Pentagon, Lockheed Martin Failed to Ensure Proper Parts for F-35

CHARLES S. CLARK

A major contractor and the Pentagon's top management office came in for criticism from an inspector general for cutting corners in assuring that the massive joint-service F-35 stealth fighter is equipped with ready-for-issue parts.

In a report dated June 13, the Defense Department watchdog found that parts for the department's largest acquisition—with an estimated $406 billion price tag and sales planned to foreign allies—were not being received according to the contracts and performance incentives.

The parts contracted for delivery by Lockheed Martin Corp. include wheel, seat, and window assemblies, said the audit addressed to the Defense secretary for acquisition, the Air Force secretary, the Air Force inspector general and the Defense Contract Management Agency. The federal contracting offices and the corporate teams working on the plane are supposed to ensure the sustaining parts are delivered “ready for aircraft maintenance personnel to install on the aircraft,” as well as have an Electronic Equipment Logbook assigned that spells out each part's history and remaining life.

Too often, however, the parts arrived not ready in accordance with contracts and incentive fees on the sustainment contracts because of “inflated and unverified F‑35A aircraft availability hours. This occurred because the [Joint Program Office] did not conduct adequate oversight of contractor performance related to receiving F‑35 spare parts and aircraft availability hours,” the report said, calling the inflation of hours unintentional.

As a result, the department received non-ready spare parts and spent up to $303 million in labor costs since 2015, “and it will continue to pay up to $55 million annually” for such parts until a fix is made. In addition, the Defense Department has “potentially overpaid” $10.6 million in performance incentive fees by not independently collecting and verifying aircraft availability hours.

“The lack of available [ready-for-issue] spare parts could result in the F‑35 fleet being unable to perform required operational and training missions,” the report warned.

The Joint Program Office was aware of the problem, auditors found during their review from June 2018 to April 2019, but did not resolve the issue or require the services to better track the non-compliant parts. Interviews with the Joint Program Office staff in Arlington, Va.; the DCMA administrative office in Lockheed Martin's facility in Fort Worth, Texas; and Lockheed staff at three sites found, for example, that of 74 spare parts delivered to Hill Air Force Base in Utah from Sept. 17-30, 2018, 59 spare parts (80 percent) were non-ready for issue. Of the 263 spare parts delivered to Luke Air Force Base in Arizona in June 2018, 213 spare parts (81 percent) were non‑ready. And of 132 spare parts delivered to the Marine Corps Air Station in Beaufort, S.C., in September 2017, 58 spare parts (44 percent) were non‑ready.

The IG recommended that the F-35 program executive officer improve oversight by coordinating with DCMA to pursue compensation from the contractor for the costs of mishandling the supply of spare parts since 2015. It also recommended that he direct the contracting officer to add clarifying language to future sustainment contracts, and task the lead contracting office with updating its Quality Assurance Surveillance Plan.

Navy Vice Adm. Mathias Winter, the program executive, agreed, stating that there is value added in tracking and using contractor performance data.

https://www.govexec.com/defense/2019/06/pentagon-lockheed-martin-failed-ensure-proper-parts-f-35/157822/

Sur le même sujet

  • Northrop Grumman secures $164M contract for Hawkeye aircraft for Japan

    7 septembre 2018 | International, Aérospatial

    Northrop Grumman secures $164M contract for Hawkeye aircraft for Japan

    By: Mike Yeo MELBOURNE, Australia — The contract for the last of four Northrop Grumman E-2D Advanced Hawkeye airborne early warning aircraft ordered by Japan has been awarded, as the country announces plans to reorganize its airborne early warning aircraft command. According to a Sept. 5 contract award announcement by the U.S. Department of Defense, Northrop Grumman has been awarded a $164 million firm-fixed-price modification to an existing contract for a new-build E-2D Advanced Hawkeye aircraft . This follows similar contract awards in November 2015, July 2016 and June 2018, and brings the total procurement cost for Japan for the four E-2Ds to $633 million, not inclusive of engineering and other related costs. The first Japanese E-2D is currently undergoing flight tests, having made its first flight from Northrop Grumman's Aircraft Integration Center of Excellence in St. Augustine, Florida, in October 2017, with delivery expected in late 2019. The E-2D is the latest variant of the E-2 Hawkeye carrierborne, airborne early warning aircraft, which is already being operated by the U.S. Navy. It features a new Lockheed Martin AN/APY-9 ultrahigh-frequency-band radar, which is able to detect and track cruise missiles and low-observable aircraft. However, the Japanese aircraft are not fitted with the Cooperative Engagement Capability, or CEC, like U.S. Navy E-2Ds. CEC is a sensor network with integrated fire control capability that combines data from multiple battle-force air-search sensors on CEC-equipped units into a single, real-time, composite track picture. Japanese media has also previously reported that the Defense Ministry is looking to equip its E-2Ds and Aegis-equipped destroyers with CEC, allowing the former to guide missiles fired by the latter. Full article: https://www.defensenews.com/air/2018/09/06/northrop-grumman-secures-164m-contract-to-modify-hawkeye-aircraft-for-japan

  • Leonardo CEO sees European 'change of mindset' on defence

    23 février 2023 | International, Autre défense

    Leonardo CEO sees European 'change of mindset' on defence

    European countries have become far more ready to invest in defence and security in the wake of the war in Ukraine, the head of Italy's defence and aerospace group Leonardo said on Thursday.

  • Europe’s new warplane program could finally, maybe, take off

    22 novembre 2022 | International, Aérospatial

    Europe’s new warplane program could finally, maybe, take off

    Eric Trappier, the boss of France's industry lead Dassault, plays down progress as a "a pseudo-political announcement."

Toutes les nouvelles