Back to news

October 9, 2024 | International, Land

American Rheinmetall Vehicles Wins Award for U.S. Army’s S-MET Inc II Program

American Rheinmetall Vehicles will manufacture and deliver eight proto­types to the Army in 2025 for testing, evaluation, and to compete against the platform delivered by the second awardee before the...

https://www.epicos.com/article/876533/american-rheinmetall-vehicles-wins-award-us-armys-s-met-inc-ii-program

On the same subject

  • Some F-35 suppliers are having trouble delivering parts on schedule, and Turkey’s departure could make that worse

    May 14, 2020 | International, Aerospace

    Some F-35 suppliers are having trouble delivering parts on schedule, and Turkey’s departure could make that worse

    By: Valerie Insinna WASHINGTON — Lockheed Martin's F-35 Joint Strike Fighter is on the verge of full-rate production, with a decision slated for early 2021. But a congressional watchdog group is concerned that as the company ramps up F-35 production, its suppliers are falling behind. And those supply chain problems could get even worse as Turkish defense manufacturers are pushed out of the program, the Government Accountability Office said in a May 12 report. According to the GAO, the number of F-35 parts delivered late skyrocketed from less than 2,000 in August 2017 to upward of 10,000 in July 2019. The number of parts shortages per month also climbed from 875 in July 2018 to more than 8,000 in July 2019. More than 60 percent of that sum was concentrated among 20 suppliers, it said. “To mitigate late deliveries and parts shortages — and deliver more aircraft on time — the airframe contractor has utilized methods such as reconfiguring the assembly line and moving planned work between different stations along the assembly line,” the GAO said. “According to the program office, such steps can cause production to be less efficient, which, in turn, can increase the number of labor hours necessary to build each aircraft,” which then drives up cost, the GAO added. Those problems could be compounded by Turkey's expulsion from the F-35 program, which was announced last year after the country moved forward with buying the Russian S-400 air defense system. Although Turkey financially contributed to the development of the F-35 as a partner in the program, the U.S. Defense Department has maintained that Turkey cannot buy or operate the F-35 until it gives up the S-400. The Pentagon has also taken action to begin stripping Turkish industry from the aircraft's supply chain, a process that involves finding new companies to make 1,005 parts, some of which are sole-sourced by Turkish companies. Ellen Lord, the Pentagon's undersecretary for acquisition and sustainment, had hoped to stop contracting with Turkish suppliers by March 2020, but in January she said that some contracts would extend through the year, according to Defense One. While the Defense Department has found new suppliers to manufacture the parts currently made in Turkey, it is uncertain whether the price of those components will be more expensive. Furthermore, as of December 2019, the new production rates for 15 components were lagging behind that of the legacy Turkish producers. “According to program officials, some of these new parts suppliers will not be producing at the rate required until next year, as roughly 10 percent are new to the F-35 program,” the GAO said. “Airframe contractor representatives stated it would take over a year to stand up these new suppliers, with lead times dependent on several factors, such as part complexity, quantity, and the supplier's production maturity. In addition, these new suppliers are required to go through qualification and testing to ensure the design integrity for their parts.” The F-35 Joint Program Office disagreed with the GAO's recommendation to provide certain information to Congress ahead of the full-rate production decision, including an evaluation of production risks and a readiness assessment of the suppliers that are replacing Turkish companies. In its statement, the JPO said it is already providing an acceptable number of updates on the program's readiness for full-rate production. Hard times for the F-35's engine supplier Not all F-35 production trends reported by the GAO were bad for the aircraft. Since 2016, Lockheed has made progress in delivering a greater proportion of F-35s on schedule, with 117 of 134 F-35s delivered on time in 2019. However, one of the biggest subsystems of the F-35 — the F135 engine produced by Pratt & Whitney — drifted in the opposite direction, with a whopping 91 percent of engines delivered behind schedule. At one point in 2019, Pratt & Whitney stopped deliveries of the F135 for an unspecified period due to test failures, which also contributed to the reduction of on-time deliveries. According to the Defense Contracts Management Agency, “there have been 18 engine test failures in 2019, which is eight more than in 2018, each requiring disassembly and rework,” the GAO wrote. “To address this issue, the engine contractor has developed new tooling for the assembly line and has established a team to identify characteristics leading to the test failures. Plans are also in place for additional training for employees.” https://www.defensenews.com/air/2020/05/12/some-f-35-suppliers-are-having-trouble-delivering-parts-on-schedule-and-turkeys-departure-could-make-that-worse/

  • En France, l’aviation de chasse est à la peine

    November 16, 2021 | International, Aerospace

    En France, l’aviation de chasse est à la peine

    DÉFENSE En France, l'aviation de chasse est à la peine Dans une vaste enquête, Air & Cosmos pointe les fortes tensions qui pèsent sur les flottes de l'armée française, en particulier dans le secteur stratégique de la chasse. Si au Sahel, 58% des frappes aériennes en 2020 ont été réalisées par des drones Reaper, cette efficacité apparait en partie due à la nature asymétrique du conflit qui se joue dans la bande sahélo-saharienne. Or, la plupart des autres conflits nécessiteront probablement des chasseurs, polyvalents, réactifs et adaptables. Dans ce contexte, l'Armée de l'Air et de l'Espace (AAE), qui s'est vu prélever 12 appareils à destination de la Grèce, fait face à une réduction de ses équipements, alors qu'au moins 12 autres avions devraient suivre afin d'honorer le contrat passé avec la Croatie. Une situation qui, d'après Air & Cosmos met à mal la situation de l'AAE, fragilisée par le manque de personnels (ses effectifs ont décru de 25% en quelques années) et les ponctions export. Une situation qui justifierait l'établissement d'un plan d'urgence pour assurer la modernisation et la soutenabilité des équipements des armées françaises. Air & Cosmos du 12 novembre

  • Maine lawmakers want contract relief, quicker payments for industry to combat COVID-19 impact

    March 20, 2020 | International, Naval

    Maine lawmakers want contract relief, quicker payments for industry to combat COVID-19 impact

    By: Aaron Mehta WASHINGTON — In a letter to Secretary of Defense Mark Esper and acting Navy secretary Thomas Modly, the congressional delegation from Maine has requested quicker payments and relief from contractual obligations for the defense industrial base, including local shipyards, impacted by the COVID-19 outbreak. In the letter sent Thursday, the delegation — Republican Sen. Susan Collin and Independent Sen. Angus King, as well as democratic Reps. Chellie Pingree and Jared Golden — warn that “the Department of Defense and the Navy must immediately act to protect our nation's defense industrial base, including our nation's shipyards.” Maine is home to Bath Iron Works, owned by General Dynamics, which produces both the Zumwalt and Arleigh Burke class destroyers. The delegation has three key demands. The first is for the department to “work to mitigate cash flow and other financial burdens” on contractors and subcontractors as a result of the outbreak, “to include relief from contracting requirements that are uniquely impacted by COVID-19.” The contract relief being sought involves waiving schedule and price requirements in case delivery times are impacted by loss of workforce due to coronavirus-inflicted travel bans, closures, quarantines or travel restrictions. It could also potentially give cover should a subcontractor be unable to deliver a part on time. Second, to take “any actions possible to accelerate or advance payments or new contract obligations in order to provide immediate stability to the industrial base.” The lawmakers offer to “immediately assist” the department if additional funding or “new legal authorities” are needed to make such sped-up payments possible. And third, the delegation calls for the department to clarify “planning and public guidance to ensure a stable industrial base while also ensuring the health and safety of the defense industrial base workforce” — that is, to make clear what workers must stay at work, and which could potentially work from home. A spokesman for General Dynamics told Defense News earlier this week that they are allowing anyone who can work from home to do so, while curtailing travel and pausing participation in trade shows. “An outbreak of COVID-19 at one of our nation's shipyards or other large defense contractors could truly be devastating to our national defense,” the delegation writes. “We ask you to work with and support industry to take all the necessary protective actions.” King is a member of the Senate Armed Services Committee, while Collins sits on the appropriations defense subcommittee. Pingree is a member of the House Appropriations Committee while Golden is on the House Armed Services Committee. It is expected that Collins, at least, will be speaking directly to Modly about the issue in the near future. https://www.defensenews.com/coronavirus/2020/03/19/maine-lawmakers-want-contract-relief-quicker-payments-for-industry-to-combat-covid-19-impact

All news