WASHINGTON — Only about half of the F-35s worldwide were ready to flyduring an eight-month period in 2018, with the wait for spare parts keeping jets on the ground nearly 30 percent of the time, according to a new report by the Government Accountability Office.
Over the past several years, the Defense Department has sought to improve mission capable rates by making improvements to the way it and F-35 contractor Lockheed Martin order, stockpile and repair spare parts. However, GAO's findings imply that the situation may have gotten worse.
The GAO's report, released April 25, investigated how spare parts shortages impacted F-35 availability and mission capable rates in 2018, with most data gathered between a May and November sustainment contract period.
“In 2017, we reported that DOD was experiencing sustainment challenges that were reducing warfighter readiness, including delays of 6 years in standing up repair capabilities for F-35 parts at its depots and significant spare parts shortages that were preventing the F-35 fleet from flying about 20 percent of the time,” GAO said in the report.
“According to prime contractor data, from May through November 2018, F-35 aircraft across the fleet were unable to fly 29.7 percent of the time due to spare parts shortages,” it said. “Specifically, the F-35 supply chain does not have enough spare parts available to keep aircraft flying enough of the time necessary to meet warfighter requirements.”
That lack of improvement may make it more difficult for the U.S. Air Force, Navy and Marine Corps to hit an 80 percent mission capable rate by the end of fiscal year 2019, as mandated by then-Defense Secretary Jim Mattis last fall.
The military services stopped providing mission capable rates for aircraft last year, citing operational sensitivities. However, the data put forth by the GAO indicates that progress stagnated in the lead up to Mattis' order.
From May to November 2018, mission capable rates — which measure how many planes possessed by a squadron can perform at least one of its missions — hovered around 50 percent for all versions of the F-35.
But when GAO assessed how many planes were fully mission capable — meaning that they were ready to fulfill all of their mission sets — all variants were far from meeting the 60 percent target. Only 2 percent of F-35C carrier takeoff and landing versions hit the fully mission capable mark, with the F-35Bs slightly better at 16 percent and the F-35A at 34 percent.
The GAO is skeptical that the services will be able to hit the 80 percent mission capable rate goal this year, and it is even more critical of the Defense Department's plans to fund spares in future years.
The department intends to buy “only enough parts to enable about 80 percent of its aircraft to be mission-capable based on the availability of parts.” However, that planning construct will likely only yield a 70 percent mission capable rate at best, the GAO said, because it only accounts for the aircraft on the flight line and not jets that are in the depot for longer term maintenance.
No silver bullet for parts shortage issues
Like all complicated problems, there is no single solution for the F-35 spare parts shortage, which is driven by a number of factors.
GAO indicated that the Defense Department still has “a limited capacity” to repair broken parts, creating a backlog of 4,300 parts still needing to be addressed. Between September and November, it took more than six months to fix parts that should have been repaired in a window of two to three months.
The F-35's much-maligned Autonomic Logistics Information System (ALIS) was designed to be able to track parts and automate the process of generating and expediting work orders, however, GAO notes that the system still requires manual workarounds from users in order to accomplish tasks.
Supply and maintenance personnel cited challenges such as “missing or corrupted electronic spare parts data,” limited automation and problems caused by ALIS's subsystems not communicating with each other properly, it said.
As the F-35 is still a relatively new platform, it has taken time for the program to assess which parts have been failing more often than previously estimated — but that is an area where the Defense Department is making progress, the GAO stated.
“DOD has identified specific parts shortages that are causing the greatest aircraft capability degradation, and it is developing short-term and long-term mitigation strategies to increase the quantity and reliability of these parts,” the report said.
One such component is a coating used on the F-35's canopy to help it maintain its stealth characteristics, which has been found to peel off at an unexpected rate, creating a heightened demand for canopies.
“To address these challenges, the program is looking for additional manufacturing sources for the canopy and is considering design changes,” the GAO stated.
But — somewhat paradoxically — the F-35 has been flying for a long enough time that there is significant parts differences between the first jets that rolled off the production line to the most recently manufactured planes. The GAO found “at least 39 different part combinations across the fleet” on top of variations in software.
“According to the program office, DOD spent more than $15 billion to purchase F-35 aircraft from the earliest lots of production, specifically lots 2 through 5 ... but it faces challenges in providing enough spare parts for these aircraft,” the report stated.
One problem — the cannibalization of F-35 aircraft for parts — is partially user-inflicted.
“From May through November 2018, F-35 squadrons cannibalized (that is, took) parts from other aircraft at rates that were more than six times greater than the services' objective,” the GAO stated. “These high rates of cannibalization mask even greater parts shortages, because personnel at F-35 squadrons are pulling parts off of other aircraft that are already unable to fly instead of waiting for new parts to be delivered through the supply chain.”
During an interview this February, Lt. Col. Toby Walker, deputy commander of the 33rd Maintenance Group, told Defense News that F-35 maintainers at Eglin Air Force Base, Fla., had stopped pulling parts off a cannibalized F-35 and had seen some improvements to mission capable rates as a result.
“We're not continually moving parts from one aircraft to another. We're relying on the program to provide our parts,” he said. “It was a very strategic plan to do that to increase aircraft availability by not sitting an aircraft down.”
In a statement, Lockheed Martin said that it had taken key steps to improve parts availability, such as transitioning some suppliers to performance based logistics contracts that incentivize companies to meet certain targets, as well as “master repair agreements” that will allow other suppliers to make longer term investments in their production capability.
“These actions are beginning to deliver results and we're forecasting additional improvement. Newer production aircraft are averaging greater than 60 percent mission capable rates, with some operational squadrons consistently at 70 percent,” the company said.
“From a cost perspective, Lockheed Martin has reduced its portion of cost per aircraft per year by 15 percent since 2015. Our goal is to further reduce costs to $25,000 cost per flight hour by 2025, which is comparable to legacy aircraft while providing a generational leap in capability.”
August 19, 2024 | International, Land
Thanks, Tracy, for that kind introduction. Good afternoon everyone, bonjour tout le monde.
December 17, 2020 | International, Land
By: Sebastian Sprenger COLOGNE, Germany — The European Commission has awarded Estonia and the country's robotics company Milrem a grant to lead the way on a standard architecture for military unmanned ground vehicles, the company announced. The deal, worth close to $40 million and signed Dec. 11, formally kicks off a pan-European development for a new generation of battlefield ground robots. Named Integrated Modular Unmanned Ground System, or iMUGS, the project uses Milrem's THeMIS vehicle as a reference platform for creating a “standardized European-wide ecosystem for aerial and ground platforms,” according to the company. Also covered by the project is relevant technology in the fields of command and control, communications, sensors, payloads, and algorithms. The connection to the European Union's coffers comes through the bloc's European Defence Industrial Development Programme. Besides Estonia as the lead, Belgium, Finland, France, Germany, Latvia and Spain also are part of the iMUGS group, adding a combined €2 million (U.S. $2.4 million) to the effort. The countries each bring their relevant national companies to the table, including Safran Electronics & Defense, Nexter Systems, Krauss-Maffei Wegmann, Diehl Defence, and Bittium Wireless. “Estonia has the honor and a great responsibility taking the lead in this project as nothing on a similar scale has been conducted before,” said Martin Jõesaar, chief of the project office in the Estonian Centre for Defence Investment. “Our goal is not only making iMUGS a one-time effort, but to build it into a base project for future developments. Our long-term goal is that each of the modular systems built will pave a way for further innovation in its field.” While the sums involved in iMUGS are relatively small in the world of defense programs, the effort has the potential to shape the European market for military robotic vehicles. The initiative is a prime example of defense companies like Milrem, some of them years ago, sensing a chance to position their own offerings firmly in the thicket of European defense priorities. But the THeMIS robot is not the only game in town. Rheinmetall is equally trying to position its unmanned portfolio in the European market, even without EU backing. In the case of its Mission Master vehicle, the intellectual property belongs to the company's Canadian division, which makes support through EU channels tricky. Still, the vehicle is being tried by the land forces of several countries on the European continent. According to Milrem, European countries are expected to need thousands of ground robots during the next 10-15 years, creating a market valued in the billions of euros. “With seven participating nations and key industrial players, the unmanned ground system developed during iMUGS is expected to become the preferred European solution for integrating into armed units,” the company claims. https://www.defensenews.com/global/europe/2020/12/16/european-union-awards-grant-to-forge-unmanned-ground-vehicle-standard/
July 5, 2021 | International, Aerospace, C4ISR
The need for better target recognition is important in environments with moving targets and near civilians.