Bath Shipyard Scrambles As Thousands Retire; Months Behind On Destroyer Work, Says President

“Last year we hired 1,800 people, which was the most hired for 30 years I think,” BIW President Dirk Lesko said. "We probably would have hired 500 or 600 more people last year if we could have.”

By on May 26, 2020 at 5:22 PM

WASHINGTON: A round of highly-anticipated talks between Maine's Bath Iron Works shipyard and the local labor union representing many of the company's 6,800 employees kicked off this morning, with both sides hoping to keep one of the nation's most important shipyards humming.

The labor negotiations could have a major impact on delivery of Arleigh Burke destroyers to the Navy, which BIW President Dirk Lesko told me are already running six months behind schedule even as he scrambles to hire several thousand new workers.

“Last year we hired 1,800 people, which was the most hired for 30 years I think,” Lesko said. “The challenge that we have is that, at least prior to COVID-19, the economy was very good, and there's much less of a manufacturing sector to draw people from here than in other parts of the US. We probably would have hired 500 or 600 more people last year if we could have.”

Some 1,800 new employees are being trained up to replace hundreds of older tradesmen who retired over the past several years after being hired during the last shipbuilding binge in the 1980s. Training the new group has taken time, and slowed some projects down. “Those people are leaving in groups, requiring us to replace them in big groups,” Lesko said.

The talks come after attendance rates at the shipyard dipped by more than half in the early days of the COVID-19 crisis, Workers stayed home due to local closures and the union pushed back over the use of non-union subcontractors. At one point in late March, only 41 percent of workers showed up for their shifts; by the end of April, only about 45 percent of Local S6 union members had clocked in over the previous month.

The delays in work on the destroyers came well before COVID-19 however, and stemmed from a variety of issues: the aging workforce, the time it takes to train skilled workers, and the lingering effects of the delayed work on the Navy's troubled DDG-1000 Zumwalt destroyers, which is years behind schedule and has eaten up a good portion of the limited pier space at Bath.

Lesko said the workers on the Zumwalt will turn back to their Arleigh Burke work later this year, freeing up labor and space at the pier to begin eating away at those delay times.

But the low attendance rates at the shipyard, demands for pay increases, and company's use of some non-union subcontractors for some work are major points of contention between the company and the union.

Last week, union leadership posted this on their Facebook page, “it is disheartening that, the very week our membership returns to work as normal after being encouraged to stay out and stay safe due to COVID-19 they are rewarded by subbing out their work. Claiming there were so many people out of work they are now further behind schedule.”

Those issues will begin to be hashed out this week as the two sides look to get production of the Navy's workhorse destroyers back on track. Lesko told me the schedule slippages occurred before the COVID personnel shortages, but certainly haven't made up time with so many skilled workers staying home.

The company currently has 11 Arleigh Burkes under contract with six under construction, ships that will be a critical part of the Navy's long and troubled effort to build a 355-ship fleet by the end of the decade.

“They're in a tough position going into the labor negotiations because the unions will say ‘you can't afford a strike so you'll need to pay,'” naval analyst Bryan Clark of the Hudson Institute said. But any extra costs to the company would incur could make the costs to the Navy also go up. “That could make it harder for Bath to compete” for any future destroyer work, Clark said.

The company had plans to hire another thousand workers this year before the COVID disruption, which stopped the hiring process. “We had a strong pipeline of people in our training programs in place, and our facilities were coming together in a way that I felt pretty confident about,” Lesko said. He added the company plans to get back to that as soon as possible.

While the new workers are being trained and are making their way to the waterfront, the company has dealt with a few stinging defeats.

The loss of the $795 million contract to build the first 10 of a new class of guided missile frigates for the Navy to Wisconsin-based Fincantieri Marinette Marine was a major blow to Bath, as the company looks to life after destroyer work runs out in the coming years. The company also lost out on a hard-fought effort to build the Coast Guard's Offshore Patrol Cutters in 2016.

Lesko said the company will be in the running for the possibility of a recompete for the frigate contract after the first 10 ships are built, which would put another 10 ships up for grabs. He also expressed hope in talk coming from the Navy that it might be in the market for a new class of large surface combatants in the coming years, but those plans have yet to be fleshed out.

Much of the Navy's future plans remain in limbo until Defense Secretary Mark Esper finishes his review of the Navy's force structure plans some time late this summer, which will guide the Navy's shipbuilding blueprint for the coming decades. Given the outcome of the November presidential election and knock-on effects of the ballooning federal deficit, however, those plans could change again next year as priorities, and budgets, change.

These uncertainties are deeply worrying for the Navy and the Pentagon leadership, as they can ill-afford to lose a shipyard at a time when ship construction and repair are already stressed after years of budget cuts and reduced building rates. The Navy has ambitious plans for a new class of Columbia nuclear-powered submarines, modernizing Virginia-class subs, finishing up the Ford-class aircraft carriers and starting work on the new frigate program. There is also talk of building new classes of smaller amphibious ships and supply vessels to help the Marines in their own transformation efforts. This will take multiple shipyards working on multiple projects at once.

In the near-term, there's widespread concern over how shipyards are dealing with local manufacturing shutdowns as a result of the COVID-19 crisis.

Navy acquisition chief James Geurts told reporters last week that the Navy has seen around 250 suppliers close due to the pandemic in the past two months, but he's “seeing many more of those open than close,” in recent days.

His office is tracking 10,000 companies and suppliers, and of those 250, all but 35 are open now, he said. “While we haven't seen major impacts to current work yet on most of our shipbuilding programs, we are keeping a very close eye on downstream work to make sure that [if] a part we were expecting in September doesn't show up, we understand how to adjust to that,” he said.

Lesko said that he hasn't seen much disruption at his shipyard. “There have been modest levels of disruption, a relatively small number of suppliers” that have temporarily shuttered, he said. “We've been able to work through all of that with our existing supplier base. I would not want to leave you with the impression that I don't think the supply base in some cases is fragile, but at least at this point, they have been able to support us and have done quite well.”

https://breakingdefense.com/2020/05/bath-shipyard-scrambles-as-thousands-retire-months-behind-on-destroyer-work-says-president/

Sur le même sujet

  • Salon Eurosatory 2022 : dossier spécial d’Air & Cosmos

    17 juin 2022 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

    Salon Eurosatory 2022 : dossier spécial d’Air & Cosmos

    Air & Cosmos consacre un dossier au salon Eurosatory 2022, qui s’est tenu du 13 au 16 juin à Paris. Le magazine publie notamment un article présentant les évolutions du parc d’hélicoptères de l’armée de Terre. Le standard 2 du Tigre sera évalué à l’automne 2022, tandis que le Guépard doit arriver en 2027. Le 4ème régiment d’hélicoptères des forces spéciales (RHFS) a de plus conclu un accord de coopération renforcée avec le GAMSTAT (Groupement aéromobilité de la section technique de l’armée de Terre) de Valence, qui dispose « de moyens réservés, en hélicoptères, en experts de domaines et en capacité de fabrication pour le soutien aux expérimentations ».

  • France to Launch Future Combat Air System demonstrator in 2021

    7 décembre 2020 | International, Aérospatial

    France to Launch Future Combat Air System demonstrator in 2021

    France will launch the Future Combat Air System (SCAF) demonstrator next year as part of the enhancement of the armed forces' operational capabilities. Florence Parly, Minister of the Armed Forces, made the announcement as part of the discussion of the Finance Bill (PLF) for 2021 in the French parliament on Thursday. In addition to the SCAF demonstrator, equipment deliveries include 157 Griffon and 20 Jaguar armored vehicles for the Army, a new Multi-Mission Frigate (FREMM) for the French Navy and three new aircraft-MRTT Phénix for the French Air and Space Army. The Senate adopted the bill which provides a budget hike of 4.5% compared to the 2020 budget. In 2021, the army's budget is increased to 39.2 billion euros, 1.7 billion euros more than in 2020. The main thrusts of this budget are the ramp-up of major facilities, support for the French economy and the dynamism of the regions, and an investment effort in terms of innovation, recruitment and the Family plan, Parly said. Minister Parly was quoted as saying in a MoD release, "the 2021 defense budget assignment for the third consecutive year, followed the commitments and financial trajectory of the Military Program Law (LPM) 2019-2025.” The (FCAS- French acronym SCAF) a French-German-Spanish project, received the go-ahead to commence the demonstrator phase in February this year. On February 12 the French and German governments awarded an initial framework contract to Dassault (France) and Airbus (German), besides major system partners MTU Aero Engines, Safran, MBDA, and Thales. https://www.defenseworld.net/news/28469#.X86XENhKiUk

  • US Navy officially inducts Triton UAV into service

    11 juin 2018 | International, Aérospatial

    US Navy officially inducts Triton UAV into service

    Gareth Jennings, London - Jane's Navy International The US Navy (USN) has officially commenced operations of its Northrop Grumman MQ-4C Triton Broad Area Maritime System (BAMS) unmanned aerial vehicle (UAV), it was announced on 1 June. A ceremony to formally induct the high-altitude long-endurance (HALE) UAV into service with Unmanned Patrol Squadron (VUP)-19 – the navy's first unmanned patrol squadron – was held the previous day at Naval Base Ventura County in Point Mugu, California. VP-19 now has two Triton UAVs, which are housed in specially constructed to facilities designed to accommodate their nearly 40 m wingspans. With this milestone, VP-19 will undertake training and trials ahead of the platform's inaugural overseas deployment, which will be to the Pacific island of Guam later this year. For this and later deployments, the Triton will operate in concert with the manned Boeing P-8A Poseidon maritime multimission aircraft. The MQ-4C Triton has been developed from the Block 30 RQ-4N naval variant of the RQ-4 Global Hawk HALE UAV to provide the USN with a persistent maritime intelligence, surveillance, and reconnaissance (ISR) capability in support of a full range of military operations. Designed for high-altitude, long-endurance ISR tasks, the Triton has a range of about 2,000 n miles and, with an endurance of 24 hours, will be able to cover more than 2.7 million sq miles in a single mission. Its payload primarily comprises the AN/ZPY-3 multifunction active-sensor radar. The USN has established the infrastructure to train its Triton operators at Naval Air Station (NAS) Jacksonville in Florida. Operators undergo training under the supervision of Patrol Squadron (VP) 30 at the 11,600 m2 Integrated Test Center (ITC), which is also used for the training of P-8A Poseidon and P-3 Orion crews. http://www.janes.com/article/80602/us-navy-officially-inducts-triton-uav-into-service

Toutes les nouvelles