14 janvier 2019 | International, Aérospatial, Naval

Sink Feeling: The Navy's 7 Big Problems (One Is the F-35)

by Michael Peck

“The Navy continues to struggle with rebuilding the readiness of the existing fleet due to enduring maintenance and manning challenges,” the report finds. “As the Navy seeks to expand its fleet by 25 percent, these challenges will likely be further exacerbated and the Navy will likely face additional affordability challenges.”

The Navy must fix the teething troubles of a new and complicated aircraft that lacks sufficient spare parts: in 2017, only 15 percent of Marine F-35Bs were rated fully mission-capable. “The Navy and the Marine Corps may have to decide whether they are willing to accept less reliable and maintainable aircraft than originally planned,” GAO warned.

How can the U.S. Navy buy more ships and planes when it can't maintain the ones it has?

That's the question posed by a new Government Accountability Office report .

“The Navy continues to struggle with rebuilding the readiness of the existing fleet due to enduring maintenance and manning challenges,” the report finds. “As the Navy seeks to expand its fleet by 25 percent, these challenges will likely be further exacerbated and the Navy will likely face additional affordability challenges.”

Auditors point to seven problems that GAO, Congress's watchdog agency, have highlighted over the past several years, but which have yet to solved:

Training:

After a series of embarrassing collisions at sea in 2017, which led to fears that Navy has forgotten basic ship-handling skills, training was revamped along with fewer waivers for required training. Still, “while the Navy has demonstrated its commitment to ensuring that crews are certified prior to deploying, training for amphibious operations and higher-level collective training may not be fully implemented for several years.”

Maintenance backlogs:

Between 2012 and 2018, only 30 percent of maintenance was completed on schedule. In particular, most Navy attack submarines have suffered maintenance delays. The backlog is caused by insufficient capacity in public shipyards as well as shortages of shipyard workers.

Overworked sailors:

In 2017, GAO concluded that the Navy was underestimating how many sailors were needed to man ships, leading to undersized crews and overworked sailors. The Navy says it is aiming for surface ships based overseas to have a minimum of 95 percent of their complement, but GAO auditors who interviewed crews in Japan were told that “the Navy's methods for tracking fit and fill do not account for sailor experience and may be inaccurately capturing the actual presence of sailors onboard and available for duty on its ships. Moreover, sailors consistently told us that ship workload has not decreased, and it is still extremely challenging to complete all required workload while getting enough sleep.”

Unrealistic budgeting:

The Navy wants to boost the number of ships by 25 percent, and is planning to buy 301 new ships between now and 2048 as well as extending the life of older destroyers and submarines. But GAO and the Congressional Budget Office have calculated that the Navy “has consistently and significantly underestimated the cost and timeframes for delivering new ships to the fleet. For example, the Navy estimates that buying the new ships specified in the fiscal year 2019 plan would cost $631 billion over 30 years while the Congressional Budget Office has estimated that those new ships would cost $801 billion—a difference of 27 percent.”

Aging aircraft:

Numerous aircraft models across the Navy, Air Force and Marine Corps have been plagued by low availability rates due to aging aircraft, lack of spare parts for older planes, and too few mechanics.

Too few pilots:

The shortage of Marine Corps fighter pilots quadrupled to 24 percent between 2006 and 2017, while the Navy has been scrambling to fill pilot vacancies. “Further compounding their pilot shortages, we also found that the services have not recently reevaluated squadron requirements to reflect an increased fighter pilot workload,” said GAO. “As a result, the reported shortage actually could be greater.”

The F-35:

The Navy must fix the teething troubles of a new and complicated aircraft that lacks sufficient spare parts: in 2017, only 15 percent of Marine F-35Bs were rated fully mission-capable. “The Navy and the Marine Corps may have to decide whether they are willing to accept less reliable and maintainable aircraft than originally planned,” GAO warned.

Michael Peck is a contributing writer for the National Interest. He can be found on Twitter and Facebook.

https://nationalinterest.org/blog/buzz/sink-feeling-navys-7-big-problems-one-f-35-41502

Sur le même sujet

  • Ukraine aerospace sector's push for Western tie-ups met with skepticism | Reuters

    5 décembre 2023 | International, Aérospatial

    Ukraine aerospace sector's push for Western tie-ups met with skepticism | Reuters

    Aerospace group Motor Sich has little to show so far for a wartime effort to woo potential partners in the West, as it seeks new direction after it lost Russia as its biggest client and had a China tie-up blocked.

  • Meet the new hybrid tank competing for serial production in Turkey

    1 février 2021 | International, Terrestre

    Meet the new hybrid tank competing for serial production in Turkey

    By: Burak Ege Bekdil ANKARA, Turkey — A Turkish-Qatari armored vehicles manufacturer has unveiled a hybrid tank that combines the hull of a German Leopard 2A4 with a Turkish-made turret in an effort to win a serial production contract. The tank was displayed by BMC on Jan. 23 to a high-profile delegation including Turkish Defense Minister Hulusi Akar and top military brass. A BMC official said the company hopes to win a serial production/upgrade contract from the Turkish government for the hybrid tank. He added that serial production would involve more than 300 Leopard tanks receiving the hybrid upgrade. “If the military command decides to order mass production, we will start the work immediately,” he said. BMC hopes the hybrid model will become combat-proven after entering the Turkish military's inventory. “That will pave the way for similar upgrades on hundreds of Leopards in different parts of the world,” the company official said. “Export potential is bigger than the Turkish contract.” The hybrid Leopard is equipped with Turkish-made active protection, fire control and laser warning systems. It combines the chassis of the iconic German tank with the turret of the locally developed Altay, which includes a 120mm smoothbore gun. A source with knowledge of the hybrid program told Defense News the contract is estimated to be worth “several hundreds of millions of dollars.” The tank will not be a substitute to the multibillion-dollar Altay program. Under that effort, Turkey plans to build 1,000 units of the new-generation main battle tank. BMC won the serial production contract for the Altay, but the program has struggling over the past few years as Turkey continues its search for an imported power pack (engine and transmission system). Most recently BMC started negotiations with South Korea's Hyundai-Rotem for a power pack for the Altay after talks failed with German suppliers, among a number of other companies. https://www.defensenews.com/industry/techwatch/2021/01/29/meet-the-new-hybrid-tank-competing-for-serial-production-in-turkey

  • Cure de rajeunissement des hélicoptères CH-146 | Un projet de 800 millions, retombées difficiles à chiffrer

    2 juin 2022 | International, Aérospatial

    Cure de rajeunissement des hélicoptères CH-146 | Un projet de 800 millions, retombées difficiles à chiffrer

    Bell Textron Canada pilotera un projet de 800 millions pour prolonger la durée de vie des 85 CH-146 Griffon de l’Aviation royale canadienne, mais seulement 9 hélicoptères se poseront à l’usine de la multinationale située à Mirabel pour y subir une cure de rajeunissement.

Toutes les nouvelles