28 janvier 2021 | International, Aérospatial

Boeing’s cost overruns on KC-46 now exceed initial contract with US Air Force

By:

Edited on 1/27/21 at 1:44 p.m. to provide more details on the cost overrun.

WASHINGTON — With the Jan. 27 announcement of a new $275 million charge on the KC-46, Boeing has now paid as much in cost overruns for the troubled program as the U.S. Air Force invested in the tanker's development.

The new charge, which the company reported as part of fourth-quarter 2020 earnings, means Boeing has now paid more than $5.0 billion out of pocket to pay for the myriad technical problems and production issues that have cropped up since the company won the program in 2011. Under the firm, fixed-price contract signed then, Boeing is responsible for paying for any costs in excess of the contract's $4.9 billion ceiling.

The latest KC-46 overrun occurred “primarily due to production inefficiencies including impacts of COVID-19 disruption,” the company said.

Steve Trimble of Aviation Week put together a list of KC-46 charges by year, finding that the program documented its largest overrun in 2020 despite seeing charges decrease to only $148 million in 2019.

The company previously attributed $494 million in charges to the ongoing pandemic during the first, second and third quarters of 2020.

The KC-46 is a commercial-derivative plane based on the Boeing 767 airliner. Because it is manufactured on the 767 production line in Everett, Washington, before undergoing military-specific upgrades, any slowdown in commercial plane volume also makes it more expensive to produce the KC-46.

Boeing President and CEO Dave Calhoun said in October he believed the KC-46 had moved past the technical problems that plagued the program over the past few years, and the tanker would prove to be an asset for the company after the pandemic had run its course.

“The tanker has been a drag on us for three or four years in every way you can think of with respect to investors,” he said at the time. “But we are continuing to clear the hurdle with our customers with respect to its performance in their fleet and their need for that tanker.

“That whole relationship, I believe, will begin to transition next year, and opposed to being a drag on our franchise — which it's been — I believe it will become a strength in our franchise.”

In an message to Boeing employees on Wednesday, Calhoun pointed to some key wins in the defense and space sector, including the first flight of the MQ-25 tanker drone with an aerial refueling store, and the demonstration of the F/A-18 Super Hornet's ski jump launch capability for the Indian Navy.

Over the past month, Boeing has inked contracts with the U.S. Air Force for the sixth and seventh lots of KC-46 production, raking in $3.8 billion for an additional 27 tankers.

However, during the earnings call, Calhoun noted that analysts should not count on Boeing's defense business to generate a massive amount of near-term growth in the wake of the pandemic.

“We continue to believe that we're going to have stable growth, admittedly at the lower end of the single digits. That's the best guidance that we can talk about because we do believe there is pressure that will ultimately come down as a result of all of the COVID spending here in the United States,” he said.

“But a large part of our business now is international market, and the order activity in those international markets is pushed to the right somewhat — and almost entirely because of COVID-related stuff,” he said. “We still like our position because we have a lot of ongoing programs that the military and of course our defense [spending] bills have been kind to.”

The Air Force plans to buy 179 KC-46 aircraft over the program of record. The first KC-46 was delivered to the service in 2019.

https://www.defensenews.com/industry/2021/01/27/boeings-cost-overruns-on-kc-46-now-exceed-its-initial-contract-with-the-air-force

Sur le même sujet

  • Contract Awards by US Department of Defense - May 05, 2020

    6 mai 2020 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

    Contract Awards by US Department of Defense - May 05, 2020

    NAVY Raytheon Space and Airborne Systems, McKinney, Texas, is awarded $325,000,000 for a firm-fixed-price contract for the repair of the Advanced Targeting Forward Looking Infrared System used in support of the F/A-18 aircraft. Work will be performed in McKinney, Texas (59%); and Jacksonville, Florida (41%). Work is expected to be complete by May 2025. This is a five-year base period with no option periods. Annual working capital (Navy) funds in the amount of $54,507,477 will be obligated at time of award, and funds will not expire at the end of the current fiscal year. One company was solicited for this sole-sourced requirement under authority 10 U.S. Code 2304 (c)(1), and one offer was received. The Naval Supply Systems Command, Weapon Systems Support, Philadelphia, Pennsylvania, is the contracting activity (N00383-20-D-WC01). Flightline Electronics Inc., Victor, New York, is awarded an $18,588,079 firm-fixed-price indefinite-delivery/indefinite-quantity contract for the manufacture and delivery of 543 TTU-597/E engineering change proposal kits to address parts obsolescence and availability issues on the fuel control test set for Navy and Foreign Military Sales customers. Additionally, this contract provides logistics support documents to include technical manual updates, provisioning data and the interim support items list. Work will be performed in Victor, New York (60%); and Cheltenham, Gloucestershire, United Kingdom (40%), and is expected to be complete by May 2024. No funds will be obligated at the time of award. Funds will be obligated on individual orders as they are issued. This contract was not competitively procured pursuant to 10 U.S. Code 2304 (c)(1). The Naval Air Warfare Center, Aircraft Division, Lakehurst, New Jersey, is the contracting activity (N68335-20-D-0008). Bell Boeing Joint Project Office, Amarillo, Texas, is awarded a $10,178,059 modification (P00029) to a previously awarded, fixed-price-incentive-firm-target, cost-plus-fixed-fee contract (N00019-17-C-0015). This modification provides for additional repairs in support of the V-22 Common Configuration Readiness and Modernization program. Additionally, this modification provides non-recurring engineering for a drive tube engineering change proposal in support of V-22 (Osprey multirole combat aircraft) production. Work will be performed in Fort Worth, Texas (30%); Ridley Park, Pennsylvania (15%); Amarillo, Texas (13%); Red Oak, Texas (3%); East Aurora, New York (3%); Park City, Utah (2%); McKinney, Texas (1%); Endicott, New York (1%); various locations within the continental U.S. (28%); and various locations outside the continental U.S. (4%). Work is expected to be complete by September 2022. Fiscal 2018 aircraft procurement (Navy) funds in the amount of $4,804,019; fiscal 2019 aircraft procurement (Navy) funds in the amount of $5,119,758; fiscal 2020 operations and maintenance (Navy) funds in the amount of $240,500; and fiscal 2020 aircraft procurement (Navy) funds in the amount of $5,108 will be obligated at time of award, $5,044,519 of which will expire at the end of the current fiscal year. The Naval Air Systems Command, Patuxent River, Maryland, is the contracting activity. AIR FORCE StandardAero Inc., San Antonio, Texas, has been awarded a $237,395,588 firm-fixed-price, indefinite-delivery/indefinite-quantity contract action for the J85 engine repair. The contractor will provide maintenance, repair and overhaul repairs of the J85 engine. Work will be performed in San Antonio, Texas, and is expected to be completed by May 2028. This award is the result of a competitive acquisition in which one bid was received. Fiscal 2020 operations and maintenance funds in the amount of $10,135,844 is being obligated at the time of award. Air Force Life Cycle Management Center, Tinker Air Force Base, Oklahoma, is the contracting activity (FA8124-20-D-0005). L-3 Communications Integrated Systems, Greenville, Texas, has been awarded a not-to-exceed $76,000,028 cost-plus-fixed-fee, undefinitized contract modification (P00008) to contract FA8620-19-F-4872 for procurement of Group B materials, ground systems integration lab and subcontracts. Work will be performed in Greenville, Texas, and is expected to be completed by March 31, 2024. This contract involves 100% Foreign Military Sales and is the result of a sole-source acquisition. Foreign Military Sales funds in the amount of $37,240,021 are being obligated at the time of award. The 645th Aeronautical Systems Group, Wright-Patterson Air Force Base, Ohio, is the contracting activity. DMS Contracting Inc., Mascoutah, Illinois (FA4407-20-D-0001); C. Rallo Contracting Co. Inc., St. Louis, Missouri (FA4407-20-D-0002); Davinroy Mechanical Contractor Inc., Belleville, Illinois (FA4407-20-D-0003); Hank's Excavating & Landscaping Inc., Belleville, Illinois (FA4407-20-D-0004); J&B Builders Inc., St. Charles, Illinois (FA4407-20-D-0005); Mantle-Plocher JV, Worden, Illinois (FA4407-20-D-0006); Surmeier & Surmeier, Mascoutah, Illinois (FA4407-20-D-0007); and Pugsley Byrne JV LLC, Brighton, Illinois (FA4407-20-D-0008), have been awarded indefinite-delivery/indefinite-quantity contracts with a maximum estimated aggregate value of $45,000,000 under a multiple award task order contract. The awards are in support of the multiple award paving contract program to support the Scott Air Force Base construction program, including paving and civil categories. Work will be performed on Scott AFB, Illinois, and is expected to be completed May 4, 2021. These awards are the result of a competitive acquisition and nine offers were received. Fiscal 2020 operations and maintenance funds in the amount of $500 are being obligated to each contractor at the time of award. The 375th Contracting Squadron, Scott Air Force Base, Illinois, is the contracting activity. DEFENSE LOGISTICS AGENCY SupplyCore Inc.,* Rockford, Illinois, has been awarded a maximum $60,000,000 firm-fixed-price contract for facilities maintenance, repair and operations items. This was a sole-source acquisition using justification 10 U.S. Code 2304(c)(1), as stated in Federal Acquisition Regulation 6.302-1. This is an 18-month bridge contract with no option periods. Locations of performance are Illinois and Alaska, with a Nov. 5, 2021, performance completion date. Using military services are Army, Navy, Air Force, Marine Corps and Coast Guard. Type of appropriation is fiscal 2020 through 2022 defense working capital funds. The contracting activity is the Defense Logistics Agency Troop Support, Philadelphia, Pennsylvania (SPE8E3-20-D-0011). Raytheon Co., Andover, Massachusetts, has been awarded a maximum $36,688,190 firm-fixed-price delivery order (SPRRA2-20-F-0077) against a seven-year basic ordering agreement (SPRRA2-19-R-0046) for radio frequency exciters. This was a sole-source acquisition using justification 10 U.S. Code 2304 (c)(1), as stated in Federal Acquisition Regulation 6.302-1. This is a three-year, 11-month contract with no option periods. Location of performance is Massachusetts, with a March 31, 2024, performance completion date. Using military service is Army. Type of appropriation is fiscal 2020 through 2024 defense working capital funds. The contracting activity is Defense Logistics Agency Aviation, Redstone Arsenal, Alabama. Leading Technology Composites Inc., doing business as LTC Inc., Wichita, Kansas, has been awarded a maximum $26,752,704 modification (P00010) exercising the second one-year option period of a one-year base contract (SPE1C1-18-D-1073) with three one-year option periods for enhanced side ballistic inserts. This is a firm-fixed-price, indefinite-quantity contract. Location of performance is Kansas, with a May 4, 2021, performance completion date. Using military services are Army, Navy, Air Force, Marine Corps and Coast Guard. Type of appropriation is fiscal 2020 through 2021 defense working capital funds. The contracting activity is the Defense Logistics Agency Troop Support, Philadelphia, Pennsylvania. American Water Enterprises LLC, Camden, New Jersey, has been awarded a $21,810,972 modification (P00251) to a 50‐year contract (SP0600‐03‐C‐8268), with no option periods for the ownership, operation and maintenance of the water and wastewater utility systems at Fort Rucker, Alabama. This is a fixed-price with prospective-price-redetermination contract. Locations of performance are New Jersey and Alabama with an April 15, 2054, performance completion date. Using military service is Army. Type of appropriation is fiscal 2020 through 2054 Army operations and maintenance funds. The contracting activity is Defense Logistics Agency Energy, Fort Belvoir, Virginia. Raytheon Co., Andover, Massachusetts, has been awarded a maximum $8,362,088 firm-fixed-price delivery order (SPRRA2-20-F-0079) against a seven-year basic ordering agreement (SPRRA2-19-R-0046) for radio frequency exciters. This was a sole-source acquisition using justification 10 U.S. Code 2304 (c)(1), as stated in Federal Acquisition Regulation 6.302-1. This is a two-year, nine-month contract with no option periods. Location of performance is Massachusetts, with a Jan. 31, 2023, performance completion date. Using military service is Army. Type of appropriation is fiscal 2020 through 2023 defense working capital funds. The contracting activity is Defense Logistics Agency Aviation, Redstone Arsenal, Alabama. ARMY ASM Research LLC, Fairfax, Virginia, was awarded a $40,284,199 firm-fixed-price contract to provide comprehensive credentialing and privileging program support for the Army National Guard or Air National Guard. Bids were solicited via the internet with four received. Work locations and funding will be determined with each order, with an estimated completion date of May 4, 2025. The National Guard Bureau Operational Contracting Division, Arlington, Virginia, is the contracting activity (W9133L-20-D-1000). Miller Electric Co. Inc., Reno, Nevada, was awarded a $12,000,000 modification (P00004) to contract W911SA-17-D-2006 for sustainment, modernization and improvement projects for the 88th Army Reserve Centers throughout the states of Kansas and Nebraska. Bids were solicited via the internet with six received. Work locations and funding will be determined with each order, with an estimated completion date of May 31, 2021. The 419th Contract Support Brigade, Fort McCoy, Wisconsin, is the contracting activity. CAE USA Inc., Tampa, Florida, was awarded an $11,157,134 firm-fixed-price contract for advanced helicopter flight training support services. Bids were solicited via the internet with seven received. Work will be performed at Fort Rucker, Alabama, with an estimated completion date of May 15, 2027. Fiscal 2020 operations and maintenance, Army funds in the amount of $11,157,134 were obligated at the time of the award. U.S. Army Mission and Installation Contracting Command, Fort Eustis, Virginia, is the contracting activity (W9124G-20-C-0008). Manhattan Construction Co., Tulsa, Oklahoma, was awarded an $8,300,000 modification (PZ0001) to contract W912BV-20-C-0008 for alternate care facilities in Oklahoma. Work will be performed in Tulsa and Oklahoma City, Oklahoma, with an estimated completion date of May 10, 2020. Fiscal 2020 civil construction funds in the amount of $8,300,000 were obligated at the time of the award. U.S. Army Corps of Engineers, Tulsa, Oklahoma, is the contracting activity. DEFENSE ADVANCED RESEARCH PROJECTS AGENCY Perspecta Labs Inc., Basking Ridge, New Jersey, was awarded a $29,917,092 cost-plus-fixed-fee contract for a research project under the Fast Network Interface Cards (FastNICs) program. The FastNICs program will speed up applications such as the distributed training of machine learning classifiers by 100x through the development, implementation, integration and validation of novel, clean-slate network subsystems. Work will be performed in Basking Ridge, New Jersey, with an expected completion date of May 2024. Fiscal 2019 research, development, test and evaluation (RDT&E) funding in the amount of $1,110,000; and fiscal 2020 RDT&E funding in the amount of $2,925,000 are being obligated at time of award. This contract was a competitive acquisition under an open broad agency announcement and eight offers were received. The Defense Advanced Research Projects Agency, Arlington, Virginia, is the contracting activity (HR0011-20-C-0090). *Small business https://www.defense.gov/Newsroom/Contracts/Contract/Article/2177362/source/GovDelivery/

  • Contracts for July 20, 2021

    21 juillet 2021 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

    Contracts for July 20, 2021

    Today

  • Australia, Naval Group conclude sub negotiations

    17 décembre 2018 | International, Naval

    Australia, Naval Group conclude sub negotiations

    By: Nigel Pittaway MELBOURNE, Australia – Australian Defence Minister Christopher Pyne confirmed that the Australian government has finally concluded negotiations for the formal signing of a strategic partnering agreement for 12 large conventionally-powered attack submarines from Naval Group. Australia is acquiring the vessels under its $50 billion (U.S. $36.12 billion) Project Sea 1000 (Future Submarine) to replace its existing fleet of six Collins Submarines from the early 2030s. The subs will be the ‘Attack' class with the lead vessel named HMAS Attack. They will be fabricated in Australia to a design previously known as the Shortfin Barracuda 1A. Recent local media reports have suggested that negotiations between the parties had stalled, placing the government's timeline for the Collins replacement in jeopardy, but Pyne said on Thursday the program was still on track. “There's been a lot of ill-informed mythmaking around the negotiations but I'm very happy to say today the negotiations are complete,” Pyne said during sod-turning event at the site of the Future Submarine Construction Yard at Osborne in South Australia. “The strategic planning agreement will be signed in February next year and we can continue to get on with the submarine project, which has been under the design and mobilization contract for the last two years.” Declining to provide details of the intricacies of the agreement due to their commercial nature, Pyne said the negotiations were officially concluded at an Australian Government National Security Committee meeting in Melbourne on Dec. 10. “Suffice to say the Australian government's interests, the Australian taxpayer's interests, have been taken care of,” he said. “Naval Group Australia will deliver 12 regionally-superior submarines on time and on budget.” Australia's Chief of Navy, Vice Adm. Mark Noonan, also denied reports of an emerging capability gap between the retirement of the first Collins submarines and the Attack boats entering service, which some analysts have suggested might require a ‘Plan B' to be formulated. “I don't believe that's the case,” he told reporters. “We've got a very solid plan to ensure that there is no gap in our nation's submarine capability, and there is a very advanced plan that will see a number of our current Collins class submarines going through a life of type extension program, which will ensure that capability gap doesn't exist.” https://www.defensenews.com/global/asia-pacific/2018/12/14/australia-naval-group-conclude-sub-negotiations/

Toutes les nouvelles