Nearly All the F-35 Jet Engines Ordered Last Year Arrived Late

By Anthony Capaccio

Nearly all the engines ordered for the next-generation F-35 jet were delivered late last year as the Pratt & Whitney unit of United Technologies Corp. struggled to solve nagging difficulties with parts and suppliers, according to the Pentagon.

About 85% of the engines for the stealthy fighter were delivered late in 2019, the Defense Department's F-35 program office reported, adding that Pratt & Whitney did manage to deliver more engines than required. The tardiness figure was in line with data from 2018, but up from 48% and 58% in 2016 and 2017, respectively.

“In general, the monthly schedule performance continues to be impacted by issues with parts and suppliers which the program office is monitoring closely,” the program office said in statement Tuesday. Pratt & Whitney “continues to perform reviews” within its expansive production chain and “has made some progress but more progress is needed to meet the monthly schedule,” it added.

Engine delivery issues are just one problem that has plagued the jet's manufacturing ahead of a key decision expected in the next year on whether to move ahead into full-rate production on the $428 billion F-35 program. The fighter has also been flagged for breaking down too often, carrying a 25mm gun that doesn't shoot accurately and having shortages in its supply chain for spare parts from tire assemblies to seats. Some of the problems have since been fixed.

Nevertheless, the jet is a key part of a broader weapons modernization effort meant to bolster not just the U.S. military but those of key allies from Poland to Japan. As the sole provider of F-35 engines, Pratt & Whitney and its subcontractors are in line to collect as much as $66 billion of the total jet contract. Congress has approved about $27 billion to date for F-35 engines. But the eventual decision on full-rate production means Pratt & Whitney needs to show it can ramp up production effectively.

Overall, 128 of 150 engines delivered last year arrived late, eight arrived on time and 14 came in ahead of schedule, according to the F-35 program office. Of 93 engines in the 11th low-rate production contract bloc, 90 arrived an average of 41 days late.

In a statement, the company emphasized that it “exceeded its annual F-35 engine delivery commitment” for 2019. “This represents a 60% year-over-year increase in deliveries. We remain laser-focused on working closely” with the program office and “our supply base to achieving on-time delivery in 2020.”

Pratt & Whitney remains under a high-level “Corrective Action Request” that the Defense Contract Management Agency issued in December 2018, citing “poor delivery performance.” The agency said it's evaluating the company's corrective actions and may rescind the CAR by month's end. The company has made improvements in four areas, including deploying “focus teams” to subcontractors for ensuring adequate “critical hardware” and qualifying additional suppliers, DCMA said.

Asked if the company was ready for accelerated full-rate engine production, the agency said “as the P&W suppliers demonstrate success in meeting their contract delivery rate the probability of P&W meeting their full-rate production level increases.

https://www.bloomberg.com/news/articles/2020-03-03/nearly-all-the-f-35-jet-engines-ordered-last-year-arrived-late

Sur le même sujet

  • Contracts

    17 décembre 2021 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

    Contracts

    Your one-stop shop for Defense Department news and information.

  • Le suédois Saab va s'impliquer dans le programme de drone MALE européen conduit par Airbus - Zone Militaire

    9 juillet 2022 | International, Aérospatial

    Le suédois Saab va s'impliquer dans le programme de drone MALE européen conduit par Airbus - Zone Militaire

    En février dernier, neuf ans après avoir été proposé par Airbus, Dassault Aviation et Leonardo, le projet de drone MALE européen, encore appelé EuroDrone,

  • Bourget 2019 : le Ministère des Armées sélectionne le drone NX70

    17 juin 2019 | International, Aérospatial

    Bourget 2019 : le Ministère des Armées sélectionne le drone NX70

    Par BOQUET Justine Le Ministère des Armées a sélectionné le micro-drone NX70 de Novadem. Novadem a annoncé le 17 juin que son drone NX70 avait été sélectionné par le Ministère des Armées pour venir équiper les soldats français déployés en opérations extérieures. Plus de 50 micro-drones auraient ainsi été commandés par la DGA, pour un montant d'un peu plus de 2 M€. « Chacun des 27 systèmes acquis est composé de deux micro-drones, d'un segment sol et du soutien technique associé », a détaillé l'entreprise aixoise. Les premiers systèmes ont d'ores et déjà été remis à la DGA et ont été évalués par la STAT (Section Technique de l'Armée de Terre). Ces drones viendront équiper les soldats de l'Armée de Terre afin de renforcer leurs moyens de détection et ainsi les doter d'outils d'observation leur permettant de mieux appréhender leur environnement tactique. « Au-delà de ses capacités de détection et de reconnaissance de jour et de nuit, le NX70 peut être doté de capacités étendues lui permettant, par exemple, d'assurer des missions d'observation de plusieurs heures gr'ce à son dispositif d'alimentation en énergie depuis le sol via un c'ble libérable en plein vol », détaille Novadem. Petit drone tactique pesant environ 1 kilo, le NX70 dispose d'une portée de 3 km et d'une autonomie de 45 minutes. Sa capacité à voler en environnement complexe lui permettra ainsi de s'adapter aux thé'tres d'opération, peu importe leurs caractéristiques météorologiques. https://www.air-cosmos.com/article/bourget-2019-le-ministre-des-armes-slectionne-le-drone-nx70-10359

Toutes les nouvelles