August 7, 2020 | International, Aerospace

UK facilities for American F-35 jets are delayed and over budget

By:

WASHINGTON — The U.S. Air Force is on track to begin permanently basing its F-35 jets abroad next year, with RAF Lakenheath in England set to become the service's first international F-35 base. But construction on new hangars and facilities necessary for supporting the high-tech stealth jet have gone over budget and over schedule, and many buildings won't be ready when the first planes arrive in November 2021.

On average, construction projects associated with the F-35 beddown at Lakenheath are about 25 percent over the initial $480 million budget estimated in 2015, said Lt. Col. Clinton Warner, who leads the 48th Fighter Wing's F-35 program integration office.

“The overall trend has been projects are late and also over budget,” he told Defense News during a July interview. “A lot of the assumptions that were made back in 2015 weren't necessarily valid. There's been cost growth that was outside of the planning assumptions that were made back in 2015.”

The cost increase is not the only problem. As RAF Lakenheath's first F-35 squadron stands up, neither the hangars planned to house the jets nor the headquarters building used for planning operations and maintenance will be ready, Warner said. A training simulator building will also be late.

Despite the delays, the Air Force still plans to move forward with the beddown of the jet. Warner said the service is exploring options to keep operations on track, such having the new F-35 squadron share space with existing units — which include three American F-15 squadrons — or potentially leasing additional facilities on base from the United Kingdom.

“In terms of getting here and flying the aircraft, we will still do that. [There is] really no difference in terms of the capability is going to be delivered, but it'll just look different in how we do it,” Warner said. “It will be some strain on the units here at the base, as there's more crowding and with waiting for those facilities to come online.”

The arrival of U.S. Air Force F-35s in Europe has been a long-awaited milestone for the service, which announced in 2015 that RAF Lakenheath would become the first international location to get the jets. Since then, F-35s temporarily deployed to the base in 2017.

“Having a fighter with the capability of the F-35s one hop closer to a part of the world that's seemingly less stable certainly will have a deterrent effect,” said Frank Gorenc, a retired four-star general who commanded U.S. Air Forces in Europe from 2013 to 2016.

“Being able to daily train with the partners that have F-35s will have a deterrent effect,” Gorenc told Defense News. “It will cause interoperability to soar both on the maintenance side and on the operations side. I think the benefits of having that equipment — the demonstration of having a fifth-generation [fighter jet] in theater combined with F-15Es and F-16s — I think is the right signal.”

Under the current plans, F-35 pilots and maintainers will begin to arrive at RAF Lakenheath in June 2021, with the first aircraft to follow in November. The base will eventually be home to two F-35 squadrons, each with a total of 24 jets.

That beddown will follow more than five years of planning and development on the part of the Air Force, which stood up a team in 2015 to get the base ready for the incoming jets.

In 2018, the U.S. Air Force chose Kier-Volker Fitzpatrick, a joint venture of U.K.-based design and construction firms Kier Group and VolkerFitzpatrick, to build and renovate all installations associated with the F-35 presence at RAF Lakenheath. Construction began in July 2019, with seven of 14 new facilities — which will include new hangars, a building for flight simulation, a maintenance unit and storage facilities — currently either being built or already complete.

As unforeseen costs have mounted, the base's program integration office has had to request $90 million in additional funding from Congress, as well as permission from the Pentagon to revise the scope of the projects, Warner said.

But there's no overarching answer for why costs have ballooned.

“Each individual project had a different set of assumptions, a different set of risk profiles, and some were correct and some are not correct,” Warner said.

With only a few years between the decision to base F-35s at Lakenheath in 2015 and the original planned start of operations in 2020, the U.S. government wanted to put a construction firm under contract sooner rather than later, said Stephen King of the Defence Infrastructure Organisation, a U.K. government agency charged with overseeing the building and maintenance of military facilities.

But workforce costs grew as the project was discovered to be more complex than originally anticipated.

“When the workers are tendered, the prices that are coming back in are found to be different from those originally estimated, and it seems to be the price of doing business on a military establishment. There seems to be an ‘add-on' to the outside market,” King said.

Because the F-35 is a stealth jet that processes large amounts of classified information, many of the installations linked with its operations must meet certain security specifications. Building those structures to both U.S. and U.K. standards while using a foreign workforce of U.K. citizens posed challenges that the U.S. Air Force did not foresee during the design process, Warner said.

“Luckily most of these problems are behind us, but they did cause delays in terms of when we were programming out in the schedule and looking at what we thought it would look like,” he said. “Some of the challenges associated with building those secure facilities were not fully understood.”

Air Force officials have said keeping the projects on track was always going to be a challenge. In 2016, Col. Robert Novotny, who was then the commander of the base's 48th Fighter Wing, predicted construction projects could face troubles getting funding or finding a skilled workforce to build the new facilities, and that F-35s likely wouldn't begin to arrive on base until at least 2021 or 2022.

“For me, the concern I have when I look at Lakenheath is not the F-35,” he told Defense News in July 2016. “For me, the concern I have is: Are we going to be able to build enough stuff fast enough?”

https://www.defensenews.com/smr/nato-air-power/2020/08/06/uk-facilities-for-american-f-35-jets-are-delayed-and-over-budget/

On the same subject

  • Pentagon, Industry Struggle To Chart Impacts Of COVID On Arsenal

    April 22, 2020 | International, Naval

    Pentagon, Industry Struggle To Chart Impacts Of COVID On Arsenal

    "I think a three month slow-down in program activity is an optimistic projection based on the level of damage the economy is currently sustaining." By PAUL MCLEARYon April 21, 2020 at 3:33 PM WASHINGTON: Defense industry and Pentagon leaders are struggling to assess what impact the COVID-19 pandemic will have on building and maintaining the global US arsenal, but early assessments agree there'll be some disruption and delay as the global economy teeters. How much, how long, and where those disruptions will occur are something of an open question. With massive supply chains across the globe that run from small mom and pop manufacturing shops to massive global conglomerates, there's no one formula to assess what will happen to the industrial base in the weeks and months to come. On Monday, Pentagon acquisition chief Ellen Lord said she expects the largest programs to see three-month delays, but some analysts say that assessment could be too rosy. “I think a three month slow-down in program activity is an optimistic projection based on the level of damage the economy is currently sustaining,” said Andrew Hunter, former chief of staff to two heads of Pentagon acquisition. Hunter is now at the Center for Strategic and International Studies. The designation of the defense industry as critical infrastructure has ensured that shipyards, factories, and shops have generally remained open, as workers stagger shifts and companies provide liberal leave and teleworking where possible. That has placed the defense industry in a good position relative to other parts of the economy. But the supply chain those companies rely on “is tightly interlinked with the commercial economy, especially the aviation and automotive sectors, and this will transmit a degree of economic disruption into defense in the coming months,” Hunter said. Lord singled out the aerospace sector, along with shipyards and space launch as areas most at risk of slowdown and disruption. So far, though, the Navy and its largest shipbuilder say they're mostly working through the issues, and are staying away from putting a specific length of time on any delays. “We do not have a list of programs that are delayed, but as Ms. Lord and [Navy acquisition head James] Guerts have both said, while it's too soon to identify specific delays, generally we are expecting and planning for program disruptions,” Navy spokesman Capt. Danny Hernandez told me in an email. Geurts has moved to accelerate funding for some work and parts supplies so industry can eventually ramp up once the entire workforce is back on the job. Speaking to reporters last week, Geurts said over the “next three four weeks we'll get a better view of the exact delay and disruption and then how we might mitigate that, or quite frankly, where do we have opportunities where we can accelerate things” due to some excess capacity in the supply base because it's not being consumed by commercial aviation or shipbuilding. At the country's largest shipbuilder, Huntington Ingalls, company executives told me recently they're not seeing significant reductions in the number of parts they're receiving. “We are working with a few critical suppliers that are having challenges, but I think for the most part are going to be able to get through that,” said Lucas Hicks, vice president of new construction aircraft carrier programs. “We have reached out to all the suppliers and are working with them to try to help them.” There will be some pain, though how much is up for debate. Analyst Byron Callan of Capital Alpha Partners said in a note Monday that a three-month impact might not force companies to drastically change their expectations for the whole year. Any slippages this spring “could conceivably be made up in subsequent months, but that may be a challenge. Contractors could sustain prior guidance and just call out COVID-19 as a risk for the full year, or drop guidance altogether. No one has a perfect crystal ball.” Hawk Carlisle, president of the National Defense Industrial Association, said on a Monday conference call organized by the Jewish Institute for National Security of America that the slowdown in the global economy “is going to cause things to cost more, whether it's service agreements or products and manufacturing capability.” He's looking to the next congressional stimulus package for an acknowledgment “that these programs are going to exceed budget,” he added, “because of this two to three months of delays, partial workforce, paying the workforce, inability to perform on contract.” But Hunter thinks, so far, the Pentagon has handled the situation as well as can be expected: “To the department's credit, they have been aggressively looking for issues in the supply chain, which means that Ms. Lord's estimate becomes a lot more likely if they succeed in staying ahead of these problems.” https://breakingdefense.com/2020/04/pentagon-industry-struggle-to-chart-impacts-of-covid-on-arsenal

  • US drive to make green jet fuel with ethanol stalled by CO2 pipeline foes | Reuters

    November 14, 2023 | International, Aerospace

    US drive to make green jet fuel with ethanol stalled by CO2 pipeline foes | Reuters

    The U.S. drive to develop sustainable aviation fuel (SAF) using ethanol could be slowed because of growing opposition to proposed pipelines that would curb greenhouse gas emissions from ethanol plants by capturing carbon dioxide and carrying it away to other states for storage.

  • Boeing assembles team to bid for next-gen missile defense interceptor

    September 25, 2020 | International, C4ISR, Security

    Boeing assembles team to bid for next-gen missile defense interceptor

    Jen Judson WASHINGTON ― Boeing has assembled a team with General Atomics Electromagnetic Systems and Aerojet Rocketdyne to bid to build the Missile Defense Agency's Next Generation Interceptor (NGI). The agency decided last year to scrap its plans to redesign the kill vehicle of its current Ground-Based Interceptors (GBI) that is part of the Ground-Based Midcourse Defense (GMD) system designed to defend the homeland against possible intercontinental ballistic missiles from North Korea and Iran. The MDA is holding a competition instead to design a brand new interceptor for the GMD system. The company has an extensive history with the GMD system in place at Fort Greely, Alaska, and Vandenberg Air Force Base, California, having held the development and sustainment contract for years. That contract is set to expire in 2023 and MDA is weighing options to break up that contract to foster competition that promotes increased capability. “The Boeing-led team will deliver critical technology to enhance our homeland missile defense,” Norm Tew, Boeing Missile and Weapon Systems vice president, said in a Sept. 24 statement. “Combined, we bring decades of expertise in proven missile and weapon systems.” An NGI “requires a new way of thinking supported by a proven ability to deliver pioneering solutions,” Scott Forney, president of GA-EMS, said in a separate company statement issued Sept. 24. “We are excited to partner with Boeing to deliver the disruptive technologies needed to help MDA rapidly deploy an interceptor system that bolsters the nation's missile defense network and ensures that the U.S., our allies, and partner nations maintain military overmatch against ever evolving threats from adversaries.” Aerojet Rocketdyne will supply the propulsion system. “As the country's premier hit-to-kill propulsion provider, we're able to deliver low-cost, high-performance systems by leveraging our skilled workforce and strategic investments in innovative technology and materials,” Eileen Drake, Aerojet Rocketdyne CEO, said in the Boeing statement. Boeing reports the team submitted its NGI offering to MDA on Aug. 12. Also according to the statement, Northrop Grumman will serve as a “component supplier” on the Boeing team. Northrop is also teaming up separately with Raytheon to compete against the Boeing team and Lockheed Martin. Raytheon was the developer of the now-canceled RKV. MDA aims to downselect to two companies later this year, who will then compete for the right to build the interceptor. Proposals were due July 31, but MDA noted in its request for proposals that there may be some give in that schedule due to the ongoing COVID-19 coronavirus pandemic. The agency requested $664.1 million in fiscal year 2021 for the NGI program, as part of a $4.9 billion five-year budget plan. https://www.defensenews.com/2020/09/24/boeing-assembles-team-to-bid-for-next-gen-missile-defense-interceptor/

All news