7 avril 2020 | International, Terrestre

How are the US Army’s modernization plans faring under a pandemic?

By: Jen Judson

WASHINGTON — The Army commands in charge of acquisition and modernization are taking it day-by-day as the COVID-19 pandemic worsens in the United States, but so far see minimal impact to production lines and modernization efforts underway.

“The Army has been very carefully looking at our industrial base and our ability to maintain programs, both for continued readiness and continued modernization, and, in general, we are still remaining fairly close to being on track,” Bruce Jette, the Army's acquisition chief, told reports in an April 3 teleconference.

“That doesn't mean that individual programs or individual issues haven't arisen, but, at this point, we have, we think, in the long run, we can resolve any of the challenges we have at hand,” he added.

Jette said he has sent letters out to contracting officers, program managers and program executive officers as well as industry providing them guidance and insight “into how we want to work together as a team, through good constructive and continuous and transparent communications, make sure that we know what's going on in each other's camp well enough that we can respond quickly.”

One major point of concern is what might happen with sub-tier suppliers to the bigger prime contractors, Jette said, so the Army is doing what it can to understand challenges that these suppliers might be experiencing if they have to shut down production to keep employees safe and healthy should cases of coronavirus crop up.

“We are still working various individual issues,” Jette said. “I track, on a daily basis, about 21 pages... on suppliers down to those lower levels.” That list provides projection for 30, 60 and 90 days, but are updated all the time.

So far, Boeing is the only major defense contractor to shut down an Army production line, according to Jette. The company reported late in the evening on April 2 that it would have to halt its H-47 Chinook production line in Ridley Park, Pennsylvania, for 10 days to better prevent the spread of the coronavirus after some employees tested positive for the virus.

Jette said he didn't believe the work stopping at the Boeing plant would affect the delivery schedule for the H-47s to the force.

All other lines are delivering on schedule including the newest version of the Bradley Infantry Fighting Vehicle — the A4 — he said.

The fielding of the Joint Light Tactical Vehicle, Jette said, will be delivered at a “lower density,” but added, “it doesn't mean we won't catch up, it just means that we're slowing down.”

Jette also said testing would likely be difficult in the coming months due to “the density packing necessary in some cases and how that puts a lot of people at risk.”

The Joint Assault Bridge that was already delayed due to other issues was supposed to go into testing, but that will have to be rescheduled, Jette said.

“It became a concern about moving the unit, moving the equipment together, getting all the testers,” he said, “and again, I go back to this issue that sometimes military operations require you to be in very close quarters for extended periods of time and that kind of violates our desire to keep people social distancing at this point.”

The 2020 calendar year is also packed with major milestones for the Army's ambitious modernization plans. And as the country's citizens continue to self-isolate, avoid travel and work from home as much as possible, it becomes hard to conduct various tests or prototyping activities to move major programs along.

“It's a changing situation, it changes pretty much daily,” Gen. Mike Murray, the Army Futures Command commander, told reporters on the same call.

"It is very much a running estimate because it does change each and every day and we're not in control of this timeline, so in many ways, we are adjusting to the timeline to try to keep everything on track as best we

The Army is having to take a “slight pause” in some activities, Murray said, such as briefly stopping some testing at Aberdeen Proving Ground, Maryland.

“It's not because of a system,” he said. “It's based upon the maintenance of the systems as you test them. ... All the vehicles we're testing have to, daily, go into the maintenance bay to be maintained and so the interaction and the proximity, we just have to work through some mitigation strategies, we should have that done very quickly.”

The Army's Interim Mobile Short-Range Air Defense System (IM-SHORAD) is one of the vehicles affected by the pause at APG. The system was undergoing automotive testing.

The Army's plan to get to a critical soldier touchpoint or evaluation of the Integrated Visual Augmentation System this summer may be interrupted, Murray said, based on how long social distancing will be needed.

“It's not Microsoft itself,” as the company is completely teleworking, but the IVAS deliveries could be affected by sub-suppliers, for example, he said.

But, according to Murray, even if the touchpoint is delayed, he said the Army would do what is possible to avoid delaying the first unit equipped and believes, at this time, that the service will stay on schedule for t he initial fielding.

The Army also has several major tests and evaluations coming up including a long-awaited Limited User Test (LUT) for its Integrated Air-and-Missile Defense Battle Command System (IBCS). A delay on the LUT would pile onto years of delays for the troubled program meant to serve as the brains of the Army's future air and missile defense system.

And the Army is planning on another flight test of Lockheed Martin's Precision Strike Munition (PrSM) later this month, which will deliver a new long-range precision fires capability to the battlefield. LRPF is the Army's number one modernization priority.

“We are working through mitigation strategies to keep both of those on track,” Murray said. “Every day we're readjusting and reevaluating whether we can physically do that or not.”

The IBCS LUT and the PrSM test involve an entire community of representatives coming together, he said, but “I'm not ready to say today that either one of those are slipping; those are closer in and we'll work them through to keep them on schedule as best we possibly can. And if the analysis proves that we can't, there's a lot of sequential things that happen in a program; we may have to look at some concurrency.”

Murray noted there are plenty of modernization programs that so far remain unaffected and likely will stay on track, such as Future Vertical Lift efforts to bring two future aircraft online in the mid 2030s, the Army's new network and initial work to restart the Optionally Manned Fighting Vehicle program to replace the Bradley.

The Army and the Navy were also able to execute a major hypersonic missile test in March.

For now, Murray said, he is focused not on alternative strategies, but how to mitigate impact to current ones.

“I'm looking as far out as this fall just to make sure that we can get ahead of it with mitigation strategies," Murray said.

https://www.defensenews.com/land/2020/04/06/can-the-army-stay-on-top-of-modernization-plans-during-covid-pandemic/

Sur le même sujet

  • BAE Systems Joins Boeing’s MQ-25 Industry Team

    17 juin 2019 | International, Aérospatial

    BAE Systems Joins Boeing’s MQ-25 Industry Team

    NASHUA, N.H.--(BUSINESS WIRE)--BAE Systems has been awarded contracts by The Boeing Company to supply the Vehicle Management Control System and Identification Friend or Foe (IFF) System for the MQ-25. “BAE Systems leads the industry in high-integrity fly-by-wire and mission-critical IFF technologies,” said Corin Beck, director of Military Aircraft Systems at BAE Systems. “Our relationship with Boeing started more than four decades ago and has resulted in aircraft that have some of the most advanced avionics and reduced size transponders in the world.” The Vehicle Management Control System will control all flight surfaces and perform overall vehicle management duties for the MQ-25 unmanned aerial vehicle. The IFF product ensures operation in contested environments by reliably identifying both coalition and enemy vehicles. The MQ-25 is the U.S. Navy's first operational carrier-based unmanned aircraft and is designed to provide a much-needed refueling capability. The contract supports Boeing's engineering and manufacturing development program to provide four MQ-25 aircraft to the U.S. Navy for Initial Operational Capability by 2024. “The MQ-25 program is vital because it will help the U.S. Navy extend the range of the carrier air wing, and Boeing and our industry team is all-in on delivering this capability,” said Dave Bujold, Boeing's MQ-25 program director. “The work we're doing is also foundational for the future of Boeing – where we're building autonomous systems from seabed to space.” BAE Systems is an industry leader in the design, development, production, and support of highly reliable flight control systems for commercial and military aircraft. It was the first to introduce fly-by-wire in both military and civil applications. BAE Systems is also a world leader in IFF equipment and this program expands its footprint to approximately 150 platforms worldwide. https://www.businesswire.com/news/home/20190617005088/en

  • Fortinet Rolls Out Critical Security Patches for FortiClientLinux Vulnerability

    11 avril 2024 | International, Terrestre

    Fortinet Rolls Out Critical Security Patches for FortiClientLinux Vulnerability

    If you use FortiClientLinux, update immediately. Critical vulnerability could let attackers run code on your system. Patch now, get the details here.

  • L'Espagne rejoint la France et l'Allemagne dans le projet d'avion de combat du futur

    18 février 2019 | International, Aérospatial

    L'Espagne rejoint la France et l'Allemagne dans le projet d'avion de combat du futur

    Frédéric Dubessy FRANCE / ESPAGNE. Le projet SCAF - pour système de combat aérien du futur - s'enrichit d'un nouveau partenaire. Après la France et l'Allemagne, l'Espagne s'associe à cette initiative comme l'a indiqué Margarita Robles, ministre espagnole de la Défense, jeudi 14 février 2019 au siège de l'Otan à Bruxelles. Une lettre d'intention a été signée le même jour entre les trois pays. Alors que l'Allemagne a pris les commandes du projet de char européen au niveau industriel, c'est la France qui se trouve à la tête de cet avion du futur avec Airbus Defence and Space, filiale d'Airbus, et Dassault Aviation. Fin avril 2018, les deux entreprises paraphaient un accord industriel. Le 31 janvier 2019, elles se voyaient attribuer le contrat de l'architecture et du concept (65 M€) alors que Safran et MTU Aero Engines développeront le moteur. Annoncé en juillet 2017, le nouvel avion de combat européen constituera la matrice d'une défense européenne en étant connecté à d'autres avions, à des satellites, des systèmes de l'OTAN et des systèmes de combat terrestres et navals. L'avion de combat du futur devrait être opérationnel "à l'horizon 2040", selon Florence Parly, ministre française de la Défense. Il viendra alors remplacer le Rafale du Français Dassault aviation et l'européen Eurofighter EF-2000 (ou Typhoon) développé par la Grande-Bretagne, l'Allemagne, l'Italie et l'Espagne (la France s'étant retirée en 1986 pour sortir le Rafale). Aucun budget n'est pour l'instant fixé, et aucun coût réparti entre les trois pays, le projet n'en étant qu'à une phase d'études. https://www.econostrum.info/L-Espagne-rejoint-la-France-et-l-Allemagne-dans-le-projet-d-avion-de-combat-du-futur_a25249.html

Toutes les nouvelles