8 mai 2020 | International, Aérospatial

COVID Can’t Stop A Busy Summer For Army FVL

Despite disruptions worldwide, Future Vertical Lift flight tests, virtual industry days, and design reviews are all moving ahead on schedule or mere weeks behind.

By on May 07, 2020 at 5:07 PM

WASHINGTON: As the Army urgently develops weapons to counter Russia and China, it's largely staying on its tight schedule despite both the COVID-19 pandemic and the service's own history of dysfunction and delay. A prime example is the Future Vertical Lift initiative to replace existing helicopters and drones, which is on track for all but two of more than 20 major events – from field tests to contract awards – happening this year. Half a dozen are scheduled for May and June alone.

What's the biggest impact COVID has had on FVL so far? Of the five project managers who spoke to reporters this morning, just one said he's definitely delaying something, a Critical Design Review for the new Improved Turbine Engine. How big was that delay? Just two weeks.

The engine system CDR will start June 15th instead of June 1st, said the turbine PM, Col. Roger Kuykendall. But the deadline to complete the review wasn't until October, he went on, “so we're actually still ahead of our schedule.”

The other major impact has been on combat units field-testing potential Future Tactical Unmanned Aerial System drones, but that's still in flux, said the unmanned aircraft PM, Col. Scott Anderson. Masked soldiers began flying one contending design, the Arcturus JUMP-20, began at Fort Riley a month ago. The second test unit, at Fort Campbell, started flying a different contender last week, as planned, Col. Anderson said. The third unit, at Fort Lewis, was scheduled to start in June: “The had asked to move back to July,” he said, “but it looks like, as of this morning, they're going to maybe try to come back to June.”

That the FTUAS field tests are happening mostly on schedule is particularly remarkable, because it takes a team of soldiers to operate and maintain the drones, and they can't maintain social distancing all the time. Most of the other FVL projects are in different stages of development where schedules, while packed, are full of activities that are a lot easier to do online, like planning sessions and digital design. But even where physical objects have to be built or flown, the project managers stay they're staying on schedule.

For the Future Long-Range Assault Aircraft to replace the Reagan-era UH-60 Black Hawk, PM Col. David Phillips said, “our demonstrators are continuing to fly.” Those are the Bell V-280 Valor tiltrotor and the Sikorsky-Boeing SB>1 Defiant compound helicopter, which despite the term of art “demonstrator” are de facto prototypes. The companies are now refining their designs and, in 2022, the Army will choose one for mass production. While Phillips didn't provide details like flight hours – the Defiant has had a lot fewer so far – he said both aircraft are still providing test data to mature key technologies like flight controls.

FLRAA's smaller sister is the Future Attack Reconnaissance Aircraft, a light scout to replace the retired OH-58 Kiowa. Once again it's Bell and Sikorsky competing, but for FARA they haven't built the prototypes yet. Those are set to fly in 2023. (That said, Sikorsky's existing S-97 Raider is very close to their FARA design). Most of the work this year is being spent on digital design, said the FARA PM, Col. Gregory Fortier, but that should finish by December, so preparations to build the physical prototypes do have to get underway now.

“We have currently seen no impact, [but] there are certainly concerns within Bell and Sikorsky about long lead materials and shipping and the [subcontractors] at the second and third tier,” Col Fortier said. “They are okay with the summer timeframe and into the fall,” Fortier said. “If this thing stretches six months to a year, then that's a different conversation.”

The FARA scout, FLRAA transport, and future drones will all have as many components in common as possible, especially electronics, and need to seamlessly share both tactical and maintenance data. To make this happen, they're being designed to a common set of technical standards known as the Modular Open System Architecture, allowing the Army to plug-and-play MOSA-compliant components from any company for both maintenance and upgrades.

While existing Army aircraft can't be retrofitted with the complete open architecture, the Army plans to upgrade them with a mini-MOSA called the Aviation Mission Common Server. AMCS will both provide some of the benefits of open architecture to the current fleet and real-world experience to help build the future system.

AMCS, too, remains on schedule, the project manager said. “We are currently on track to award an OTA [Other Transaction Authority contract] in June 2020 and negotiations are currently ongoing,” Col. Johnathan Frasier said.

The Schedule To Stay On

Future Vertical Lift is doing a lot this year. Here's a list of most – not all – of the things they've accomplished so far and what they aim to do. A startling amount of it is due in June.

Modular Open Systems Architecture (involves multiple project managers)

  • April: Over 300 government and industry participants joined in a virtual meeting of the Architecture Collaboration Working Group fleshing out MOSA.
  • June: A follow-on ACWG meeting is scheduled. The Army will award an Other Transaction Authority (OTA) contract for the Aviation Mission Common Server (AMCS).

Engine & Electrical (PM: Col. Roger Kuykendal)

  • May-June: Tentative date for an industry day on electrical systems, including batteries, generators, Auxiliary Power Units (APUs), and thermal management (i.e. cooling).
  • June 15-19: Critical Design Review for the integrated engine system.
  • October: Power management systems demonstration, conducted with the Army C5ISR center.
  • Fall: Improved Turbine Engine testing begins.

Future Long-Range Assault Aircraft (PM: Col. David Phillips)

  • March 17: The Army awarded Bell and the Sikorsky-Boeing team contracts for Competitive Demonstration & Risk Reduction (CDRR) of their rival FLRAA designs.
  • June: FLRAA and FARA will hold a joint industry day – virtually, of course – on their shared mission systems. And the FLRAA competitors will deliver conceptual designs to help shape the program's final requirements.
  • Fall: Those FLRAA requirements will come up for review by the Army Requirements Oversight Council (AROC), a high-level body usually chaired by either the four-star boss of Army Futures Command or even the Army Chief of Staff himself.

Future Attack Reconnaissance Aircraft (PM: Col. Gregory Fortier)

  • March 25: The Army picked Bell and Sikorsky to build competing prototypes.
  • May 15: Industry responses are due for a formal Request For Information (RFI) on FARA mission systems.
  • June: FLRAA and FARA hold their joint industry day on shared mission systems. Boston Consulting Group will deliver the first of two studies on FARA-specific mission systems.
  • Summer (month not specified): Deloitte will deliver the second FARA mission systems study. Sikorsky and Bell will both go through Preliminary Design Review.
  • December: Sikorsky and Bell will submit their final designs. With those approved, they'll begin building the actual prototypes.

Unmanned Aircraft Systems (PM: Col. Scott Anderson)

  • April: The first FTUAS contender began field testing (formally “demonstrations”) at Fort Riley, Kan.
  • May: The second FTUAS contender began field testing at Fort Campbell, Ken.
  • May-June: This is the likely window for the Army to award three Other Transaction Authority contracts for the mini-drones known as Air-Launched Effects (ALE).
  • June-July: Third FTUAS contender begins testing at Fort Lewis, Wash.
  • July: Fourth contender begins testing at Fort Bliss, Tex.
  • August-September: A fifth unit begins testing at Fort Bragg, NC. There are only four different designs being studied, so this brigade will double up on of the designs already in testing.
  • Fall: The Army Requirements Oversight Council will review the final requirement for FTUAS – which will be based on how the contenders actually performed – as well as requirements for a highly automated Scalable Control Interface (SCI) for all future drones.

https://breakingdefense.com/2020/05/covid-cant-stop-a-busy-summer-for-army-fvl

Sur le même sujet

  • Contract Awards by US Department of Defense - July 23, 2019

    24 juillet 2019 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité, Autre défense

    Contract Awards by US Department of Defense - July 23, 2019

    DEFENSE LOGISTICS AGENCY Innovation Associates Inc., Johnson City, New York, has been awarded a maximum $450,000,000 firm‐fixed‐price, indefinite‐delivery/indefinite‐quantity contract for automated pharmaceutical equipment, accessories, maintenance and training under the Patient Monitoring and Capital Equipment Program. This is a five-year base contract with one five‐year option period. This was a competitive acquisition with 36 responses received. Location of performance is New York, with a July 22, 2024, performance completion date. Using customers are Army, Navy, Air Force, Marines, and federal civilian agencies. Type of appropriation is fiscal 2019 through 2024 defense working capital funds. The contracting activity is the Defense Logistics Agency Troop Support, Philadelphia, Pennsylvania (SPE2D1‐19‐D‐0017). Sikorsky Aircraft Corp., Stratford, Connecticut, has been awarded a maximum $9,804,501 firm-fixed-price delivery order (SPRPA1-19-F-C15B) against basic ordering agreement SPRPA1-17-G-C101, for H-53 hydraulic fluid tanks. This was a sole-source acquisition using justification 10 U.S. Code 2304 (c)(1), as stated in Federal Acquisition Regulation 6.302-1. This is a one-year contract with no option periods. Location of performance is Connecticut, with a Sept. 30, 2020, performance completion date. Using military service is Navy. Type of appropriation is fiscal 2019 Navy working capital funds. The contracting activity is the Defense Logistics Agency Aviation, Philadelphia, Pennsylvania. ARMY ASNA, Santa Ana, California (W911QY-19-D-0045); and Mills Manufacturing Corp.,* Ashville, North Carolina (W911QY-19-D-0046), will compete for each order of the $249,000,000 firm-fixed-price contract for the purchase T-11 Personnel Parachute System. Bids were solicited via the internet with two received. Work locations and funding will be determined with each order, with an estimated completion date of July 22, 2019. U.S. Army Contracting Command, Aberdeen Proving Ground, Maryland, is the contracting activity. North Carolina Division of Services for the Blind, Raleigh, North Carolina, was awarded a $42,289,265 firm-fixed-price contract for full food services to be provided at Fort Bragg, North Carolina. Bids were solicited via the internet with five received. Work locations and funding will be determined with each order, with an estimated completion date of July 31, 2024. U.S. Army Mission and Installation Contracting Command, Fort Sam Houston, Texas, is the contracting activity (W9124J-19-D-0014). NAVY GCR-MDI LLC,* Pinehurst, North Carolina, is awarded an $8,014,356 indefinite-delivery/indefinite-quantity contract for base operations support services at Naval Submarine Base, Kings Bay, and outlying areas. The work to be performed provides for base operations support services to include custodial, pest control, integrated solid waste management, grounds maintenance and landscaping, pavement clearance, and other related services. The maximum dollar value including the base period and four option years is $40,320,917. Work will be performed in Kings Bay, Georgia (99%); and outlying areas (1%), and is expected to be completed by September 2020. If all options are exercised, work will continue through September 2024. No funds will be obligated at time of award. Fiscal 2020 operations and maintenance (Navy); fiscal 2020 Defense Health Program; and fiscal 2020 family housing operations and maintenance (Navy) contract funds in the amount of $7,527,488 for recurring work will be obligated on individual task orders issued during the base period. This contract was competitively procured via the Navy Electronic Commerce Online website, with three proposals received. The Naval Facilities Engineering Command, Southeast, Jacksonville, Florida, is the contracting activity (N69450-19-D-1725). *Small Business https://dod.defense.gov/News/Contracts/Contract-View/Article/1914030//

  • Boeing, Saab announce rollout of EMD-phase T-7A Red Hawk aircraft - Skies Mag

    2 mai 2022 | International, Aérospatial

    Boeing, Saab announce rollout of EMD-phase T-7A Red Hawk aircraft - Skies Mag

    The first T-7A Red Hawk advanced trainer test aircraft built under the Engineering and Manufacturing Development (EMD) phase of the program was revealed at Boeing’s production facilities in St. Louis, Missouri.

  • RAF Retiring Reaper In 2024, Paving Way For Protector

    30 juillet 2019 | International, Aérospatial

    RAF Retiring Reaper In 2024, Paving Way For Protector

    By Tony Osborne LONDON—Britain is planning to retire its General Atomics MQ-9 Reaper unmanned aircraft systems in 2024 as the Royal Air Force transitions to its new Protector platform. Although Royal Air Force (RAF) officers have not detailed when the first of the new Protector aircraft will arrive, there will be a transition as crews retrain from Reaper onto Protector, with the Reaper complementing the Protector on operations, Wing Commander Judith Graham, the RAF's Protector Program Manager, told Aerospace DAILY at the Royal International Air Tattoo earlier this month. “Reaper is an extraordinarily valuable capability for the UK government, so we don't want there to be a capability gap,” Graham said. The plan for avoiding a capability gap between Reaper and Protector suggests that a significant number of Protectors will have entered service by the time the Reaper is retired. The UK currently has 10 MQ-9 Reapers that it purchased as an urgent operational requirement for operations in Afghanistan. Today, they operate over Iraq and Syria, but none are destined for use in UK airspace. Work also is underway to select the site for a new facility at RAF Waddington, UK, from which the Protector fleet and the UK's new E-7 Wedgetail airborne early warning aircraft will be operated. Graham said the facility needs “to be ready for Protector by the end of 2021,” suggesting that first Protector deliveries could take place in 2022. Britain plans to centralize its Protector operations from Waddington, resulting in the UK presence at Creech AFB, Nevada being scaled down. Because of the Protector's ability to self-deploy and perform autonomous landing and take-off, there also is a significantly reduced need for forward-based personnel to land the aircraft at forward-operating locations, further reducing the personnel burden. The UK currently is planning to buy 16 Protectors, a derivative of General Atomics' self-developed, certifiable SkyGuardian platform, which has been redesigned to pave the way for it to meet military airworthiness requirements. As a result, the aircraft now features an all-weather capability with an electro-expulsive de-icing system that blows the ice off the leading edges of the wings and Y-stabilizers. General Atomics also has increased the fatigue life and damage tolerance of the aircraft and produced flight-critical software certifiable to the DO-178 standard. British Protectors will be armed with the Raytheon Paveway IV laser-guided-bomb and MBDA Brimstone air-to-ground missile. There also are plans to fit it with Leonardo's Sage Electronic Support Measures system. The aircraft will also be equipped with General Atomics' Lynx synthetic aperture radar, but there are studies to look at installing a larger radar, such as Leonardo's Seaspray surface-search radar. Work on the integration of such a radar, which could allow the Protector to support the UK's new P-8 Poseidon in the maritime patrol role, is being scoped but is not yet funded. RAF officers are working alongside General Atomics at its San Diego, California, facility as part of a combined test team to pave the way for the platform's certification by the UK Military Aviation Authority, which the RAF hopes will allow the aircraft to fly in non-segregated airspace for training and support to national authorities. They are hoping to do this even without the immediate installation of General Atomics internally developed sense-and-avoid radar. The RAF's Protectors will be compatible, but not immediately equipped, with the active electronically scanned array radar, but Graham said work was underway with the UK's newly renamed Strategic Command (formerly Joint Forces Command) to understand the requirement for the radar, and test and evaluation work was underway. Officials state that the radar likely will be introduced as part of the full operational capability for the platform. The UK also will use the General Atomics Advanced Cockpit ground control station, which uses a similar flight management system to the Beechcraft King Air 350. Under current plans, the British Protectors will be flown by a crew of three—a pilot, a sensor operator and a mission intelligence coordinator. Rather than flying the aircraft from inside transportable containers, the seven ground control stations will occupy a permanent building with room for expansion. There also will be scope to add an additional mission specialist, should a particular mission require it, officials say. https://aviationweek.com/defense/raf-retiring-reaper-2024-paving-way-protector

Toutes les nouvelles