10 juin 2020 | International, Aérospatial

US Air Force delays full-rate production decision for KC-46 aircraft

By:

WASHINGTON — The U.S. Air Force will delay a full-rate production milestone for the KC-46 aerial refueling tanker to the end of fiscal 2024 to correspond with a fix for one of the aircraft's key systems, the service announced late Monday.

The Pentagon's independent weapons tester — Director of Operational Test and Evaluation Robert Behler — intends to conclude operational testing of the KC-46 only after prime contractor Boeing fixes the tanker's critical deficiencies and has finalized its production configuration.

“Accordingly, the Air Force will defer the KC-46 full rate production decision until after the completion of [initial operational test and evaluation], and the receipt of the statutorily-required Beyond Low Rate Initial Production report from [Behler],” the Air Force said in a statement.

The KC-46 program has several remaining category 1 deficiencies, the term used by the Pentagon to describe the most serious form of technical problems.

Two of the deficiencies involve the aircraft's remote vision system, which is a series of cameras and sensors used by the boom operator to see outside the KC-46 and refuel other aircraft. The Air Force has contended that the RVS does not properly function in all weather and lighting conditions; the service has refused to deploy the KC-46 until the problem is fixed.

Boeing in April agreed to completely redesign the system on its own dime, which will take until at least 2023.

One other issue involves the KC-46 boom, which was developed to meet NATO-specific requirements but cannot refuel the A-10 aircraft. The Air Force is paying to redesign the boom actuator, as the service signed off on the original design and did not realize until afterward that it did not meet the specifications needed to refuel the A-10.

In March, the Air Force announced an additional category 1 deficiency after maintainers found fuel leaking between the tanker's primary and secondary fuel protection barriers. It is unclear whether this is still a problem, as Boeing had already developed a fix and began retrofitting aircraft when the issue was revealed.

“Given its confidence in deficiency resolution timelines for both the aerial refueling boom and Remote Vision System, the Air Force is rescheduling the KC-46's Full Rate Production Decision milestone to late Fiscal Year 2024,” the service stated.

The Air Force notes that delaying the full-rate production decision will not affect the program's cost — which is locked into place courtesy of a firm, fixed-price deal with Boeing that holds the contractor financially responsible for cost overruns;nor will it cause the service to alter its current delivery schedule.

Boeing is already producing KC-46s at “full rate,” which for the program is 15 tankers per year. It delivered the first KC-46 to McConnell Air Force Base, Kansas, in January 2019. Since then, Altus Air Force Base, Oklahoma, and Pease Air National Guard Base, New Hampshire, have also taken on new KC-46s.

Boeing is set to produce 179 KC-46s over the program of record. The company has racked up cost overruns of about $4.6 billion in excess of the $4.9 billion contract it was awarded in 2011.

https://www.defensenews.com/air/2020/06/09/the-air-force-delays-a-full-rate-production-decision-for-the-kc-46/

Sur le même sujet

  • Tunisia receives four T-6C training aircraft from U.S

    18 juillet 2023 | International, Aérospatial

    Tunisia receives four T-6C training aircraft from U.S

    The Tunisian defense ministry said on Tuesday it had received four T-6C training aircraft from the United States, as part of cooperation to renew its fleet of training aircraft for the air force.

  • Pressed to prove value of amphibious ships, Marines seek to add drones

    29 juin 2023 | International, Aérospatial, Naval

    Pressed to prove value of amphibious ships, Marines seek to add drones

    The Corps’ prized amphibious ships might house and launch unmanned aircraft and vessels, along with an undefined array of other warfighting technology.

  • The US military ran the largest stress test of its sealift fleet in years. It’s in big trouble.

    2 janvier 2020 | International, Naval

    The US military ran the largest stress test of its sealift fleet in years. It’s in big trouble.

    By: David B. Larter WASHINGTON — The U.S. military in September ordered the largest stress test of its wartime sealift fleet in the command's history, with 33 out of 61 government-owned ships being activated simultaneously. The results were bad, according to a new report. In an unclassified U.S. Transportation Command report posted to its website, the so-called turbo activation revealed that less than half of the sealift fleet would be fully prepared to get underway for a major sealift operation in a crisis. “The relatively low ... Qualitative Mission Success Rate indicates the Organic Surge Fleet is challenged to be immediately available for a large-scale inter-theater force deployment without delays/impacts to force closure due to degraded readiness,” the report read. The Dec. 16 report confirms what senior military and transportation officials have been saying for years now: that the sealift fleet is in urgent need of recapitalization if it is to be relied upon to support a large-scale operation overseas. In a crisis, nearly 90 percent of all Army and Marine Corps equipment would be carried by ship. The Navy is on the hook to pay for recapitalization, but it has so far failed to land on a strategy to do so. Overall, 40.7 percent of the 61 ships operated by Military Sealift Command and the Maritime Administration were fully ready to support a major sealift operation. Sal Mercogliano, a merchant marine and current professor at Campbell University who closely follows these issues, said the major equipment casualties are the driving factor that is dragging down readiness. “You had 22 out of the 61 ships in either C-5 or C-4 condition,” Mercogliano said. “C-5 means that you can't even leave the dock; C-4 means you can leave the dock but you are not in any condition to sail any real distance. In my ballpark, that's non-mission capable. So right off the bat you lose 22 of the 61 ships. Then of the 33 that they activated, nine of them had issues. Three of them were C-4 level. “So when you add together the ones that had issues with the ones that couldn't be activated, they're saying you can only really count on about 40 percent of the fleet to active when they are aiming for 85 percent.” Ultimately, the degraded status of the sealift fleet means that combatant commanders won't be able to count on its capacity for logistics support, Mercogliano said. “If you are Indo-Pacific Command, or you are Central Command, and you are counting on a certain amount of square footage available to you, that's going to have huge ramifications,” he added. In recent testimony, INDOPACOM Commander Adm. Phil Davidson said as much, saying his operational plans depend on logistics support. “Clearly recapitalization of our sealift system is going to be critically important, as it's aging out and really has propulsion plants that [are] expiring in capability and our ability to maintain them,” Davidson said. “It's [a] risk to our troops and all of our people that are forward in the region if there is any delay in our ability to deliver the logistics in accordance with the [operation] plans.” Manning concerns In a November interview prior to the compilation of the final report, Maritime Administrator retired Rear Adm. Mark Buzby told Defense News that the test validated the data they had on ship readiness and the Maritime Administration's ability to crew the vessels, which he has long maintained is enough for initial activation but would suffer during a prolonged effort. “I think given the scale of the test, as we've been saying, we are OK for doing initial manning for our ships when they are activated,” Buzby said. “Something that we couldn't test in this fairly short-term activation was the follow-on aspect. “We believe we have plenty of manning to man up the ships initially, get them past the sea buoy and get them on the mission. But the problem is going to manifest itself four to six months down the line when some of them want to rotate. Who is going to be standing on the pier ready to take their place? That's where we have a problem. You just couldn't show that in this activation.” One of the primary issues has been, as Davidson intimated, that many of the plants in the Ready Reserve Force are steam-operated plants, which are all but nonexistent in the commercial world, so it is increasingly difficult to find qualified engineers. Finding steam engineers went well for the turbo activation, Buzby said, but it proved difficult and will only become more so as fewer opportunities to retain updated certifications become available. In a 2018 interview with Defense News, Buzby described a shortage of personnel that would affect the sealift fleet's ability to operate for an extended period of time. The Maritime Administration, part of the Department of Transportation, estimates it has 11,768 qualified mariners with unlimited credentials available to crew the Ready Reserve Force, a number that just exceeds the needed total of 11,678 to operate both the reserve and commercial fleets at the same time. But that comes with a catch: This service is entirely voluntary. “Maritime Workforce Working Group estimates that there are sufficient mariners working in the industry to activate the surge fleet if the entire pool of qualified United States citizen mariners identified by MWWG are available and willing to sail when required,” the report read. “This assumption is of paramount importance given the voluntary nature of mariner service.” Furthermore, that number is just what it would take to activate the ships and temporarily operate them. If the nation needed to sustain a large-scale effort, it would soon begin to falter. “We are about 1,800 mariners short for any kind of long-term sustainment effort,” Buzby said. “We believe we have enough today to activate all the ships we would need to activate. ... But anything less than an all-of-nation effort ... where everyone who went out to sea, stayed at sea, we start to run short of people as we rotate.” https://www.defensenews.com/naval/2019/12/31/the-us-military-ran-the-largest-stress-test-of-its-sealift-fleet-in-years-its-in-big-trouble/

Toutes les nouvelles