9 juillet 2020 | Local, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

Canadian Armed Forces equipment delivered late half the time, auditor general finds

By . Published on Jul 8, 2020 10:32am

Half of all late requests for military materials and equipment arrived in Canadian soldiers' hands more than two weeks behind schedule because of a problem-ridden supply chain that often forced the military to incur extra shipment costs, a new report from the Auditor General has found.

“We concluded that National Defence often did not deliver on time the materiel the Canadian Armed Forces requested, and that it did not have the right controls in place to determine whether it avoided needless transportation costs,” said the report authored by Auditor General of Canada Karen Hogan, which was released on Wednesday.

During the period of the audit, there were approximately 1 million requests for materiel — military materials and equipment — submitted and fulfilled by National Defence. The audit oversaw all materiel covered by the National Defence Act, with the exclusion of ammunition, bombs, missiles and large equipment like aircraft, vessels and vehicles.

The Auditor General found that 50 per cent of all late materiel requests were delayed by at least 15 days and 25 per cent were at least 40 days late.

Of the highest priority requests — of which there were about 86,000 observed — 60 per cent were late. Fifty per cent of all were at least six days late, and 25 per cent were at least 20 days late.

The Auditor General found that 162,000 requests, about 16 per cent of all it tracked during its audit, were more than one year late, having been stalled at some point in the supply chain.

The goal of National Defence's supply chain is to “fulfill materiel requirements in the most economical and timely manner possible,” the Auditor General's report says. It attempts to achieve this by keeping equipment nearby where it thinks it will eventually be used.

However, most equipment bought by the military is initial delivered to Canadian Armed Forces supply depots in Edmonton and Montreal. They then supply regional warehouses, which supply smaller localized military units. Materiel is transferred at units' requests, which are made in a number of ways, but are defined as being of one of three levels of priority — high priority, essential and routine.

“We found that National Defence's systems and processes often did not ensure the timely and efficient delivery of military supplies to the Canadians Armed Forces,” Hogan's report says.

Stock shortages caused delays, National Defence poorly managed priorities and costs for transportation were bungled.

Per it's report, the Auditor General made three recommendations.

It suggested that National Defence review its materiel forecasting to ensure it sufficiently stocks items at the correct locations, that it improve its oversight of high-priority requests so that the categorization is only used when necessary, and that it provide clear guidance on how to select the proper mode of transportation for items to ensure that decisions about shipments are based on fully understanding how much it'll cost.

In a statement released shortly after the Auditor General's report, Defence Minister Harjit Sajjan said he “welcome(s)” its findings and accepts all recommendations.

Similar concerns were raised a few years ago by the Auditor General's office about National Defence's equipment supply. In the fall of 2016, it raised issues with the military's ability to properly account for its inventory. The same fiscal year, National Defence announced a 10-year inventory management plan to address the Auditor General's concerns. The Trudeau government also released its multi-decade defence policy in the spring of 2017.

One of the focal points of Strong, Secure, Engaged was to ensure the military was properly equipped.

“Providing (the women and men of the Canadian Armed Forces) the training, equipment and care they deserve is the most important objective of this policy,” reads a line from the opening paragraph of Sajjan's opening message in more than 100-page policy.

Upon being re-elected, Sajjan was again reminded of his responsibility to “ensure the Canadian Armed Forces have the capabilities and equipment required to uphold their responsibilities,” in the mandate letter assigned to him by Trudeau.

In an emailed statement to iPolitics, Conservative Defence Critic James Bezan said “effective and efficient supply chains are crucial to the operating capability of the Canadian Armed Forces.”

“Our military heroes rely on these supply chains to defend Canadians at home and abroad. It is clear that more work needs to be done in order to make these supply chains better for our men and women and uniform,” Bezan said.

“The delivery of supplies must be timely so that materiel reaches military members when they need it,” Hogan's recently released report said.

Defence Minister Harjit Sajjan said in a statement Wednesday that the Canadian Armed Forces will enhance its data analytics capabilities and “rely on real data to ensure” the military has the right supply chain approach for its ever-evolving requirements and to help better anticipate future needs.

“These steps will make sure that we have the right equipment, in the right quantities, at the right places to meet the challenges we ask our members to face now and in the future,” he said.

https://ipolitics.ca/2020/07/08/canadian-armed-forces-equipment-delivered-late-half-the-time-auditor-general-finds/

Sur le même sujet

  • Unlike Finland, Canada nixes cold-weather tests, fly-off among competing fighter jets

    15 janvier 2020 | Local, Aérospatial

    Unlike Finland, Canada nixes cold-weather tests, fly-off among competing fighter jets

    Finland, which is considering the same aircraft as Canada, for its new jet fleet, is requiring each competing aerospace company to provide two aircraft to test at low temperatures and in real world operating conditions. DAVID PUGLIESE, OTTAWA CITIZEN Updated: January 15, 2020 Canada won't conduct a fly-off between fighter jets competing to become the country's new warplane nor conduct testing to see how such aircraft perform under cold weather conditions. The decision not to proceed with such tests under Canada's $19-billion future fighter procurement program stands in contrast to Finland, which is considering the same aircraft as Canada, for its new jet fleet. Each competing aerospace company is required to provide Finland with two aircraft to test at low temperatures and be evaluated in real world operating conditions. Public Services and Procurement Canada has confirmed that Canada will not do any fly-offs among competing jet or tests for cold-weather operations like Finland has underway. “We do not have plans for an exercise of this nature,” stated department spokeswoman Stéfanie Hamel. Finland and Canada are considering the Boeing Super Hornet, Lockheed Martin F-35 and Saab Gripen. The Finnish Air Force is also testing the Dassault Rafale and the Eurofighter Typhoon, both of which pulled out of the Canadian competition because of worries the process was rigged to favour the F-35. Finland hopes to buy 64 aircraft. Canada will purchase 88 aircraft. Canadian aerospace industry representatives say the competing companies as well as allied air forces could provide Canada with results from tests they have conducted on the competing aircraft. Finland could have taken the same route but its procurement staff want to ensure the country is getting value for money since the project will cost around $14 billion. Finnish defence ministry program manager Lauri Puranen outlined in a blog post the extensive tests that will be conducted and the reasons for not relying on tests conducted by others. “The Finnish operating environment and operating methods may differ from other users' weather and lighting conditions,” Puranen stated. “Winter conditions affect the operation of the multi-function fighter and especially the performance of electro-optical systems, but possibly other active and passive systems as well.” The fighter jet candidates will be tested on the ground, in the air, and during takeoff and landing, he added. The testing of the competing aircraft is currently underway. Another series of tests involving the jets taking part in flight operations and a simulated lengthy war game will be conducted by the Finnish Air Force later this year. Finland expects to select a winner for the aircraft program in 2021. The planes, which will replace Finland's current fleet of F-18s, are expected in 2025. The Canadian government expects bids for its fighter jet program to be submitted by the end of March. A winning bidder is to be determined by early 2022. The first aircraft would be delivered to the Royal Canadian Air Force by 2025. Information about how Canada intends to evaluate the jets is limited. But Public Services and Procurement Canada has noted that technical merit will make up the bulk of the assessment at 60 per cent. Cost and economic benefits companies can provide to Canada will each be worth 20 per cent. Concerns have been raised by Lockheed Martin's rivals that the competition has been designed to favour the F-35. This newspaper reported last year the requirements for the new jets put emphasis on strategic attack and striking at ground targets during foreign missions. That criteria is seen to benefit the F-35. In addition, the federal government changed criteria on how it would assess industrial benefits after the U.S. government threatened to pull the F-35 from the competition. The Conservative government had previously selected the F-35 as the air force's new jet but backed away from that plan after concerns about the technology and growing cost. During the 2015 election campaign, Justin Trudeau vowed that his government would not purchase the F-35. But at the same time, Trudeau stated his government would hold an open competition for the fighter purchase. The Liberal government backed away from its promise to freeze out the F-35 and the aircraft is now seen as a front-runner in the competition as it has many supporters in the Royal Canadian Air Force. Many of Canada's allies plan to operate the plane. Canada is a partner in the F-35 program and has contributed funding for the aircraft's development. https://ottawacitizen.com/news/national/defence-watch/unlike-finland-canada-nixes-cold-weather-tests-fly-off-among-competing-fighter-jets

  • Superior simulation: A look inside ITPS's new aircraft simulation center - Skies Mag

    17 mars 2023 | Local, Aérospatial

    Superior simulation: A look inside ITPS's new aircraft simulation center - Skies Mag

    ITPS Canada has invested in a new Advanced Aircraft Simulation Centre that takes realistic test pilot and tactical training scenarios to a whole new level.

  • Royal Canadian Air Force to upgrade CF-18A Hornets with Raytheon AESA radars

    27 septembre 2021 | Local, Aérospatial, C4ISR

    Royal Canadian Air Force to upgrade CF-18A Hornets with Raytheon AESA radars

    The Royal Canadian Air Force (RCAF) plans to upgrade some of its ageing Boeing CF-18A Hornets with Raytheon Technologies’ APG-79(V)4 active electronically scanned array (AESA) radars.

Toutes les nouvelles