July 9, 2024 | International, Land
Ukraine industry chief sees bumper year for land-based drones
Kyiv's head of strategic industries said that the push for ground robotics was part of a bigger bet on "defense tech."
May 10, 2019 | International, Naval
"Nous travaillons sur une nouvelle génération de porte-avions a déclaré Florence Parly au micro de Jean-Jacques-Bourdin. Puisque le porte-avions (le Charles-de-Gaulle) aujourd'hui déployé dans l'océan Indien est un élément extrêmement fédérateur y compris au plan européen".
La ministre française des Armées a en revanche jugé prématurée la proposition allemande d'un porte-avions européen, soulignant que cela nécessitait un commandement européen compliqué à mettre en œuvre.
" Je crois qu'on n'en est pas encore tout à fait là." "Il faut réfléchir d'abord à ce que pourraient être les conditions d'emploi d'un porte-avions européen", a observé Florence Parly.
"Une chose est de le construire à plusieurs, une autre de le mettre sous un commandement européen. Là, c'est beaucoup plus compliqué", a-t-elle ajouté.
Rappelons que le Charles-de-Gaulle a quitté son port d'attache toulonnais fin 2018 pour une mission de 4 mois. Long de 261,5 mètres, ce vaisseau-amiral français peut emporter 40 aéronefs, dont 30 avions Rafale. Sa construction avait débuté en 1987 pour remplacer le Clemenceau.
 
					July 9, 2024 | International, Land
Kyiv's head of strategic industries said that the push for ground robotics was part of a bigger bet on "defense tech."
 
					July 6, 2020 | International, Aerospace, Naval, Land, C4ISR, Security
La ministre des Armées, Florence Parly, a présenté vendredi la nouvelle « stratégie énergétique de défense » des Armées. Parmi les mesures annoncées figurent notamment le lancement d'un démonstrateur de blindé hybride de modèle Griffon en 2022, ou le développement de la simulation pour les séances d'entraînement dans l'armée de l'Air afin d'économiser du kérosène. Les systèmes d'hébergement de données informatiques vont de plus être revus pour tenter de réutiliser la chaleur des réseaux pour des infrastructures des Armées. Des recherches sur l'hydrogène sont également programmées, notamment pour équiper les piles à combustibles des soldats ou trouver des minidrones propulsés à l'hydrogène. D'ici fin 2021, un logiciel mesurant précisément les consommations énergétiques de toutes les emprises des Armées devrait par ailleurs être disponible. Les Echos du 3 juillet
 
					August 4, 2020 | International, Land
By: Jen Judson WASHINGTON — The coronavirus pandemic has caused another delay for the U.S. Army's plagued M113 replacement program, which has struggled with manufacturing problems as the BAE Systems-made Armored Multi-Purpose Vehicle entered low-rate initial production, according to the company's second quarter fiscal 2020 earnings briefing released last week. The company had to delay delivery of the first LRIP vehicles by roughly four to six months, moving delivery from March to July. But as BAE prepared to move ahead on delivery, the pandemic hit, bringing with it another delay of roughly a month, which pushed the vehicles' delivery date to August. The AMPV program entered LRIP in January 2019, but the program office indicated last year that delivery of the first vehicles would be delayed by two months and the completion of production qualification testing would be delayed by seven months due to tooling and assembly line challenges at BAE's facility in York, Pennsylvania. Because of the issues, the Army's AMPV budget request in FY21 showed the program took a hit. The service indicated it would buy 32 vehicles instead of the 143 planned for the fiscal year, and the program's budget was cut from $445 million to $193 million. The Army and BAE developed “a production approach that would allow us to incorporate efficiencies during LRIP that modernize manufacturing and increase the overall throughput of the program,” Amanda Niswonger, a BAE spokeswoman, told Defense News in an Aug. 3 statement. “This included installing new technology and processes such as robotic welding, digital X-ray, and advanced machining. And we worked closely with the Army to update and refine manufacturing processes to incorporate the most modern weld and inspection technology,” she said. “These changes had an impact on our delivery timeline which was not reflected in the original delivery schedule, but continues to meet the Army's fielding schedule.” The service and BAE had formalized the schedule change just as COVID-19 hit the U.S., which affected a large number of manufacturing facilities and supply chains globally. “We have worked tirelessly to mitigate the impacts from COVID-19 with our employees, supply network, and customer base to keep our manufacturing sites operational and continue to receive parts as needed,” Niswonger said. “Unfortunately we could not overcome all the challenges and our first delivery has slipped one month.” https://www.defensenews.com/land/2020/08/03/pandemic-causes-latest-delay-in-us-armys-m113-replacement-program/