June 12, 2020 | International, Naval

If the US Navy isn’t careful, its new unmanned tanker drone could face a 3-year delay

By:

WASHINGTON — The US Navy could face a three-year delay in testing of the MQ-25 Stingray carrier-based tanking drone if it doesn't get its designated test ships through the required modernizations on time, a possibility the Navy said was remote.

Two carriers — Carl Vinson and George H.W. Bush — have limited windows to complete the installation of unmanned aircraft control stations, and if operational commitments intervene it could create significant issues for the program, according to Navy officials and a government watchdog report.

“Program officials stated that, among other things, the Navy's potential inability to maintain its schedule commitments could require modifications to the contract that would impact the fixed-price terms,” the Government Accountability Office reported. “Specifically, the Navy faces limited flexibility to install MQ-25 control centers on aircraft carriers.

“If the Navy misses any of its planned installation windows, the program would have to extend MQ-25 development testing by up to 3 years. According to officials, such a delay could necessitate a delay to initial capability and result in a cost increase.”

Navy officials say a three-year delay is “extremely unlikely,” however the Navy has struggled in recent years to balance its modernization schedules with operational commitments, a problem that its “Optimized Fleet Response Plan” deployment rotation scheme was supposed to address. Ultimately, a delay would further push back the Navy's ability to extend its carrier air wing's range through unmanned tanking, critical to keeping the service's powerful strike arm relevant against long-range guided munitions.

The Navy believes it can avoid a schedule delay and is working toward keeping the program on track, said Jamie Cosgrove, a spokesperson for Naval Air Systems Command.

“The Navy is still planning to achieve [initial operating capability] in 2024,” Cosgrove said. “A three-year extension of development testing and a delay to IOC is extremely unlikely and represents improbable scenarios where both aircraft carriers currently designated to support MQ-25 testing are unavailable due to operational requirements, or the program misses the planned periods to install the MQ-25 test equipment on those two carriers.

“Should either of these unlikely scenarios occur, the program will reevaluate the schedule and determine how to best mitigate schedule impacts to deliver the mission-critical MQ-25 to the Fleet ASAP.”

Unmanned control

The specific alternations needed to operate the MQ-25 Stingray include special control and network equipment, Cosgrove said.

The program of record is the Unmanned Carrier Aviation Mission Control System and installing it will include setting up a control room known as the Unmanned Aviation Warfare Center on the ship. The equipment in the UAWC will include control stations, network interfaces and routing equipment, commanding and control equipment and network infrastructure, Consgrove said.

The Navy awarded Boeing an $805 million contract to build the first four MQ-25 aircraft, with options for three additional aircraft. In April, the Navy announced it had exercised the option to the tune of $84.7 million, bringing the total number of Stingrays under contract to 7.

Ultimately the Navy plans to buy 69 additional aircraft as part of the its full production run, according to the GAO report.

The Navy's former air boss Vice Adm. Mike Shoemaker told USNI Proceedings in a 2017 interview that the MQ-25 would extend the carrier air wing's range by up to 400 miles.

Juggling maintenance

The Navy has struggled to maintain its carrier schedules in recent years as the problems have arisen with carriers during their availabilities. For example, last year, the carrier Abraham Lincoln was extended on its deployment because its relief, the carrier Harry S Truman, was stuck in maintenance to repair unforeseen issues.

That can throw a monkey wrench into the Navy's overstretched deployment rotation scheme, meaning that other carriers have their deployments extended while still others have their maintenance availabilities truncated to play catch up. But that can lead to even more problems down the road with differed maintenance and worn-out equipment that ultimately adds up to a significant readiness hole that is tough to dig out from.

All of this is exacerbated by crushing demands from Combatant Commanders for Navy forces overseas, which ultimately is driving the vicious cycle.

That means the Navy will have to manage the risk of impacting the Vinson and Bush's upcoming maintenance availabilities to not set back the MQ-25 development cycle.

https://www.defensenews.com/naval/2020/06/10/if-the-us-navy-isnt-careful-its-new-unmanned-tanker-drone-could-face-a-3-year-delay/

On the same subject

  • Pratt & Whitney is pitching a new version of the F-35 engine

    June 14, 2018 | International, Aerospace

    Pratt & Whitney is pitching a new version of the F-35 engine

    WASHINGTON — Pratt & Whitney is developing upgrades to the F-35's engine that will give it the power and cooling necessary to make the U.S. Defense Department's most sensor-heavy fighter jet even more of a powerhouse. The new Growth Option 2.0 upgrade for the F135 engine, launched on Tuesday, adds a more advanced power and thermal management system that could be used to help the F-35 incorporate new weapons and sensors, the company said. It also integrates a new compressor and turbine technologies that yield greater thrust and fuel savings, which were part of the Growth Option 1.0 concept unveiled in 2017. In a June 12 interview with Defense News, Matthew Bromberg, president of Pratt & Whitney's military engines unit, said the company decided to work on improvements to the F135's power and thermal management system, or PTMS, based on feedback from the F-35 Joint Program Office. Pratt in 2017 tested an early version of the Growth Option 1.0 motor called the fuel burn reduction demonstrator engine, which demonstrated that the upgrade could improve thrust by up to 10 percent and reduce fuel consumption by up to 6 percent. But while the community that flies the F-35B short-takeoff-and-vertical-landing variant was gung-ho on the thrust improvements, the JPO said that better power and cooling was what was really needed — especially as the program transitions from the development phase to modernization, also known as Block 4 or Continuous Capability Development and Delivery, Bromberg said. Pratt has already begun testing some technologies from the Growth Option 2.0 suite in various rigs and demonstrators. Bromberg called the upgrades “relatively low risk” and said it could probably be proven out in a four-year technology demonstration program. But he declined to talk about completed testing or to quantify the new power and cooling improvements, saying only that they were “significant.” Although the Defense Department hasn't signed onto an upgraded F135 engine as part of the Continuous Capability Development and Delivery effort, Pratt executives have been hopeful that it will do so as it finalizes that strategy. “As the F-35 program moves forward with the Continuous Capability Development and Delivery strategy, we strive to stay in front of propulsion advances needed to enable F-35 modernization,” Bromberg said in a statement. “We're continuously assessing customer needs and responding with technology options to keep them ahead of evolving threats.” https://www.defensenews.com/industry/2018/06/13/pratt-whitney-is-pitching-a-new-version-of-the-f-35-engine/

  • Le ministère des Armées a consommé tous ses crédits en 2020

    January 13, 2021 | International, Aerospace, Naval, Land, C4ISR, Security

    Le ministère des Armées a consommé tous ses crédits en 2020

    La ministre des Armées, Florence Parly, a déclaré, mardi 12 janvier, lors de son audition à l'Assemblée nationale, que son ministère a consommé les 37,5 milliards d'euros qui étaient prévus en loi de finances initiale pour 2020, malgré les perturbations induites par la crise sanitaire. Elle a également indiqué que le ministère des Armées a bénéficié de 800 millions d'euros de crédits dégelés en novembre, une « date qui n'avait jamais été aussi anticipée par rapport à la fin de l'année ». En 2021, le ministère doit présenter une actualisation de la loi de programmation militaire (LPM), dont la mise en œuvre devra intervenir avant la fin de l'année 2021. Cette actualisation doit notamment permettre de préciser l'évolution des effectifs pour les années 2024 et 2025 et de vérifier la bonne adéquation entre les objectifs fixés dans la LPM, les réalisations et les moyens consacrés. Florence Parly a précisé que ce processus doit aussi déterminer les menaces auxquelles la France risque d'être confrontée dans les années à venir. La Tribune du 13 janvier

  • New Ransomware-as-a-Service 'Eldorado' Targets Windows and Linux Systems

    July 8, 2024 | International, Security

    New Ransomware-as-a-Service 'Eldorado' Targets Windows and Linux Systems

    New Eldorado ransomware targets Windows and Linux systems, affecting 16 companies. Discover the latest ransomware threats and cybersecurity measures.

All news