9 juillet 2020 | International, Naval

US Navy shakes up the carrier Ford program after latest setback

By:

WASHINGTON –The officer overseeing the deployment of the carrier Gerald R. Ford was fired Wednesday, the latest jolt to the trouble program that has been operating under a microscope as technical problems with nearly two dozen new technologies bundled into the lead ship have piled up.

Capt. Ron Rutan was removed by Assistant Secretary of the Navy for Research, Development and Acquisition James Geurts last Wednesday in connection with his “performance over time” in the role as program manager for the ship.

“Based on the recommendation of PEO Aircraft Carriers [Rear Adm. James Downey] due to performance over time, ASN RDA Geurts reassigned CVN 78 (PMS 378) Program Manager Capt. Ron Rutan to Naval Sea Systems Command (NAVSEA) staff, and selected Capt. Brian Metcalf, previously LPD 17 program manager and Executive Assistant to COMNAVSEA, as his relief, effective 1 July,” according to a statement from Naval Sea Systems Command spokesman Rory O'Connor

The Navy said the change was made to get “fresh eyes” on the effort to get the new aircraft carrier through its post-delivery test and trial period, which will go on through the rest of this year before the ship heads into full-ship shock trials, where live explosives are set off next the ship to see how it handles battle damage.

“While there is no perfect time for leadership transitions, it is prudent to bring in renewed energy now to lead the CVN 78 team through the challenges ahead,” the statement reads. “Capt. Metcalf's proven program management acumen and extensive waterfront experience will be a tremendous asset to the CVN 78 team in the months ahead.”

News of Rutan's removal was first reported by USNI News.

The Ford has had a witches' brew of technical problems and accompanying delays and setbacks since construction of the ship began in 2005. Much of the trouble is the result of trying to pack too much new stuff in a single new hull, and Rutan's firing shows the problems are still vexatious, said Jerry Hendrix, a retired Navy captain and analyst with the Telemus Group.

“Obviously the problems on the Ford are still beyond the managers' ability to control them,” Hendrix said . “And while this may be a blow to Capt. Rutan's career, it sounds like they just needed to move on to someone who will take a different approach and brought a different perspective. It may be more about getting to the next guy as it is removing the current guy.

“Look, I don't think it's possible to overstate the complexity of the Ford program.”

The ship, conceived in an era when the Defense Department was looking to make giant steps forward in military technology while it had no direct peer competitors, packed at least 23 new technologies into the lead ship. Those included a complete redesign of the systems used to arm, launch and recover the ship's aircraft.

All those systems have, in their turn, caused delays in getting the Navy's most expensive-ever warship to the fleet, which was originally to have deployed in 2018, but now will likely not deploy until 2023. The Ford cost the Navy roughly $13.3 billion, according to the latest Congressional Research Service report.

Trials and tribulations

The latest hiccup came in the form of a fault in the power supply system to the electromagnetic aircraft launch system, which is replacing the old steam catapult system on the Nimitz-class carriers. The fault curtailed flight operations on the ship for several days while the crew and contractors tried to identify the issue.

Prior to the latest EMALS issue, the Advanced Weapons Elevators – which are designed to reduce the time it takes to get bombs armed and to the flight deck for mounting on aircraft – became the center of a firestorm and contributed to former Secretary of the Navy Richard Spencer's firing last year.

In January 2019, Spencer announced he'd told the President that if the weapons elevators aren't functioning by mid-summer, then he should fire him. But within months Spencer had to admit that the weapons elevators would not be finished until the end of 2021 or maybe 2022, which he blamed on Huntington Ingalls Industries for not communicating adequately.

Making the Ford deployment ready was a focus of former acting Navy Secretary Thomas Modly, who likened the ship to an albatross around the Navy's neck.

“The Ford is something the president cares a lot about, it's something he talks a lot about, and I think his concerns are justified,” Modly said. “It's very, very expensive, and it needs to work.

“And there is a trail of tears that explains why we are where we are, but right now we need to fix that ship and make sure it works. There is nothing worse than having a ship like that, our most expensive asset, being out there as a metaphor for why the Navy can't do anything right.”

https://www.defensenews.com/naval/2020/07/07/the-us-navy-shakes-up-the-carrier-ford-program-after-latest-setback/

Sur le même sujet

  • Economics Of Rocket Reuse Still Up In The Air

    16 avril 2020 | International, Aérospatial

    Economics Of Rocket Reuse Still Up In The Air

    Irene Klotz The first Falcon 9 rocket to land successfully after dispatching a payload into orbit stands on permanent display outside SpaceX headquarters in Hawthorne, California, a testament to the perseverance of founder, CEO and chief engineer Elon Musk, who wants a fleet of fully reusable spaceships to reduce the cost of colonizing Mars. The vision is shared by fellow tech entrepreneur Jeff Bezos, whose Kent, Washington-based Blue Origin space company is developing a series of reusable vehicles, beginning with the New Shepard suborbital passenger transport system. The New Shepard made 12 uncrewed flight tests over the last five years, with more to come before commercial flights begin. Bezos also has pumped $2.5 billion into developing the New Glenn, a reusable system powered by seven BE-4 methane-fueled engines designed to carry nearly 50 tons to low Earth orbit. “That is the smallest orbital vehicle we are planning to build and launch,” says Clay Mowry, Blue Origin vice president of sales, marketing and customer experience. But the first BE-4s to power a rocket to orbit may not be aboard the New Glenn. United Launch Alliance (ULA) is buying the engines to power the first stage of its Vulcan rocket, an expendable booster—at least for now—which, like the New Glenn, is slated to debut next year. At some point, ULA may decide to recover and reuse just the BE-4 engines, a pair of which will fly on each Vulcan. The idea is for the engine compartment to disengage after launch and fall back through the atmosphere protected by an inflatable hypersonic shield. A helicopter would be positioned to snag the engine section midair as it makes a parachute descent. ULA calls the approach its Sensible Modular Autonomous Return Technology, or SMART. “It does not impact, in any significant way, the overall performance of the launch vehicle because you don't have to save fuel to fly home with,” ULA CEO Tory Bruno tells Aviation Week. “You still get to burn up all your fuel, separate your engine, which is the most expensive piece, and recover it.” “We have not really changed our assessment over the last couple of years because we have yet to see the other forms of reusability—flyback or propulsive return to Earth—demonstrate economic sustainability on a recurring basis,” Bruno says. “It's pretty darn hard to make that actually save money. . . . We've seen nothing yet that changes our analysis on that.” SpaceX currently is the only launch company reflying orbital rockets. SpaceX launched its final version of the workhorse Falcon 9 booster, called the Block 5, in May 2018. Within two months, the company was flying Block 5s exclusively. The upgrade includes higher-thrust Merlin engines, stronger landing legs and dozens of upgrades to streamline recovery and reuse. Block 5s were designed to fly 10 times with minimal maintenance between flights, and up to 100 times with refurbishment. SpaceX President and Chief Operating Officer Gwynne Shotwell says the company no longer expects to need to fly a Falcon 9 more than 10 times. “We don't have to ramp up our production, at least for boost phases, like we thought we were going to,” Shotwell said on March 10 at the Satellite 2020 conference in Washington. “From a reliability perspective, we want to know the limits of Falcon 9, so we'll push them, but . . . some government customers want new vehicles—I think over time, they will come to flight-proven vehicles as well,” she added. “But if I have to build a couple of new ones every year, or 10 new ones a year, that adds to the fleet, and I don't know that I'll have to push a rocket more than 10 [flights.]” With regard to how much the company has been able to cut costs by reflying rockets, Shotwell would only say, “We save a lot of money.” As a privately held company, those operating expenses are not publicly available, but the Block 5 flight record is. So far, SpaceX has flown 14 Block 5 core boosters over 31 missions, including two Falcon Heavy flights, which use three cores apiece. Of those 14 boosters with flight history, five remain part of the operational fleet. The rest were expended—several after multiple missions—due to payload performance requirements or unsuccessful landings. One booster was intentionally destroyed as part of a Crew Dragon capsule launch abort flight test. SpaceX's fleet leader flew five times before failing to land on a drone ship stationed off the Florida coast on March 18. SpaceX has not said if the botched landing was related to a premature engine shutdown during the final phases of ascent. The rocket's remaining eight Merlin engines compensated for the shutdown, and the payload—a batch of 60 SpaceX Starlink broadband satellites—reached its intended orbit. While it continues to fly the Falcon 9 and Falcon Heavy for NASA, national security and commercial missions, SpaceX is developing a fully reusable, human-class deep-space transportation system called Starship at its own expense. Another company testing the waters of reusability is Rocket Lab, which builds and flies the Electron small-satellite launcher. “For a long time, I said we weren't going to do reusability,” Rocket Lab CEO Peter Beck said in August 2019, when he announced the new initiative. “This is one of those occasions where I have to eat my hat.” Electrons do not have the performance for a propulsive return like SpaceX's Falcons do, so Rocket Lab is pursuing a midair, helicopter recovery system to snare the booster's first stage. The intent is not to reduce costs per se but to increase flight rates without having to boost production. The company currently is producing one Electron rocket about every 30 days. “We need to get that down to one a week,” Beck says. “We view [rocket reuse] as sort of a journey,” ULA's Bruno adds. “We're going to start with the engines because we're pretty sure we can save money with that and pass those savings on right away. As we learn more by doing, we'll continue to assess other valuable parts of the rocket, and we may discover that we can do that there as well.” “There is one funny thing about reusability,” he adds. “As you make your rocket less expensive, and you make parts of your rocket less expensive, it's harder to close a business case on reuse because the thing you're recovering isn't as valuable. There's a balance there.” https://aviationweek.com/shows-events/space-symposium/economics-rocket-reuse-still-air

  • Fincantieri buys Leonardo’s torpedo unit in deal that could reach $446M

    9 mai 2024 | International, Terrestre

    Fincantieri buys Leonardo’s torpedo unit in deal that could reach $446M

    Originally known as WASS, the torpedo unit saw €160 million in revenue last year.

  • US Army increases investment on counter-drone program

    2 août 2018 | International, C4ISR

    US Army increases investment on counter-drone program

    By: Daniel Cebul WASHINGTON — Leonardo DRS has received an additional $13 million to continue engineering and testing a vehicle-mounted system that the U.S. Army hopes will protect soldiers from small drones, according to a July 31 Defense Department statement. Leonardo was awarded an initial $16 million contract by the Army in July 2017 to develop a counter-UAV capability dubbed the Mobile Low, Slow Unmanned Aerial Vehicle Integrated Defense System, or MLIDS, with hopes of deploying “numerous production systems in early summer 2018." At the annual Association of the U.S. Army conference in October, the company announced it had received a $42 million production contract for an undisclosed number of MLIDS to fit the Army's requirement to defeat small, inexpensive unmanned systems such as quadcopters and fixed-wing aircraft that operate as airborne improvised explosive devices. “Drones are becoming an increasingly dangerous threat against our forward-deployed soldiers, and we are proud to support this urgent requirement to protect them from potentially lethal small unmanned aerial vehicles,” Aaron Hankins, vice president and general manager for DRS Land Systems, said in October 2017. “We are working hard to deliver the best capability to our soldiers as quickly as possible." Full article: https://www.c4isrnet.com/unmanned/2018/08/01/us-army-increases-investment-on-counter-drone-matv-program/

Toutes les nouvelles