February 15, 2021 | International, Naval

It will be at least a decade before Canada sees any of its new frigates

New frigates are being packed with more combat capability than comparable ships of allies

Murray Brewster

It will be 2031, at the earliest, before the navy sees the first of its new frigates; a setback brought about partly by the fact Canada, Britain and Australia are still feeling their way around how to build the ultra-modern warship.

The outgoing president of Irving Shipbuilding Inc., which is in charge of constructing combat ships for the federal government, said he anticipates steel will be cut on the first of the new generation high-end warships by mid-2024.

"We have been trying to take an honest look at where we are and what it will take to build the ship," said Kevin McCoy who recently announced his retirement from the East Coast shipbuilder.

The current estimate is that it will take up to seven-and-a-half years to build the surface combatant, a timeline being used by Britain's BAE Systems Inc., which is constructing the first of what's known as the Type 26 design.

Both Canada and Australia are building their own variants.

"Early on [in the shipbuilding process] estimates are not very good," said McCoy. "Early estimates are not very good for price; they're not very good for size; they're not not very good for duration," McCoy said. "The British ship has a seven-and-a-half year build cycle. So, we're locked in. We said our build cycle will be seven-and-a-half years as well."

If they can find ways to speed up the process, they will, he said.

If that timeline holds, it means the federal government's marquee shipbuilding strategy will be two decades old by the time it produces the warship it was principally set up to create.

While Irving has been pumping out smaller, less complicated arctic patrol ships and Seaspan, in Vancouver, is building coast guard and science vessels, the strategy conceived by the former Conservative government was driven by the necessity of replacing the navy's current fleet of Halifax-class frigates.

Originally, when the shipbuilding strategy was unveiled, it envisioned Canada receiving the first new frigate in 2017. A lot of water, wishful thinking and even money has gone under the bridge since then.

Building off existing design

The current Liberal government, since taking over in 2015 and embracing the strategy, has been opaque in its public estimates of the build time; suggesting, in some documents, a delivery time in mid-2020s while other more internal records have pegged the first new frigate in the 2027 timeframe.

The Department of National Defence, in a statement, acknowledged some of the design and build intricacies are now better understood, and because of that; the first warship will be "approximately 2-3 years later than the previous estimate."

A spokeswoman echoed McCoy's remarks about finding ways to move construction along.

"We continue to look for efficiencies and are actively working with industry to accelerate the project in order to deliver this important platform to the RCN as soon as possible," said National Defence spokesperson Jessica Lamirande.

One of the ways they could do that, she said, would be to construct some, less complex modules of the warship early, the way it has been in the navy's Joint Support Ship project at Seaspan's Vancouver Shipyard.

McCoy, a blunt-talking former U.S. Navy admiral, suggested the expectations going to the surface combatant program were ultimately unworkable because the federal government came in expecting to do a so-called "clean sheet" design; meaning a warship built completely from scratch.

It was the shipyard, he said, which ultimately inched the federal government toward building off an existing design because of the enormous risk and expense of purpose-built ships, a position the Liberals adopted in the spring of 2016.

The selection of the British Type 26 design by the Liberal government has spawned criticism, a court challenge and will figure prominently in upcoming reports by the auditor general and the Parliamentary Budget Officer.

Combat capability packed into ship

The nub of the complaints have been that the frigate is not yet in the water and is still under construction in the United Kingdom.

The defence department acknowledged that adapting the British design to Canadian expectations and desires will take a year longer than originally anticipated and is now not scheduled to be completed until late 2023, early 2024.

Canada, McCoy said, can expect to pay no more $2.5 billion to $3 billion, per ship as they are produced, which is, he claimed, about what other nations would pay for a warship of similar capability.

"This is a big ship, lots of capability" he said, indicating that full displacement for the new frigate will likely be about 9,400 tonnes; almost double the 4,700 tonnes of the current Halifax-class.

McCoy said what is not generally understood amid the public concern over scheduling and cost is the fact that the Canadian version of the Type 26 will be expected to do more than its British and Australian cousins.

Where those navies have different warships, performing different functions, such as air defence or anti-submarine warfare, Canada's one class of frigates will be expected to perform both because that is what the government has called for in its requirements.

Dave Perry, a defence analyst and vice president of the Canadian Global Affairs Institute, has studied the program and said he was surprised at the amount of combat capability that was being packed into the new warship.

"On the one hand, Canada's one [class] of ship will have more combat capability than many of the other classes of ship that our friends and allies sail with, but it also adds an additional level of complexity and challenge getting all of that gear, all of that firepower into one single floating hull and platform," he said.

https://www.cbc.ca/news/politics/canada-shipbuilding-decade-frigates-1.5912961

On the same subject

  • SpaceX, ULA each get Air Force contracts for trio of space launches

    February 25, 2019 | International, Aerospace

    SpaceX, ULA each get Air Force contracts for trio of space launches

    By: Valerie Insinna WASHINGTON — The battle between military space juggernaut United Launch Alliance and its upstart rival SpaceX continues, with the two companies splitting a collection of launch contracts worth $739 million awarded by the Air Force on Tuesday. ULA, a joint venture of Boeing and Lockheed Martin, picked up a $442 million award for three launches, while Elon Musk's SpaceX nabbed a $297 million contract for another three launches. Each company will be responsible for “launch vehicle production, mission integration, mission launch operations/spaceflight worthiness, and mission unique activities,” according to the contract award. ULA will deliver the following payloads as part of its contract: Silent Barker, a secret payload developed by the Air Force and National Reconnaissance Office, which will improve situational awareness after it is launched in fiscal year 2022. SBIRS GEO-5, the fifth geostationary satellite in the Space Based Infra Red Sensor constellation, will improve early warning for missile launches. SBIRS GEO-5 is set to be launched in FY21. SBIRS GEO-6, the sixth geostationary satellite in the SBIRS constellation, could be launched in FY22, but no firm date has been set. Meanwhile SpaceX will launch these payloads: NROL-85, a classified intelligence payload launched for the NRO, expected to be launched in FY21 NROL-87, another classified NRO payload set for a FY21 launch date. AFSPC-44, an Air Force satellite also set to be launched in FY21. The service hasn't released much information about this payload's capabilities or purpose. The contracts were awarded by the Air Force's Space and Missile Systems Center as part of the Evolved Expendable Launch Vehicle program. In a statement, Lt. Gen. John Thompson, commander of SMC and program executive officer for space programs, defended the service's strategy of awarding launch contracts in a way that balances rewarding low-price bids while also maintaining competition among rocket makers. “The competitive award of these EELV launch service contracts directly supports SMC's mission of delivering resilient and affordable space capabilities to our nation while maintaining assured access to space” he said. https://www.defensenews.com/space/2019/02/20/spacex-ula-each-get-air-force-contracts-for-trio-of-space-launches/

  • Boom Supersonic and Northrop Grumman team up to build superfast US military aircraft

    July 21, 2022 | International, Aerospace

    Boom Supersonic and Northrop Grumman team up to build superfast US military aircraft

    Boom Supersonic and Northrop Grumman plan to deliver variants of Boom's Overture aircraft for military and emergency response missions.

  • La Suède annonce d'importants investissements de Défense, pour atteindre 2% du PIB

    March 11, 2022 | International, Aerospace, Naval, Land, C4ISR, Security

    La Suède annonce d'importants investissements de Défense, pour atteindre 2% du PIB

    Le gouvernement suédois a présenté ce jeudi un projet prévoyant d'accélérer le réinvestissement dans son armée, avec l'objectif d'atteindre les 2% du PIB « aussi vite que possible », a indiqué la Première ministre, Magdalena Andersson, lors d'une conférence de presse. Cette décision fait suite à l'invasion de l'Ukraine par la Russie. Magdalena Andersson avait écarté en début de semaine l'option de l'adhésion de la Suède à l'OTAN, estimant qu'une telle initiative risquerait de « déstabiliser » le nord de l'Europe. Le Figaro du 11 mars

All news