Back to news

January 19, 2021 | International, Aerospace

Key Upgrades Mark 2021 As Turnaround Year For KC-46A

Guy Norris

As progress accelerates on a key visual system redesign, a wing refueling pod certification and the hopes for more international sales, Boeing believes its troubled KC-46A tanker program has finally turned a corner.

Marking a shift away from more than three years of delays, challenges and frustration for the U.S. Air Force, the program's brighter outlook builds on two agreements announced between Boeing and the service last April. The first covered the redesign and retrofit of a fully compliant boom operator remote vision system (RVS), at no cost to the government, while the second released $882 million of withheld payments to Boeing for previous noncompliance in 33 KC-46A deliveries.

“That was a real turning point, and it's been extremely collaborative since then,” says Boeing KC-46A Vice President and General Manager Jamie Burgess. “That's really been cultivated by the agreement that we reached on the new RVS system,” he says, acknowledging the change to the relationship with the Air Force. “For a while, we were at a bit of an impasse in terms of what needed to be done to address the Air Force's concerns. There's a lot of hard work left to go, but it's been a really long relationship now,” he adds.

Boeing is working on a two-phase approach to correct the well-documented RVS deficiencies that were revealed during flight tests. These defects mostly center on the oversensitivity of the aft-looking camera system to direct sunlight, which led to image issues in the hybrid 2D-3D video feed to the boom operator. “The first phase is really just intended to address that distortion piece of it, and that's primarily a software change that's being implemented now,” Burgess says. The fix, dubbed the enhanced RVS, “digitally addresses the distortion around the edges of the picture,” he adds.

The fix will also make viewing the system “more comfortable for the operator when looking through the 3D glasses,” says Sean Martin, KC-46A global sales and marketing leader, referring to the stereoscopic eyewear required for the system. “It makes the image more like what they are used to seeing in real life.”

The second phase, and the subject of the Air Force agreement, is RVS 2.0. Described by Burgess as “a full technological refresh of the system,” the revised package will include new cameras, new displays, a light-detection and ranging (lidar) system and all new supporting computing infrastructure. The redesigned aerial-refueling operator station will feature much larger 40-in. displays compared with the current 24-in. screens, giving the position “much more of a kind of home theater feel to it,” Burgess says. The image will remain in 3D but will be presented in color and 4K resolution. The Air Force has also opted for a collimated mirror projection method over an LCD option, “so we are working with them to mature that design,” the manufacturer adds.

In collaboration with the Air Force, Boeing completed the RVS 2.0 system readiness review in December and remains on track to hold the preliminary design review in the second quarter. The system is due to be fielded around late 2023 or early 2024.

The redesign will also be provisioned for semi-autonomous or autonomous aerial refueling (AAR), satisfying a long-term capability vision of both the Air Force and Boeing. “The computing-system upgrade will be able to handle the processing for future automation,” Burgess says. “In parallel, we're working toward developing all of the computing algorithms that will be required to track the receiver [aircraft] using machine-learning-type software. We will feed that into our boom control laws, so that it can go find the receptacle on that receiver,” he adds, referring to the KC-46A's fly-by-wire controlled boom.

The algorithm development work builds on the company's long-running collaboration with the Air Force Research Laboratory on autonomous refueling as well as other related efforts, such as the unmanned MQ-25 tanker for the U.S. Navy. “We have a lab now where we're developing those algorithms that we can move into KC-46 when the Air Force has a requirement for it,” Martin says. “We want to bring the capability to them, but we haven't received a requirement from them that says they need that. But we're working on it, and we're committed to it.”

Boeing says the end is also in sight for another issue that has overshadowed the tanker development: the long-delayed certification of the Cobham-developed wing air-refueling pods (WARP). The wing-mounted pods, along with a centerline station, form part of the tanker's hose-and-drogue system, which can deliver up to 400 gal. of fuel per minute, compared with 1,200 gal. per minute for the boom.

All KC-46As are provisioned at delivery to carry the pods, but in line with Boeing's initial decision to pursue both military and civil certification for the tanker and its systems, the aircraft cannot be operationally equipped with the system until the FAA approves the WARPs. The pods performed well during flight testing, but “the FAA has required a tremendous amount of testing in order to certify them,” Burgess says. “Similar pods have flown for years on other military aircraft, but they have never been FAA-certified.”

Although Cobham seriously underestimated how much work would be required for FAA certification, Burgess says: “We're at the very end of that testing and are just about done.” FAA approval is expected for the pod by the end of the first quarter. Previously, all certification work related to pods was concerned with ensuring that carriage of such systems was safe and would not affect the control and safe landing of the aircraft. “Now we had to look at certifying it to operate, so all the components—such as the ram air turbine on the front of the pod—had to be cleared for safe use,” Martin adds. “That's been the challenge for them, and they've done a great job stepping up to it.”

Another ongoing area of modification is revising a valve for the boom actuation system to correct a refueling issue specific to the Fairchild Republic A-10 attack aircraft. “The boom flies down and telescopes out to connect with the receiver aircraft, which pushes the boom up into a nominal refueling position,” Burgess says. At altitude, the A-10 with wing stores was only able to generate a force of about 650-lb. thrust resistance compared with the international standard of 1,400 lb. to which the boom was designed.

“We're changing the actuation system to make it just require less force to push it up,” Burgess says. “That's currently going through the critical design review with the Air Force.” He adds that the first qualification units are now being assembled. “We're also building up for a big full-scale lab test, and so that's well underway.”

Boeing is also preparing to design, develop and test a secure communications system, dubbed the Pegasus Combat Capability Block 1 upgrade, and expects to receive a contract for the enhancement package this year. The Air Force is studying which elements to include in the upgrade, and that puts the KC-46A on a path to play a potentially wider role as a battlespace communications node. But Boeing adds that a wing-mounted, podded, radio-frequency countermeasures system is not currently in the Block 1 suite.

With 42 tankers delivered by the end of 2020 and the firm orderbook bolstered by a $1.6 billion contract for the sixth production lot covering an additional 12 aircraft, Boeing is focused on maintaining a smooth assembly flow despite the disruption from the COVID-19 pandemic. The process includes rigorous new quality controls introduced after a series of discoveries of foreign object contamination caused the Air Force to temporarily suspend accepting the aircraft in April 2019.

“It's no secret that we realized that we had an issue as far as foreign object debris [FOD] on airplanes,” Burgess says. “We stopped the production line, and we stopped deliveries for a while and put in place a number of controls. There's a whole lot of work that goes on in the factory around what we call ‘clean as you go.' At the end of the shift, there is a cleanup to make sure that the airplanes that roll out of the factory are perfectly clean.”

The decontamination focus continues when airframes are rolled from the factory into the nearby Everett Modification Center, where all the military equipment is installed. “We do a complete FOD sweep of the airplane when it enters and again when it leaves to go to the delivery center,” Burgess says. “The aircraft delivering today are very clean. It's been a big cultural shift for the program.”

Production is currently split roughly evenly between commercial 767-300F freighters and KC-46A variants—a divide that sustains the line at about three airframes per month. With the latest order, confirmed on Jan. 12, Boeing is now on contract for 79 tankers out of an intended total of 179. The firm orderbook is expected to grow again to 94 when the Air Force awards the next contract for a further 15 aircraft under production Lot 7, which legislators approved in December.

Although program delays held up initial deliveries to the Air Force until January 2019, Burgess says the subsequent flow of operational aircraft to four bases marks an unprecedented pace for any recent modern weapons system. “I'm not aware of any other major military program that's done this,” he adds. “We delivered 28 in 2019. We'll do 14 this year.”

Boeing maintains the flexibility to introduce slots into the production skyline for international sales, the first of which is to Japan. The aircraft, the first of four that the Japan Self-Defense Force has ordered, is due to make its first flight sometime this quarter. The U.S. Congress has also approved the sale of eight aircraft to Israel, and Boeing is pursuing other prospects in Southwest Asia and the Middle East, particularly in Qatar.

https://aviationweek.com/defense-space/aircraft-propulsion/key-upgrades-mark-2021-turnaround-year-kc-46a

On the same subject

  • With a new setup, the Air Force hopes to improve information warfare operations

    July 21, 2020 | International, Aerospace, C4ISR

    With a new setup, the Air Force hopes to improve information warfare operations

    Mark Pomerleau The Air Force is realigning the cyber mission force teams it provides to U.S. Cyber Command as a way to have intelligence personnel work more closely with cyber operators. In the past, Air Forces Cyber was made up of cyber and intelligence personnel from 24th Air Force and 25th Air Force, respectively. However, the arrangement created difficulties with command relationships and oversight of teams since the intelligence operators served beneath a separate Air Force command with a separate commander. But in October, the Air Force decided to merge 24th and 25th Air Force into 16th Air Force/Air Forces Cyber, placing cyber, intelligence, surveillance and reconnaissance, electronic warfare and weather capabilities under one commander, and creating the Air Force's first information warfare entity. The new organization also serves as the Air Force's component to Cyber Command. The new organization of teams moves intelligence forces from the 70th Intelligence, Surveillance and Reconnaissance Wing to the 67th Cyber Operations Wing. “We looked at the intelligence squadron and focused on the position descriptions that really were supporting the cyber mission force ... so that we can merge those intelligence professionals into the cyber operations squadron in order to build the mission elements that supported the combatant command requirements,” Col. Lauren Courchaine, commander of the 67th Cyberspace Operations Group, told C4ISRNET in an interview. Specifically, these teams are combat mission teams – the teams that conduct cyber operations on behalf of combatant commands mostly in the offensive sphere – and cyber support teams, which provide intelligence, mission planning and other necessary support work for combat mission team. Officials at the creation of 16th Air Force said the integration would allow the service to provide more robust teams to Cyber Command. This new structure - with cyber operators, developers and intelligence forces in the same room and read in on the same missions - provides a tighter mission thread, Courchaine said. In the past, she said, when cyber operators needed intelligence support, they'd have to ask their intelligence teammates who weren't always privy to the mission or technical context, which created gaps. “Now when you have those conversations with intelligence airmen, operators and developers all in the same forum, sometimes in the same room with the same whiteboard, you come to integrated solutions up front in early vice having to work through a process where that one piece of information, potentially out of context, is levied on the intelligence requirement to somebody that you don't know in another place ... to try to understand truly what the intelligence piece that you're looking for,” Courchaine, said. “When you fuse all of them together, I think the output is significantly better and drives that operationally speed, the agility and flexibility that [16th Air Force commander] Gen. [Timothy] Haugh is looking after.” The final realignment package is still at the Air Staff awaiting final approval with details regarding new units still to be determined, to include a new group activated under the 67th Cyberspace Wing and three new squadrons. Gaining insights from joint operations The team realignment also extends to Air Force cyber teams that serve under commanders of other services under different Joint Force Headquarters-Cybers. The way cyber operations are structured within DoD is individual services do not have their own offensive teams. Instead, these teams work through several organizations, each formally known as Joint Force Headquarters-Cyber that exist beneath Cyber Command, which in turn provide planning, targeting, intelligence and cyber capabilities to the combatant commands to which they're assigned. The heads of the four service cyber components also lead their respective JFHQ-C. These organizations oversee combat mission teams and combat support teams. Courchaine said the Air Force teams, those that conduct operations in Central Command under Joint Force Headquarters-Cyber and operations focused on China under Joint Force Headquarters-Cyber Fleet Cyber, can bring a global perspective a back to the service. These teams conduct operations on behalf of European Command, Strategic Command, Transportation Command and Space Command. In some theaters, with the high tempo of operations, such as Central Command, the approach allows the teams conducting operations to bring back lessons learned to their respective services. “You can see how these three areas will really converge and enable Gen. Haugh from a 16th Air Force perspective to not just be successful in aligning the forces appropriately but driving that return on investment where we're able to converge target sets globally ... to drive operations so that we can influence our adversaries in support of national security objectives,” she said. https://www.c4isrnet.com/cyber/2020/07/19/with-a-new-setup-the-air-force-hopes-to-improve-information-warfare-operations/

  • Taiwan moves closer to acquiring 160 Turkish-made Jackal drones

    September 24, 2023 | International, Aerospace, C4ISR

    Taiwan moves closer to acquiring 160 Turkish-made Jackal drones

    The Jackal has the potential to conduct airstrikes, provide air support, attack helicopters in flight and more.

  • Lockheed Martin receives $2.3B deal for helicopter parts maintenance

    February 3, 2020 | International, Aerospace

    Lockheed Martin receives $2.3B deal for helicopter parts maintenance

    ByChristen McCurdy Jan. 31 (UPI) -- Lockheed Martin has received a $2.3 billion contract for parts maintenance for MH-60R and MH-60S helicopters for the U.S. Navy, the Department of Defense announced. The MH-60R -- also called the 'Romeo' aircraft -- has been operational since 2006. The helicopters are jointly built by Lockheed and Sikorsky Aircraft Corp. According to Lockheed, MH-60R replaces the SH-60B Bravo and SH-60F Foxtrot, and is equipped for combat duty as well as high-risk rescues. Itcan fly at speeds of up to 180 knots while carrying extra fuel tanks or torpedoes and Hellfire missiles. The MH-60S, also called the Knighthawk, replaced the CH-46 Sea Knight helicopters in 2001 and is used seek out and destroy naval mines from the air. Both models have a digital cockpit with four flat-panel color display screens that provide the crew access to advanced surveillance and information on weather conditions. The contract funds approximately 1,049 weapon replaceable assemblies and shop replaceable assemblies associated with both helicopter models. Forty-eight percent of work on the contract will be performed at various contractor supplier locations throughout the U.S., with 38 percent of work taking place in Stratford, Conn., and Owego, N.Y. Work should be completed by January 2025, but the contract does include an option that would extend the work through January 2027. https://www.upi.com/Defense-News/2020/01/31/Lockheed-Martin-receives-23B-deal-for-helicopter-parts-maintenance/3901580519254/

All news