Back to news

May 8, 2020 | International, Aerospace

COVID Can’t Stop A Busy Summer For Army FVL

Despite disruptions worldwide, Future Vertical Lift flight tests, virtual industry days, and design reviews are all moving ahead on schedule or mere weeks behind.

By on May 07, 2020 at 5:07 PM

WASHINGTON: As the Army urgently develops weapons to counter Russia and China, it's largely staying on its tight schedule despite both the COVID-19 pandemic and the service's own history of dysfunction and delay. A prime example is the Future Vertical Lift initiative to replace existing helicopters and drones, which is on track for all but two of more than 20 major events – from field tests to contract awards – happening this year. Half a dozen are scheduled for May and June alone.

What's the biggest impact COVID has had on FVL so far? Of the five project managers who spoke to reporters this morning, just one said he's definitely delaying something, a Critical Design Review for the new Improved Turbine Engine. How big was that delay? Just two weeks.

The engine system CDR will start June 15th instead of June 1st, said the turbine PM, Col. Roger Kuykendall. But the deadline to complete the review wasn't until October, he went on, “so we're actually still ahead of our schedule.”

The other major impact has been on combat units field-testing potential Future Tactical Unmanned Aerial System drones, but that's still in flux, said the unmanned aircraft PM, Col. Scott Anderson. Masked soldiers began flying one contending design, the Arcturus JUMP-20, began at Fort Riley a month ago. The second test unit, at Fort Campbell, started flying a different contender last week, as planned, Col. Anderson said. The third unit, at Fort Lewis, was scheduled to start in June: “The had asked to move back to July,” he said, “but it looks like, as of this morning, they're going to maybe try to come back to June.”

That the FTUAS field tests are happening mostly on schedule is particularly remarkable, because it takes a team of soldiers to operate and maintain the drones, and they can't maintain social distancing all the time. Most of the other FVL projects are in different stages of development where schedules, while packed, are full of activities that are a lot easier to do online, like planning sessions and digital design. But even where physical objects have to be built or flown, the project managers stay they're staying on schedule.

For the Future Long-Range Assault Aircraft to replace the Reagan-era UH-60 Black Hawk, PM Col. David Phillips said, “our demonstrators are continuing to fly.” Those are the Bell V-280 Valor tiltrotor and the Sikorsky-Boeing SB>1 Defiant compound helicopter, which despite the term of art “demonstrator” are de facto prototypes. The companies are now refining their designs and, in 2022, the Army will choose one for mass production. While Phillips didn't provide details like flight hours – the Defiant has had a lot fewer so far – he said both aircraft are still providing test data to mature key technologies like flight controls.

FLRAA's smaller sister is the Future Attack Reconnaissance Aircraft, a light scout to replace the retired OH-58 Kiowa. Once again it's Bell and Sikorsky competing, but for FARA they haven't built the prototypes yet. Those are set to fly in 2023. (That said, Sikorsky's existing S-97 Raider is very close to their FARA design). Most of the work this year is being spent on digital design, said the FARA PM, Col. Gregory Fortier, but that should finish by December, so preparations to build the physical prototypes do have to get underway now.

“We have currently seen no impact, [but] there are certainly concerns within Bell and Sikorsky about long lead materials and shipping and the [subcontractors] at the second and third tier,” Col Fortier said. “They are okay with the summer timeframe and into the fall,” Fortier said. “If this thing stretches six months to a year, then that's a different conversation.”

The FARA scout, FLRAA transport, and future drones will all have as many components in common as possible, especially electronics, and need to seamlessly share both tactical and maintenance data. To make this happen, they're being designed to a common set of technical standards known as the Modular Open System Architecture, allowing the Army to plug-and-play MOSA-compliant components from any company for both maintenance and upgrades.

While existing Army aircraft can't be retrofitted with the complete open architecture, the Army plans to upgrade them with a mini-MOSA called the Aviation Mission Common Server. AMCS will both provide some of the benefits of open architecture to the current fleet and real-world experience to help build the future system.

AMCS, too, remains on schedule, the project manager said. “We are currently on track to award an OTA [Other Transaction Authority contract] in June 2020 and negotiations are currently ongoing,” Col. Johnathan Frasier said.

The Schedule To Stay On

Future Vertical Lift is doing a lot this year. Here's a list of most – not all – of the things they've accomplished so far and what they aim to do. A startling amount of it is due in June.

Modular Open Systems Architecture (involves multiple project managers)

  • April: Over 300 government and industry participants joined in a virtual meeting of the Architecture Collaboration Working Group fleshing out MOSA.
  • June: A follow-on ACWG meeting is scheduled. The Army will award an Other Transaction Authority (OTA) contract for the Aviation Mission Common Server (AMCS).

Engine & Electrical (PM: Col. Roger Kuykendal)

  • May-June: Tentative date for an industry day on electrical systems, including batteries, generators, Auxiliary Power Units (APUs), and thermal management (i.e. cooling).
  • June 15-19: Critical Design Review for the integrated engine system.
  • October: Power management systems demonstration, conducted with the Army C5ISR center.
  • Fall: Improved Turbine Engine testing begins.

Future Long-Range Assault Aircraft (PM: Col. David Phillips)

  • March 17: The Army awarded Bell and the Sikorsky-Boeing team contracts for Competitive Demonstration & Risk Reduction (CDRR) of their rival FLRAA designs.
  • June: FLRAA and FARA will hold a joint industry day – virtually, of course – on their shared mission systems. And the FLRAA competitors will deliver conceptual designs to help shape the program's final requirements.
  • Fall: Those FLRAA requirements will come up for review by the Army Requirements Oversight Council (AROC), a high-level body usually chaired by either the four-star boss of Army Futures Command or even the Army Chief of Staff himself.

Future Attack Reconnaissance Aircraft (PM: Col. Gregory Fortier)

  • March 25: The Army picked Bell and Sikorsky to build competing prototypes.
  • May 15: Industry responses are due for a formal Request For Information (RFI) on FARA mission systems.
  • June: FLRAA and FARA hold their joint industry day on shared mission systems. Boston Consulting Group will deliver the first of two studies on FARA-specific mission systems.
  • Summer (month not specified): Deloitte will deliver the second FARA mission systems study. Sikorsky and Bell will both go through Preliminary Design Review.
  • December: Sikorsky and Bell will submit their final designs. With those approved, they'll begin building the actual prototypes.

Unmanned Aircraft Systems (PM: Col. Scott Anderson)

  • April: The first FTUAS contender began field testing (formally “demonstrations”) at Fort Riley, Kan.
  • May: The second FTUAS contender began field testing at Fort Campbell, Ken.
  • May-June: This is the likely window for the Army to award three Other Transaction Authority contracts for the mini-drones known as Air-Launched Effects (ALE).
  • June-July: Third FTUAS contender begins testing at Fort Lewis, Wash.
  • July: Fourth contender begins testing at Fort Bliss, Tex.
  • August-September: A fifth unit begins testing at Fort Bragg, NC. There are only four different designs being studied, so this brigade will double up on of the designs already in testing.
  • Fall: The Army Requirements Oversight Council will review the final requirement for FTUAS – which will be based on how the contenders actually performed – as well as requirements for a highly automated Scalable Control Interface (SCI) for all future drones.

https://breakingdefense.com/2020/05/covid-cant-stop-a-busy-summer-for-army-fvl

On the same subject

  • Norway orders state-of-the-art Leopard 2 A7 tanks: Rheinmetall supplying main armament, fire control technology and sensors

    April 14, 2023 | International, Land

    Norway orders state-of-the-art Leopard 2 A7 tanks: Rheinmetall supplying main armament, fire control technology and sensors

    For Rheinmetall, the total value of the order comes to ?129 million?if Norway exercises the option to procure additional Leopard 2 tanks, the order will be worth an additional ?44...

  • Pentagon and Lockheed Martin Sign 2020 F-35 Sustainment Contract

    January 8, 2020 | International, Aerospace

    Pentagon and Lockheed Martin Sign 2020 F-35 Sustainment Contract

    Fort Worth, Texas, January 6, 2020 /PRNewswire/ -- The F-35 Joint Program Office awarded the Lockheed Martin (NYSE: LMT) industry team a $1.9 billion contract to support operations and sustainment of the global F-35 fleet, while improving mission readiness and further reducing costs. The annual contract funds critical sustainment activities for aircraft currently in the fleet and builds enterprise capacity to support the future fleet of more than 3,000 F-35 aircraft. This includes industry sustainment experts supporting base and depot maintenance, pilot and maintainer training, and sustaining engineering across the globe. It also covers fleet-wide data analytics and supply chain management for part repair and replenishment to enhance overall supply availability for the fleet. "The F-35 continues to deliver exceptional capabilities to the field, and this contract ensures F-35s are mission ready to meet warfighter needs," said Greg Ulmer, Lockheed Martin vice president and general manager of the F-35 program. "The joint government and industry team continues to make significant progress improving readiness rates and reducing sustainment costs. In 2020, we will continue to optimize and advance the sustainment system. We are confident F-35 sustainment costs will be equal to or less than legacy jets." The F-35 Joint Program Office, together with each U.S. service, international operator and the F-35 industry team, leads F-35 sustainment and the Global Support Solution. The 2020 annualized sustainment contract will cover industry sustainment activities through December 31, 2020. Enhancing Readiness and Reducing Cost Lockheed Martin's sustainment cost per aircraft per year has decreased four consecutive years, and more than 35% since 2015. The F-35's reliability continues to improve, and the global fleet is averaging greater than 65% mission capable rates, with operational squadrons consistently performing near 75%. The F-35 enterprise continues to pursue 80% mission capable rates in the near term and reduce the F-35 Cost Per Flight Hour to $25,000 by 2025, which is equal to or less than the cost to sustain legacy, less capable aircraft. To meet these goals, the enterprise is conducting supply chain competitions and building supply capacity, synchronizing spare buys, improving parts reliability and maintainability, implementing advanced analytics tools, accelerating modifications of earlier aircraft, and supporting the stand-up of government-led regional warehouses and repair depots. More than 490 aircraft, including 134 in 2019, have been delivered and are operating from 21 bases around the globe. More than 975 pilots and 8,585 maintainers have been trained and the F-35 fleet has surpassed more than 240,000 cumulative flight hours. For additional information, visit www.f35.com. About Lockheed Martin Headquartered in Bethesda, Maryland, Lockheed Martin is a global security and aerospace company that employs approximately 105,000 people worldwide and is principally engaged in the research, design, development, manufacture, integration and sustainment of advanced technology systems, products and services. View original content to download multimedia:http://www.prnewswire.com/news-releases/pentagon-and-lockheed-martin-sign-2020-f-35-sustainment-contract-300981717.html SOURCE Lockheed Martin Aeronautics

  • American shipbuilding: An anchor for economic and national security

    November 2, 2020 | International, Naval

    American shipbuilding: An anchor for economic and national security

    By: Peter Navarro “Don't give up the ship!” These were Capt. James Lawrence's dying words defending the USS Chesapeake during the War of 1812. Over 200 years later, the United States Navy and America's critical shipbuilding industry are issuing the same cry from shipyards across our nation. Here is a simple truth: A true renaissance of America's shipbuilding industry will require a large-scale overhaul and new strategy before it can churn out the ships we urgently need to maintain our status as the greatest maritime power in world history. In the first year of his “Peace through Strength” administration, President Donald Trump made a 355-ship Navy the official national policy by signing the 2018 Defense Authorization Act. Currently, however, we are asking too few ships to do too much while many vessels are decades old and severely backlogged for critical repairs. This egregiously long queue is an open invitation to foreign adversaries, who are displaying increasingly aggressive postures and rapidly expanding their own naval capabilities. Today, only seven shipyards across the country are capable of constructing large or deep-draft Navy vessels. More subtly, each yard has become specialized to build a specific warship, whether it be a nuclear-powered Virginia-class submarine or an Independence-class littoral combat ship. This specialization, while optimal for workforce training and infrastructure investments at specific yards, makes them remarkably vulnerable when there is a downturn in government contracts or the private market contracts. Foreign competitors such as China anchor their shipyards in tens of billions of mercantilist and predatory government subsidies every year. Unable to compete with such foreign subsidization, the American shipbuilding industry has lost 75,000 jobs — a decline of over 40 percent. For every shipbuilding job in America, three indirect jobs are supported. We have therefore allowed predatory foreign markets to steal approximately 300,000 good-paying American jobs — the population of St. Louis, Missouri. Our strategic and economic adversaries know the importance of shipbuilding. To understand the dangers, consider this: From 2010 to 2018, the Chinese Communist Party has provided over $130 billion in shipping and shipbuilding subsidies. Now, it controls the world's second-largest commercial fleet by gross tons, and constructs one-third of the world's ships. If Pax Americana is to continue, we must live up to the maxim of former Assistant Secretary of the Navy and 26th President Teddy Roosevelt: “A good Navy is not a provocation to war. It is the surest guarantee of peace.” Restoring investment in shipbuilding will leave a wake of prosperity for our economic security and send waves of strength for our national security. Expansion in capacity and capabilities of our shipyards will again incentivize commercial shipbuilding, increasing industry efficiency and creating competition, eventually lowering the overall cost of production. This must be our policy goal. If we commit to a revitalization of our shipyards, in just a few years, scores of vessels could again make maiden voyages from American yards built at the hands of thousands of American steelworkers, pipefitters, welders and electricians — a renaissance of one of our nation's most integral industries. This would mean thousands of new jobs in Maine, Michigan, Pennsylvania, Wisconsin, Florida and throughout the Gulf Coast. This means secure waters around Greenland, the Bering Strait and the South China Sea as well as the straits of Bab el-Mandeb, Malacca and Hormuz. While the 296-ship fleet of the U.S. Navy is still the most powerful in the world, Communist China's People's Liberation Army Navy is now sailing approximately 350 warships and counting. Some estimates say Communist China's Navy could be as large as 450 ships by 2030 — and it's not just China that is a cause for concern. While the Chinese Communist Party militarizes the South China Sea, Russia — which will assume chairmanship of the Arctic Council in May 2021 — has been quietly rebuilding its Arctic fleet. This is a region that will be of critical importance in the years to come as northern shipping lanes open and natural resources make themselves available. As it stands now, the U.S. Navy can't effectively access these waters, as it lacks the ice-hardened warships to do so. Our shipbuilding industry was once a bulwark of American manufacturing, but decades of neglect, ambivalence to predatory foreign markets and sequestration have caused it to take on water. If we don't begin patching the holes now, it won't be just an industry that sinks. It may well be our economic and national security, as we will be unable to protect the world's sea lanes — the arteries of commerce and veins of national defense. While our enemies argue American manufacturing and might is on the decline, we repeat the battle cry of Capt. John Paul Jones: “I have not yet begun to fight!” Peter Navarro is the assistant to the president and director of the Office of Trade and Manufacturing Policy within the White House. https://www.defensenews.com/opinion/commentary/2020/10/30/american-shipbuilding-an-anchor-for-economic-and-national-security/

All news