would likely be unable to procure the F-35 in those quantities before FY23. “If we had the money, those would be 72 F-35s. But we've gotta look at this from a cost/business case.” Goldfein said. “An F-15 will never be an F-35. Never. But I need capacity.” Hewson's statement indicates that support for the F-35 continues to be strong both within the Air Force and among Pentagon leaders. However, earlier on Tuesday, acting Defense Secretary Patrick Shanahan told reporters he wants to see “more performance” from the F-35, although he did not specify particular areas of improvement. “I am biased towards giving the taxpayer their moneys' worth. And the F-35, unequivocally, I can say has a lot of opportunity for more performance,” said Shanahan, a former Boeing executive. When investors asked Hewson to respond to Shanahan's critique, the Lockheed CEO said the company remains on the same page with the Pentagon on the need to reduce the cost per plane. “We're on a path to drive it to an $80 million [unit cost] for the F-35A by full-rate production,” which is projected to begin in Lot 15 with deliveries starting in 2023, Hewson said. “So as long as we stay on our procurement rate plan — which by all accounts we're going to continue to ramp up at the rate that we envisioned — then we're going to continue to drive the price down." Aaron Mehta in Washington contributed to this story. https://www.defensenews.com/industry/2019/01/29/lockheed-ceo-boeings-f-15x-wont-disrupt-f-35-program

  • Another Boeing-Airbus tanker war is coming soon

    June 18, 2021 | International, Aerospace

    Another Boeing-Airbus tanker war is coming soon

    The Air Force wants to buy as many as 160 KC-Y tankers after it's finished with KC-46 production. Both Airbus and Boeing are ready to compete.

  • Army to award new contracts to support mobile comms units

    July 9, 2020 | International, Land, C4ISR

    Army to award new contracts to support mobile comms units

    Mark Pomerleau The Army is awarding delivery orders to three vendors to support equipment for three Expeditionary Signal Battalion-Enhanced (ESB-E) units. Specifically, the awards will support fielding of satellite baseband equipment, said Paul Mehney, director of public communications at Program Executive Office Command, Control, Communications-Tactical. Expeditionary signal battalions support units that don't have organic communications capabilities. These groups could include military intelligence battalions, chemical battalions, engineering battalions or air defense artillery branches. The ESB-E aims to be more mobile and require less equipment in order to drop in, support units and move more quickly on the battlefield. Overall, the vendors will be responsible for providing 48 baseband sets of equipment for each ESB-E formation. “Due to aggressive initial fielding timelines, after the first six ESB-E formations are fielded, the program office intends to open baseband capability competition for future ESB-E needs,” Mehney said. PacStar was recently awarded a contract to support the ESB-E program to provide its 400-Series modular platform to enhance tactical expeditionary communications, the company said in a July 7 release. The 400-Series is lightweight allowing these smaller and expeditionary units to maneuver more quickly. It includes 128 GB RAM, virtual routing and the PacStar 463 Radio Gateway. “Network modernization to meet warfighter needs and defense priorities is a core focus for the Army and across the DoD, and we are proud to support these efforts with PacStar 400-Series for ESB-E,” Peggy J. Miller, chief executive of PacStar, said in a statement. “With these solutions, ESB-E [Scalable Network Node] will get the smallest, lightest, modular tactical communications platform in the industry, which is part of our larger initiative to enable increased reliability and innovation for warfighters.” The other vendors include Klas and DTECH, with all three supporting one ESB-E. An additional delivery order for each vendor to a second ESB-E will be issued, meaning in the near future, each vendor will support two units a piece. After that, the Army will open up the contracts to competition. This approach follows how the Army has been experimenting to date by providing similar, yet comparable equipment to several ESB-E's. These companies have provided separate equipment to three units allowing the Army to gain useful feedback from units to see what they liked and disliked about the gear. This has allowed the Army to execute rapid prototyping and experimentation on a tighter timeline for making fielding decisions while providing equipment to soldiers in the interim. The first two ESB-Es fielded include the 57th ESB-E at Fort Hood and the 50th ESB-E at Fort Bragg. https://www.c4isrnet.com/battlefield-tech/2020/07/08/army-to-award-new-contracts-to-support-mobile-comms-units

All news