20 juin 2019 | International, Aérospatial

Pentagon, Lockheed Martin Failed to Ensure Proper Parts for F-35

CHARLES S. CLARK

A major contractor and the Pentagon's top management office came in for criticism from an inspector general for cutting corners in assuring that the massive joint-service F-35 stealth fighter is equipped with ready-for-issue parts.

In a report dated June 13, the Defense Department watchdog found that parts for the department's largest acquisition—with an estimated $406 billion price tag and sales planned to foreign allies—were not being received according to the contracts and performance incentives.

The parts contracted for delivery by Lockheed Martin Corp. include wheel, seat, and window assemblies, said the audit addressed to the Defense secretary for acquisition, the Air Force secretary, the Air Force inspector general and the Defense Contract Management Agency. The federal contracting offices and the corporate teams working on the plane are supposed to ensure the sustaining parts are delivered “ready for aircraft maintenance personnel to install on the aircraft,” as well as have an Electronic Equipment Logbook assigned that spells out each part's history and remaining life.

Too often, however, the parts arrived not ready in accordance with contracts and incentive fees on the sustainment contracts because of “inflated and unverified F‑35A aircraft availability hours. This occurred because the [Joint Program Office] did not conduct adequate oversight of contractor performance related to receiving F‑35 spare parts and aircraft availability hours,” the report said, calling the inflation of hours unintentional.

As a result, the department received non-ready spare parts and spent up to $303 million in labor costs since 2015, “and it will continue to pay up to $55 million annually” for such parts until a fix is made. In addition, the Defense Department has “potentially overpaid” $10.6 million in performance incentive fees by not independently collecting and verifying aircraft availability hours.

“The lack of available [ready-for-issue] spare parts could result in the F‑35 fleet being unable to perform required operational and training missions,” the report warned.

The Joint Program Office was aware of the problem, auditors found during their review from June 2018 to April 2019, but did not resolve the issue or require the services to better track the non-compliant parts. Interviews with the Joint Program Office staff in Arlington, Va.; the DCMA administrative office in Lockheed Martin's facility in Fort Worth, Texas; and Lockheed staff at three sites found, for example, that of 74 spare parts delivered to Hill Air Force Base in Utah from Sept. 17-30, 2018, 59 spare parts (80 percent) were non-ready for issue. Of the 263 spare parts delivered to Luke Air Force Base in Arizona in June 2018, 213 spare parts (81 percent) were non‑ready. And of 132 spare parts delivered to the Marine Corps Air Station in Beaufort, S.C., in September 2017, 58 spare parts (44 percent) were non‑ready.

The IG recommended that the F-35 program executive officer improve oversight by coordinating with DCMA to pursue compensation from the contractor for the costs of mishandling the supply of spare parts since 2015. It also recommended that he direct the contracting officer to add clarifying language to future sustainment contracts, and task the lead contracting office with updating its Quality Assurance Surveillance Plan.

Navy Vice Adm. Mathias Winter, the program executive, agreed, stating that there is value added in tracking and using contractor performance data.

https://www.govexec.com/defense/2019/06/pentagon-lockheed-martin-failed-ensure-proper-parts-f-35/157822/

Sur le même sujet

  • Air Force study on future aerial refueling tanker could start in 2022

    4 février 2021 | International, Aérospatial

    Air Force study on future aerial refueling tanker could start in 2022

    By: Valerie Insinna WASHINGTON — The Air Force could begin to lay out its vision for a future aerial refueling tanker, previously known as KC-Z, as early as next year, the head of Air Mobility Command said Monday. The service intends to conduct an analysis of alternatives for an advanced aerial refueling aircraft in fiscal year 2022, AMC commander Gen. Jacqueline Van Ovost said during a Defense Writers Group meeting with reporters. That study will help the Air Force determine precisely which capabilities a future tanker will need to to operate in more heavily contested battlefields against the threats posed by nations such as Russia and China. “We're thinking about the near peer [competition], and what we need for a near peer [competition],” she said. Key to that discussion is figuring out how much of the aerial refueling process can be performed without a human pilot or boom operator onboard the plane to fly it or give other aircraft gas. “Is going to be autonomous? Is it going to be pilot on the loop [or] pilot in the loop capability?” asked Van Ovost. “Is it going to be small? Is it going to be large? What kind of [self protection] is it going to have? What kind of electromagnetic spectrum capabilities is it going to have to both protect itself and enhance the lethality of the Joint Force while it's out there?” In April, Will Roper, then the Air Force's top acquisition official, told reporters that an agreement with Boeing for a new and improved KC-46 vision system could pave the way for autonomous aerial refueling. The addition of 4K high-definition cameras, modern processors and LiDAR (light detecting and ranging) sensors would help the new system accumulate much of the data necessary for a computer to correctly calculate all the variables that need to be solved for safe aerial refueling. “All you have to do is take that data that tells the world inside the jet the reality of geometries between the airplane and the boom outside the jet. Once you have that, you simply need to translate it into algorithms that allow the tanker to tank itself,” Roper said then. The Air Force is not the only service interested in automated aerial refueling. The Navy is flight testing the MQ-25 Stingray aerial refueling drone — which, like the Air Force's new KC-46 tanker, is built by Boeing. The Navy eventually hopes to operate the MQ-25 onboard aircraft carriers, where it will be used to extend the range of fighter jets like the F-35C and F/A-18EF Super Hornet. Van Ovost acknowledged the Air Force is still years away from being able to hold a competition for the platform formerly known as KC-Z. After the Air Force completes its procurement of 179 KC-46s — which, if its current buy rate holds, will occur around the 2027 timeframe — the service will buy a non-developmental “bridge tanker,” she said. That effort, which replaces the KC-Y program, will likely be a battle between Boeing and an Airbus-Lockheed Martin team, which joined forces in 2018 to market Airbus' A330 Multi-Role Tanker Transport to the U.S. Air Force. Both teams are expected to offer upgraded versions of their current aerial refueling aircraft. Van Ovost did not say when that competition will begin. Along with tackling questions about its future tanker, the Air Force is also set to begin a business case analysis whether to pursue contracted aerial refueling to support U.S. military training and test activities across the contiguous United States. After holding a Dec. 19 industry day with interested vendors, Air Mobility Command conducted a study into the feasibility and affordability of commercial air refueling services and submitted a proposal to Air Force leadership. However, Air Force leaders want more information before making a final decision, and have asked for a comprehensive business case analysis that would finalize a requirement for all of the services' needs, Van Ovost said. The study would come up with options for various contracting models — which could include tankers that are leased to the government or contractor-owned and operated — as well as hammer out details on Federal Aviation Administration certification requirements. “We're working with headquarters Air Force to finalize the parameters for the study, and then likely will be contracting out that study,” Van Ovost said. “And for expectation's sake, it does take a while. These kinds of business case analysis we have seen take 18 months, so we are going to put pen to paper and take a very close look at it.” https://www.defensenews.com/air/2021/02/02/air-force-study-on-future-aerial-refueling-tanker-could-start-in-2022/

  • Kratos Receives $20 Million Unmanned Aerial Drone System Production Contract

    9 août 2022 | International, Aérospatial

    Kratos Receives $20 Million Unmanned Aerial Drone System Production Contract

    The unmanned aerial drone systems produced under this contract award will be manufactured in a Kratos production facility

  • QinetiQ, Inzpire and BAE Systems Deliver Next Synthetic Training Concept Demonstration to the Royal Navy

    5 septembre 2023 | International, Terrestre

    QinetiQ, Inzpire and BAE Systems Deliver Next Synthetic Training Concept Demonstration to the Royal Navy

    Delivered in late June, the complex synthetic collective training demonstration was operated from Portsdown Technology Park delivering training to three platforms docked at HM Naval Base in Portsmouth

Toutes les nouvelles