COVID Can’t Stop A Busy Summer For Army FVL

Despite disruptions worldwide, Future Vertical Lift flight tests, virtual industry days, and design reviews are all moving ahead on schedule or mere weeks behind.

By on May 07, 2020 at 5:07 PM

WASHINGTON: As the Army urgently develops weapons to counter Russia and China, it's largely staying on its tight schedule despite both the COVID-19 pandemic and the service's own history of dysfunction and delay. A prime example is the Future Vertical Lift initiative to replace existing helicopters and drones, which is on track for all but two of more than 20 major events – from field tests to contract awards – happening this year. Half a dozen are scheduled for May and June alone.

What's the biggest impact COVID has had on FVL so far? Of the five project managers who spoke to reporters this morning, just one said he's definitely delaying something, a Critical Design Review for the new Improved Turbine Engine. How big was that delay? Just two weeks.

The engine system CDR will start June 15th instead of June 1st, said the turbine PM, Col. Roger Kuykendall. But the deadline to complete the review wasn't until October, he went on, “so we're actually still ahead of our schedule.”

The other major impact has been on combat units field-testing potential Future Tactical Unmanned Aerial System drones, but that's still in flux, said the unmanned aircraft PM, Col. Scott Anderson. Masked soldiers began flying one contending design, the Arcturus JUMP-20, began at Fort Riley a month ago. The second test unit, at Fort Campbell, started flying a different contender last week, as planned, Col. Anderson said. The third unit, at Fort Lewis, was scheduled to start in June: “The had asked to move back to July,” he said, “but it looks like, as of this morning, they're going to maybe try to come back to June.”

That the FTUAS field tests are happening mostly on schedule is particularly remarkable, because it takes a team of soldiers to operate and maintain the drones, and they can't maintain social distancing all the time. Most of the other FVL projects are in different stages of development where schedules, while packed, are full of activities that are a lot easier to do online, like planning sessions and digital design. But even where physical objects have to be built or flown, the project managers stay they're staying on schedule.

For the Future Long-Range Assault Aircraft to replace the Reagan-era UH-60 Black Hawk, PM Col. David Phillips said, “our demonstrators are continuing to fly.” Those are the Bell V-280 Valor tiltrotor and the Sikorsky-Boeing SB>1 Defiant compound helicopter, which despite the term of art “demonstrator” are de facto prototypes. The companies are now refining their designs and, in 2022, the Army will choose one for mass production. While Phillips didn't provide details like flight hours – the Defiant has had a lot fewer so far – he said both aircraft are still providing test data to mature key technologies like flight controls.

FLRAA's smaller sister is the Future Attack Reconnaissance Aircraft, a light scout to replace the retired OH-58 Kiowa. Once again it's Bell and Sikorsky competing, but for FARA they haven't built the prototypes yet. Those are set to fly in 2023. (That said, Sikorsky's existing S-97 Raider is very close to their FARA design). Most of the work this year is being spent on digital design, said the FARA PM, Col. Gregory Fortier, but that should finish by December, so preparations to build the physical prototypes do have to get underway now.

“We have currently seen no impact, [but] there are certainly concerns within Bell and Sikorsky about long lead materials and shipping and the [subcontractors] at the second and third tier,” Col Fortier said. “They are okay with the summer timeframe and into the fall,” Fortier said. “If this thing stretches six months to a year, then that's a different conversation.”

The FARA scout, FLRAA transport, and future drones will all have as many components in common as possible, especially electronics, and need to seamlessly share both tactical and maintenance data. To make this happen, they're being designed to a common set of technical standards known as the Modular Open System Architecture, allowing the Army to plug-and-play MOSA-compliant components from any company for both maintenance and upgrades.

While existing Army aircraft can't be retrofitted with the complete open architecture, the Army plans to upgrade them with a mini-MOSA called the Aviation Mission Common Server. AMCS will both provide some of the benefits of open architecture to the current fleet and real-world experience to help build the future system.

AMCS, too, remains on schedule, the project manager said. “We are currently on track to award an OTA [Other Transaction Authority contract] in June 2020 and negotiations are currently ongoing,” Col. Johnathan Frasier said.

The Schedule To Stay On

Future Vertical Lift is doing a lot this year. Here's a list of most – not all – of the things they've accomplished so far and what they aim to do. A startling amount of it is due in June.

Modular Open Systems Architecture (involves multiple project managers)

  • April: Over 300 government and industry participants joined in a virtual meeting of the Architecture Collaboration Working Group fleshing out MOSA.
  • June: A follow-on ACWG meeting is scheduled. The Army will award an Other Transaction Authority (OTA) contract for the Aviation Mission Common Server (AMCS).

Engine & Electrical (PM: Col. Roger Kuykendal)

  • May-June: Tentative date for an industry day on electrical systems, including batteries, generators, Auxiliary Power Units (APUs), and thermal management (i.e. cooling).
  • June 15-19: Critical Design Review for the integrated engine system.
  • October: Power management systems demonstration, conducted with the Army C5ISR center.
  • Fall: Improved Turbine Engine testing begins.

Future Long-Range Assault Aircraft (PM: Col. David Phillips)

  • March 17: The Army awarded Bell and the Sikorsky-Boeing team contracts for Competitive Demonstration & Risk Reduction (CDRR) of their rival FLRAA designs.
  • June: FLRAA and FARA will hold a joint industry day – virtually, of course – on their shared mission systems. And the FLRAA competitors will deliver conceptual designs to help shape the program's final requirements.
  • Fall: Those FLRAA requirements will come up for review by the Army Requirements Oversight Council (AROC), a high-level body usually chaired by either the four-star boss of Army Futures Command or even the Army Chief of Staff himself.

Future Attack Reconnaissance Aircraft (PM: Col. Gregory Fortier)

  • March 25: The Army picked Bell and Sikorsky to build competing prototypes.
  • May 15: Industry responses are due for a formal Request For Information (RFI) on FARA mission systems.
  • June: FLRAA and FARA hold their joint industry day on shared mission systems. Boston Consulting Group will deliver the first of two studies on FARA-specific mission systems.
  • Summer (month not specified): Deloitte will deliver the second FARA mission systems study. Sikorsky and Bell will both go through Preliminary Design Review.
  • December: Sikorsky and Bell will submit their final designs. With those approved, they'll begin building the actual prototypes.

Unmanned Aircraft Systems (PM: Col. Scott Anderson)

  • April: The first FTUAS contender began field testing (formally “demonstrations”) at Fort Riley, Kan.
  • May: The second FTUAS contender began field testing at Fort Campbell, Ken.
  • May-June: This is the likely window for the Army to award three Other Transaction Authority contracts for the mini-drones known as Air-Launched Effects (ALE).
  • June-July: Third FTUAS contender begins testing at Fort Lewis, Wash.
  • July: Fourth contender begins testing at Fort Bliss, Tex.
  • August-September: A fifth unit begins testing at Fort Bragg, NC. There are only four different designs being studied, so this brigade will double up on of the designs already in testing.
  • Fall: The Army Requirements Oversight Council will review the final requirement for FTUAS – which will be based on how the contenders actually performed – as well as requirements for a highly automated Scalable Control Interface (SCI) for all future drones.

https://breakingdefense.com/2020/05/covid-cant-stop-a-busy-summer-for-army-fvl

On the same subject

  • At Defence Expo 2020, Make-in-India achievement; Rafale engine doors, Falcon front cockpit. Here’s all Dassault aviation will show

    February 5, 2020 | International, Aerospace

    At Defence Expo 2020, Make-in-India achievement; Rafale engine doors, Falcon front cockpit. Here’s all Dassault aviation will show

    For the first time Dassault Aviation of France will be exhibiting at the Defence Expo and the main attraction besides other displays will be the Rafale mock-up with the Indian colours. Defence Expo 2020 is being held at Lucknow, Uttar Pradesh The Rafale fighter aircraft which were handed over to the defence minister Rajnath Singh last October will be arriving in India early summer. The mock-up in the colours of the IAF is to illustrate the determination of the French company's commitment to meet all future additional fighter aircraft needs. Also, a mock-up of Rafale M (Naval variant) will be on display to present capabilities of the variant taking part in the tender of 57 aircraft to equip Indian Navy aircraft carriers. There will also be a Mirage 2000 I/TI mock-up on display. Highlighting its “Make in India” achievements on display will be Rafale engine doors manufactured in the Dassault Reliance Aerospace Ltd (DRAL) 15000 square meters the facility in Nagpur, and the first Falcon 2000 cockpit front section manufactured at Dassault Reliance Aerospace Limited facility at MIHAN, Nagpur. Eric Trappier, Chairman and Chief Executive Officer of Dassault Aviation has said, “Our participation in the DefExpo is the expression of the company's full dedication to contribute to India's outreach”. According to the company larger infrastructures are being developed which will help in ramping up of DRAL capabilities towards the taking-off of an entire line of Falcon 2000 fully manufactured and assembled in India. This will pave the way for the future manufacturing and assembly of Rafale in India. And these will help to build up an Indian aerospace manufacturing eco-system, both in civil and military fields, which will position India as an international reference in the global aerospace market. The company has played a very important role in helping India to establish a state-of-the-art manufacturing facilities with cutting edge technologies. https://www.financialexpress.com/defence/defence-expo-2020-rafale-mirage-2000-make-in-india-achievement-engine-door-cockpit-dassault-aviation-dral/1855850/

  • Boeing Awarded U.S. Navy Contract for New Zealand P-8 Training

    December 17, 2020 | International, Aerospace, Naval

    Boeing Awarded U.S. Navy Contract for New Zealand P-8 Training

    Posted on December 15, 2020 by Seapower Staff OHAKEA, New Zealand — The U.S. Navy recently awarded Boeing a Foreign Military Sales (FMS) contract, valued at $109 million, to provide P-8A Poseidon training for the Royal New Zealand Air Force (RNZAF), the company said in a Dec. 14 release. A suite of training systems and courseware will prepare RNZAF aircrew and maintainers to safely and effectively operate and maintain the world's premier maritime patrol and reconnaissance aircraft for decades to come. Boeing's holistic P-8 training system will enable the RNZAF to conduct up to 70 percent of all Poseidon-related training in a simulated environment. As part of the contract, Boeing will provide: Operational Flight Trainer (OFT) – Full-motion simulator incorporates all P-8 unique displays and switches. Weapons Tactics Trainer – Simulates mission systems and tactical operations, and when coupled with the OFT, forms a Weapons Systems Trainer that enables multi-crew, high-fidelity mission rehearsal training in the same simulated environment. Virtual Maintenance Trainer – Enables training of maintenance professionals to properly perform maintenance tasks and procedures on the P-8A aircraft Scenario Generation Station – Creates custom scenarios for mission training Brief/Debrief Station – Provides post-mission analysis and playback. In addition, Boeing's Electronic Classroom will give RNZAF instructors and students access to courseware and testing capabilities. Boeing also will provide initial Instructor Cadre Training to a group of RNZAF instructors, enabling them to continue training additional RNZAF P-8A instructors and aircrews following delivery of the training system in early 2024. “This holistic training system will enable aircrew to safely train for all aspects of flying and maintaining the P-8A Poseidon,” said Tonya Noble, director of International Defense Training for Boeing. “We look forward to bringing these training capabilities in-country and working alongside the RNZAF to ensure readiness of aircrew and maintenance personnel.” All training will be conducted in Ohakea, New Zealand. In March 2020, the RNZAF acquired four P-8A Poseidon aircraft through the U.S. Navy FMS process, with expected delivery beginning in 2023. New Zealand is one of seven nations operating the P-8. https://seapowermagazine.org/boeing-awarded-u-s-navy-contract-for-new-zealand-p-8-training/

  • Navy Making Room for Railguns in Next Warship, But No Extra Investments

    August 30, 2018 | International, Naval

    Navy Making Room for Railguns in Next Warship, But No Extra Investments

    By: Megan Eckstein THE PENTAGON – The Navy's next large surface combatant will have all the space, weight and power margins the sea service could need now and into the future to accommodate new weapons in development – but the director of surface warfare said the Navy would not accelerate weapons development to get them ready in time to outfit the new ships. Rear Adm. Ron Boxall, OPNAV N96, spoke to USNI News on Aug. 28, in his first interview on the Future Surface Combatant program since its initial capabilities document was signed out by leadership. Noting that the next large surface combatant would pull from some of the advances made with the Zumwalt-class destroyers (DDG-1000) – including potentially its integrated power system that could easily support laser guns, an electromagnetic railgun, powerful radars and other power-hungry technologies – Boxall told USNI News that the new large surface combatant represented an opportunity to put these technologies into the surface fleet whereas the legacy Arleigh Burke-class destroyers simply do not have the power and cooling capacity to do so. “We're just excited that we think we do have something that is expandable, has SWaP-C (space, weight, power and cooling) for the future. I think all of us were kind of a little bit nervous about the DDG Flight III and whether we'll have long-term ability to put future energy weapons on there, or the power that we need for directed energy, lasers, things like that,” he said. But just because the new ship will be able to support energy weapons doesn't mean Boxall wants to accelerate energy weapons development to ensure they're ready to field on the first new ships. He said moving to the Future Surface Combatant in 2023 is an “aggressive timeline” and that at some point the Navy will have to “snap the chalk line and say, this is what you have that's good enough to go on there” – and if a technology isn't ready, it would wait for fielding in a later block buy of the ship. With the Navy already seeking a new hull to better support the Aegis Combat System and the AN/SPY-6(V) Air and Missile Defense radar – collectively called the DDG-51 Flight III capability – Boxall said he didn't want to force too many changes all at once. “So I'm inclined to say, as long as we build it modularly, we're going to make those assessments in stride” in terms of inserting in new weapons as they come through the development process, he said. “But I don't want to get too crazy about trying to accelerate new technology in the first of the class as we change hulls, which will hopefully be a hull that will be with us for a very long time.” Full article: https://news.usni.org/2018/08/29/navy-making-room-railguns-next-warship-no-extra-investments

All news