If the US Navy isn’t careful, its new unmanned tanker drone could face a 3-year delay

By:

WASHINGTON — The US Navy could face a three-year delay in testing of the MQ-25 Stingray carrier-based tanking drone if it doesn't get its designated test ships through the required modernizations on time, a possibility the Navy said was remote.

Two carriers — Carl Vinson and George H.W. Bush — have limited windows to complete the installation of unmanned aircraft control stations, and if operational commitments intervene it could create significant issues for the program, according to Navy officials and a government watchdog report.

“Program officials stated that, among other things, the Navy's potential inability to maintain its schedule commitments could require modifications to the contract that would impact the fixed-price terms,” the Government Accountability Office reported. “Specifically, the Navy faces limited flexibility to install MQ-25 control centers on aircraft carriers.

“If the Navy misses any of its planned installation windows, the program would have to extend MQ-25 development testing by up to 3 years. According to officials, such a delay could necessitate a delay to initial capability and result in a cost increase.”

Navy officials say a three-year delay is “extremely unlikely,” however the Navy has struggled in recent years to balance its modernization schedules with operational commitments, a problem that its “Optimized Fleet Response Plan” deployment rotation scheme was supposed to address. Ultimately, a delay would further push back the Navy's ability to extend its carrier air wing's range through unmanned tanking, critical to keeping the service's powerful strike arm relevant against long-range guided munitions.

The Navy believes it can avoid a schedule delay and is working toward keeping the program on track, said Jamie Cosgrove, a spokesperson for Naval Air Systems Command.

“The Navy is still planning to achieve [initial operating capability] in 2024,” Cosgrove said. “A three-year extension of development testing and a delay to IOC is extremely unlikely and represents improbable scenarios where both aircraft carriers currently designated to support MQ-25 testing are unavailable due to operational requirements, or the program misses the planned periods to install the MQ-25 test equipment on those two carriers.

“Should either of these unlikely scenarios occur, the program will reevaluate the schedule and determine how to best mitigate schedule impacts to deliver the mission-critical MQ-25 to the Fleet ASAP.”

Unmanned control

The specific alternations needed to operate the MQ-25 Stingray include special control and network equipment, Cosgrove said.

The program of record is the Unmanned Carrier Aviation Mission Control System and installing it will include setting up a control room known as the Unmanned Aviation Warfare Center on the ship. The equipment in the UAWC will include control stations, network interfaces and routing equipment, commanding and control equipment and network infrastructure, Consgrove said.

The Navy awarded Boeing an $805 million contract to build the first four MQ-25 aircraft, with options for three additional aircraft. In April, the Navy announced it had exercised the option to the tune of $84.7 million, bringing the total number of Stingrays under contract to 7.

Ultimately the Navy plans to buy 69 additional aircraft as part of the its full production run, according to the GAO report.

The Navy's former air boss Vice Adm. Mike Shoemaker told USNI Proceedings in a 2017 interview that the MQ-25 would extend the carrier air wing's range by up to 400 miles.

Juggling maintenance

The Navy has struggled to maintain its carrier schedules in recent years as the problems have arisen with carriers during their availabilities. For example, last year, the carrier Abraham Lincoln was extended on its deployment because its relief, the carrier Harry S Truman, was stuck in maintenance to repair unforeseen issues.

That can throw a monkey wrench into the Navy's overstretched deployment rotation scheme, meaning that other carriers have their deployments extended while still others have their maintenance availabilities truncated to play catch up. But that can lead to even more problems down the road with differed maintenance and worn-out equipment that ultimately adds up to a significant readiness hole that is tough to dig out from.

All of this is exacerbated by crushing demands from Combatant Commanders for Navy forces overseas, which ultimately is driving the vicious cycle.

That means the Navy will have to manage the risk of impacting the Vinson and Bush's upcoming maintenance availabilities to not set back the MQ-25 development cycle.

https://www.defensenews.com/naval/2020/06/10/if-the-us-navy-isnt-careful-its-new-unmanned-tanker-drone-could-face-a-3-year-delay/

On the same subject

  • CACI Awarded $83 Million Task Order to Support Portsmouth Naval Shipyard

    April 16, 2020 | International, Naval

    CACI Awarded $83 Million Task Order to Support Portsmouth Naval Shipyard

    April 14, 2020 - CACI International Inc (NYSE: CACI) announced today that it has been awarded a single-award task order for one base-year and four option-years, with a ceiling value of more than $83 million, by the U.S. Navy to provide engineering, technical, and planning expertise to the Portsmouth Naval Shipyard in Kittery, Maine. Under the task order, which the Navy awarded under its SeaPort-NxG contract vehicle, CACI engineers and technicians will provide expanded mission expertise, including planning maintenance and repair for submarines by assisting the Ships Availability Planning and Engineering Center (SHAPEC) and Deep Submergence Systems Program (DSSP). The task order is CACI's first award under the SeaPort-NxG vehicle. CACI technical expertise across submarine engineering disciplines, such as structural, mechanical, electrical, and combat systems, will help the Navy to safely return submarines to the fleet as quickly as possible. For example, CACI has developed the Shipyard Planning Engineering Automated Reports (SPEAR), the software tool SHAPEC uses to more effectively conduct its planning. John Mengucci, CACI President and Chief Executive Officer, said, “CACI engineers and technicians help Navy shipyards overcome hurdles in their maintenance and repair efforts with expertise earned through long-standing support of the mission. CACI stands ready to support the Navy shipyards in any way they may need, including by providing acquisition and engineering support.” CACI Executive Chairman and Chairman of the Board Dr. J.P. (Jack) London, said, “CACI is proud to play a critical role in helping the Navy maintain its submarine fleet and continue to project power around the world.” CACI's 23,000 talented employees are vigilant in providing the unique expertise and distinctive technology that address our customers' greatest enterprise and mission challenges. Our culture of good character, innovation, and excellence drives our success and earns us recognition as a Fortune World's Most Admired Company. As a member of the Fortune 1000 Largest Companies, the Russell 1000 Index, and the S&P MidCap 400 Index, we consistently deliver strong shareholder value. Visit us at www.caci.com. There are statements made herein which do not address historical facts, and therefore could be interpreted to be forward-looking statements as that term is defined in the Private Securities Litigation Reform Act of 1995. Such statements are subject to factors that could cause actual results to differ materially from anticipated results. The factors that could cause actual results to differ materially from those anticipated include, but are not limited to, the risk factors set forth in CACI's Annual Report on Form 10-K for the fiscal year ended June 30, 2019, and other such filings that CACI makes with the Securities and Exchange Commission from time to time. Any forward-looking statements should not be unduly relied upon and only speak as of the date hereof. CACI-Contract Award View source version on businesswire.com: https://www.businesswire.com/news/home/20200414005058/en/

  • The next few months are ‘critical’ for the Army’s new helicopter engine

    June 11, 2020 | International, Land

    The next few months are ‘critical’ for the Army’s new helicopter engine

    By: Aaron Mehta WASHINGTON — The Army's Improved Turbine Engine Program is facing a “critical” stretch which will determine whether testing on the engine will occur on time or be delayed, thanks to challenges related to the COVID-19 pandemic, a pair of Army officials said Wednesday. Patrick Mason, the program executive officer for Army aviation, and Brig. Gen. Walter Rugen, the director for future vertical lift inside Army Futures Command, said that the service has finished its component critical design review (CDR) process, and has moved on to its full program CDR, a key milestone before moving into testing. However, “given COVID and all of the factors that have gone on with COVID,” the plan to have the full CDR done during second quarter has been pushed to third quarter, Mason said at an event hosted by the Heritage Foundation. ITEP is “the number one watch item we've had across the future vertical lift portfolio for COVID impacts,” Mason said, because “hardware needs to be coming in the latter part of this year so we can test at the component level, assemble into the engine, and then go to first engine test.” “So that's going to be critical over the next month to two months, to see where we stand on hardware deliveries with that, and then whether or not we will reach first engine test at the time that we had originally stated,” he said, noting the plan is for engine tests to proceed in 2021. Mason also noted that the delay is less dramatic than it may seem, because the original plan for ITEP called for the full CDR to be completed in the fourth quarter of this year; the Army felt it was ahead of schedule enough to shift that target to second quarter, until COVID caused the delay. In other words, CDR being completed in Q3 still means the program is ahead of its original baseline. General Electric Aviation won the $517 million award for the engineering, manufacturing and development phase in February 2019. The requirements included developing a 3,000 shaft horsepower engine that reduces fuel consumption by 25 percent and increases service life by 20 percent compared to the legacy T700 currently used in the Army's AH-64 Apache and UH-60 Black Hawk helicopters. In addition to replacing the engines on those two leacy platforms, ITEP is expected to power the Future Attack Reconnaissance Aircraft, or FARA design. For the heavier future rotorcraft known as the Future Long-Range Assault Aircraft, or FLRAA, the Army is looking at a heavier engine design, although the companies competing for the design will have the ability to pick their own engine designs as part of their pitches. “We really think the efficiencies there with a two engines strategy across all of Army aviation's tactical fleet would be a powerful way to go at both readiness and affordability concerns,” said Rugen. https://www.defensenews.com/land/2020/06/10/the-next-few-months-are-critical-for-the-armys-new-helicopter-engine/

  • Contract Awards by US Department of Defense - November 16, 2020

    November 17, 2020 | International, Aerospace, Naval, Land, C4ISR, Security

    Contract Awards by US Department of Defense - November 16, 2020

    NAVY General Dynamics Electric Boat Corp., Groton, Connecticut, is awarded a $9,473,511,245 cost-plus-incentive-fee modification to previously awarded contract N00024-17-C-2117. The contract modification exercises an option for construction and test of the lead and second ships of the Columbia class SSBN 826 and SSBN 827, as well as associated design and engineering support. This modification to the integrated product and process development (IPPD) contract supports the fiscal 2021 construction start of the lead ship (SSBN 826) and advance procurement, advance construction, coordinated material buys and full construction of the follow hull (SSBN 827) in fiscal 2024. Work will be performed in Groton, Connecticut (36%); Newport News, Virginia (25%); Quonset Point, Rhode Island (17%); with other efforts performed at various sites throughout the U.S. (each less than 1%) (22%), and is expected to be completed by April 2030. Efforts within the ship include the Common Missile Compartment which is a joint U.S./United Kingdom effort. Fiscal 2021 National Sea-Based Deterrence Fund (NSBDF) funding in the amount of $545,186,307 (96%); and fiscal 2020 NSBDF funding in the amount of $19,936,251 (4%) will be obligated at the time of award and will not expire at the end of the current fiscal year. This action leverages the acquisition authorities contained in 10 U.S. Code §2218a, NSBDF. The Naval Sea Systems Command, Washington, D.C., is the contracting activity. Raytheon Co., Tewksbury, Massachusetts, was awarded a $94,039,953 cost-plus-incentive-fee, cost-plus-fixed-fee and cost-only modification to previously awarded contract N00024-17-C-5145 to exercise options and realign funding for DDG 1000 ship class integrated logistics support and engineering services. Work will be performed in Portsmouth, Rhode Island (41%); Tewksbury, Massachusetts (36%); Los Angeles, California (8%); San Diego, California (5%); Ft. Wayne, Indiana (4%); Marlboro, Massachusetts (4%); Bath, Maine (1%); and Nashua, New Hampshire (1%), and is expected to be completed by October 2021. Fiscal 2021 operation and maintenance (Navy) funding in the amount of $10,980,000 was obligated at the time of award and will expire at the end of the current fiscal year. The Naval Sea Systems Command, Washington, D.C., is the contracting activity. (Awarded Nov. 2, 2020) The Boeing Co., Seattle, Washington, is awarded a $14,181,537 modification (P00009) to firm-fixed-price order (2017) against previously issued basic ordering agreement N00019-16-G-0001. This modification exercises options for production, delivery and installation of 24 P-8A Poseidon Increment III Block I retrofit kits for the Navy. Work will be performed in Seattle, Washington (98.7%); and Mesa, Arizona (1.3%), and is expected to be completed in November 2022. Fiscal 2021 aircraft procurement (Navy) funds for $14,181,537 will be obligated at time of award, none of which will expire at the end of the current fiscal year. The Naval Air Systems Command, Patuxent River, Maryland, is the contracting activity. Progeny Systems Corp., Manassas, Virginia, is awarded a $9,428,513 cost-plus-fixed-fee and cost-reimbursable modification to previously awarded contract N00024-19-C-6267 to exercise options for engineering services. Work will be performed in Manassas, Virginia, and is expected to be completed in December 2021. Fiscal 2020 shipbuilding and conversion (Navy) (88%); and fiscal 2021 research, development, test and evaluation (Navy) (12%) funding in the amount of $3,900,000 will be obligated at time of award and will not expire at the end of the current fiscal year. The Naval Sea Systems Command, Washington, D.C., is the contracting activity. AIR FORCE Lockheed Martin Corp., Fort Worth, Texas, has been awarded a $53,190,386 hybrid cost-plus-fixed-fee and firm-fixed-price modification (P00067) to contract FA8615-12-C-6016 for miscellaneous support for 50 retrofit aircraft to the Taiwan F-16 Peace Phoenix Rising program. This modification provides for contractor over and above support and acquisition of legacy aircraft hardware and equipment. Work will be performed in Fort Worth, Texas; and Taiwan, and is expected to be completed Dec. 31, 2023. Foreign Military Sales funds in the full amount are being obligated at the time of award. The Air Force Life Cycle Management Center, Wright-Patterson Air Force Base, Ohio, is the contracting activity. CORRECTION: The contract awarded on Oct. 30, 2020, to BAE Systems Technology Solutions & Services Inc., Rockville, Maryland, for $13,365,920, listed the incorrect contract number. The correct contract number is FA8720-21-F-0042. DEFENSE LOGISTICS AGENCY Outdoor Venture Corp.,** Stearns, Kentucky, has been awarded a maximum $37,464,448 firm-fixed-price, indefinite-delivery/indefinite-quantity contract for the Modular General Purpose Tent System and components. This was a competitive acquisition with two responses received. This is a one-year base contract with four one-year option periods. Location of performance is Kentucky, with a Nov. 4, 2021, ordering period end date. Using military services are Army, Navy, Air Force and Marine Corps. Type of appropriation is fiscal 2021 through 2022 defense working capital funds. The contracting agency is the Defense Logistics Agency Troop Support, Philadelphia, Pennsylvania (SPE1C1-21-D-1404). *Small business **Small business in historically underutilized business zones https://www.defense.gov/Newsroom/Contracts/Contract/Article/2416815/source/GovDelivery/

All news