Upgrading US Navy ships is difficult and expensive. Change is coming

By:

WASHINGTON ― The U.S. Navy is looking at extending the life of its surface ships by as much as 13 years, meaning some ships might be 53 years old when they leave the fleet.

Here's the main problem: keeping their combat systems relevant.

The Navy's front-line combatants ― cruisers and destroyers ― are incredibly expensive to upgrade, in part because one must cut open the ship and remove fixtures that were intended to be permanent when they were installed.

When the Navy put Baseline 9 on the cruiser Normandy a few years ago, which included all new consoles, displays and computer servers in addition to the software, it ran the service $188 million.

Now, the capability and function of the new Baseline 9 suite on Normandy is staggering. The cost of doing that to all the legacy cruisers and destroyers in the fleet would be equally staggering: it would cost billions.

So why is that? Why are the most advanced ships on the planet so difficult to keep relevant? And if the pace of change is picking up, how can the Navy stay relevant in the future without breaking the national piggy bank?

Capt. Mark Vandroff, the current commanding officer of the Carderock Division of the Naval Surface Warfare Center and former Arleigh Burke-class destroyer program manager, understands this issue better than most. At this week's American Society of Naval Engineers symposium, Vandroff described why its so darn hard to upgrade the old ships and how future designs will do better.

Here's what Vandroff had to say:

“Flexibility is a requirement that historically we haven't valued, and we haven't valued it for very good reasons: It wasn't important.

“When you think of a ship that was designed in the ‘70s and built in the ‘80s, we didn't realize how fast and how much technology was going to change. We could have said: ‘You know what? I'm going to have everything bolted.' Bolt down the consoles in [the combat information center], bolt in the [vertical launch system] launchers ― all of it bolted so that we could more easily pop out and remove and switch out.

“The problem was we didn't value that back then. We were told to value survivability and density because we were trying to pack maximum capability into the space that we have. That's why you have what you have with the DDG-51 today. And they are hard to modernize because we valued survivability and packing the maximum capability into the minimum space. And we achieved that because that was the requirement at the time.

“I would argue that now as we look at requirements for future ships, flexibility is a priority. You are going to have to balance it. What if I have to bolt stuff down? Well, either we are going to give up some of my survivability standards or I'm going to take up more space to have the equivalent standards with an different kind of mounting system, for example. And that is going to generate a new set of requirements ― it's going to drive design in different directions than it went before.

“I suppose you could accuse the ship designers in the 1980s of failure to foresee the future, but that's all of us. And the point is they did what they were told to do. Flexibility is what we want now, and I think you will see it drive design from this point forward because it is now something we are forced to value.”

https://www.defensenews.com/naval/2018/06/21/upgrading-us-navy-ships-is-difficult-and-expensive-change-is-coming/

On the same subject

  • Boeing begins Poseidon assembly for Norway

    April 13, 2021 | International, Naval

    Boeing begins Poseidon assembly for Norway

    Norway's procurement of five Boeing P-8A Poseidons took a major leap forward on 12 April, with the announcement by the manufacturer that assembly of the first maritime multimission aircraft (MMA) at its facilities near Seattle, Washington, h...

  • Ukrainian pilots begin F-16 training in Arizona

    October 26, 2023 | International, Aerospace, C4ISR

    Ukrainian pilots begin F-16 training in Arizona

    The F-16 fundamentals training course is expected to last several months, an Air Force spokesperson said.

  • Pentagon awards $30 million contract to boost processing of rare earth elements

    February 2, 2021 | International, Other Defence

    Pentagon awards $30 million contract to boost processing of rare earth elements

    Andrew Eversden WASHINGTON — The U.S. Defense Department awarded a $30.4 million contract to boost domestic processing of light rare earth elements as part of an effort to become less dependent on China for critical technologies, the department announced Monday, The Pentagon awarded the funds to Lynas Rare Earths Limited, the world's largest rare earth element mining and processing company outside of China. The firm will use the funds to open a processing facility in Hondo, Texas, through its U.S. subsidiary, Lynas USA. The award is part of a broader push by the department to secure its rare earth supply chain, which is threatened by China's dominance in the industry, and move more production to the United States. China is the top producer of rare earth metals, which are a critical piece of defense systems like satellites or the F-35 fighter jet. “The significance of the award is they [the Defense Department] are continuing to march forward and put the pieces of the puzzle back in place so the U.S. will have access to rare earth [elements] to meet national security needs,” said Jeffery Green, president of J.A. Green & Company, a government relations firm that works with the defense industry. If the project is successful, Lynas would be the producer of about a quarter of the world's rare earth oxides, or processed rare earth elements. Increasing domestic production of the metals is critical because they are so widespread. “You'll find these things in almost every major defense system,” Green told C4ISRNET. To counter Chinese dominance, the Pentagon in recent years took steps to bring domestic rare earth production back to the United States. According to Reuters, in April last year the department funded the construction of a Lynas heavy rare earth metals facility in Texas, which it built through a joint venture with Texas-based Blue Line Corporation. In November 2020, the Pentagon announced three Defense Production Act awards with rare earth element producers worth more than $12.5 million in total. The Defense Department's actions on rare earth elements stems from Executive Order 13817, a Trump administration document directing the government to adopt a strategy for critical minerals. “This award aligns with the U.S. government's strategy to ensure secure and reliable supplies of critical minerals under Executive Order 13817 and follows a series of rare earth element actions the Department of Defense has taken in recent years to ensure supply and strengthen defense supply chains,” the department's announcement stated. https://www.c4isrnet.com/battlefield-tech/it-networks/2021/02/01/pentagon-awards-30-million-contract-to-boost-processing-of-rare-earth-elements

All news