Federal officials don't want to be pinned down on a date to start building new navy: documents

DAVID PUGLIESE, OTTAWA CITIZEN

DND officials warned that committing to a specific time to start cutting steel on the warships 'will add additional risk'

Irving Shipbuilding is pushing federal officials to announce a firm date to begin construction on Canada's new fleet of warships, arguing that will help drive the project along. But the company is facing resistance from federal officials concerned about missing a publicly announced start date, as happened with the Arctic patrol ships now under construction, according to documents released to Postmedia.

Federal officials have continued to say that construction of the Canadian Surface Combatant fleet would begin sometime in the early 2020s but no specific date had been set.

Irving representatives tried last year to convince federal bureaucrats of the need to set a specific date to begin construction. “(Irving) noted that hard dates is what drives the work,” according to the report from the Jan. 17, 2017 meeting of deputy ministers overseeing the national shipbuilding plan.

But the firm faced pushback from Department of National Defence officials.

“DND cautioned against setting a hard production date to work towards, noting the challenges this approach caused on AOPS,” the report noted. DND officials warned that committing to a specific time to start cutting steel on the warships “will add additional risk.”

The AOPS were announced in 2007 by then prime minister Stephen Harper and were supposed to be in the water by 2013. But construction didn't start until 2015. The first ship was launched on Sept. 15 and won't be operational until 2019.

Three consortiums have submitted bids for the surface combatant program and those are still being evaluated. The project will see 15 warships buiilt by Irving Shipbuilding in Halifax. A winning bid is expected to be selected sometime this year.

The ships will form the backbone of the future Royal Canadian Navy.

Scott Leslie, director general of large combat ship construction at Public Services and Procurement Canada, said that a more precise construction date can't be provided now because a winning design has yet to be selected.

“There are a lot of variables around it, one of the main ones being which design is chosen and how much work is required to get that design evolved and buildable at Irving Shipyards,” Leslie explained.

Irving is worried about the gap after building of the Arctic Offshore Patrol Ships but before construction of the surface combatants. If the two projects are not aligned, workers could face layoffs and Irving is worried it will lose skilled personnel.

The government has already faced delays and rising costs with the warships. In 2008, it estimated the total cost to be about $26 billion. But in 2015, then navy commander Vice Admiral Mark Norman voiced concern that taxpayers may not have been given all the information and predicted the cost alone for the ships would be around $30 billion.

Cost estimates for the entire project are now between $55 billion and $60 billion. About half is for systems and equipment on the 15 ships, according to federal documents obtained by Postmedia through the Access to Information law. “Approximately one-half of the CSC build cost is comprised of labour in the (Irving's) Halifax yard and materials,” the documents added.

Last year, Jean-Denis Fréchette, the Parliamentary Budget Officer, estimated the CSC program would cost $61.82 billion. He also warned that every year the awarding of the contract is delayed beyond 2018, taxpayers will spend an extra $3 billion, because of inflation.

The first ship will be delivered in the mid 2020s.

In November, in a surprise twist, a French-Italian consortium declined to formally submit a bid and instead offered Canada a fleet of vessels at around $30 billion. Officials with Fincantieri of Italy and Naval Group of France said they don't believe the procurement process as currently designed will be successful.

https://ottawacitizen.com/news/canada/federal-officials-dont-want-to-be-pinned-down-on-a-date-to-start-building-new-navy-documents-show/wcm/eaace91c-ece6-4a5a-b130-e1d96b7ff261

On the same subject

  • No icebreakers in federal government’s $15.7B plan for new coast-guard ships

    June 3, 2019 | Local, Naval

    No icebreakers in federal government’s $15.7B plan for new coast-guard ships

    By Lee Berthiaume, The Canadian Press OTTAWA — The Canadian Coast Guard's recent struggles resupplying northern communities and rescuing ice-jammed ferries appear set to continue despite Prime Minister Justin Trudeau's promise to spend $15.7 billion on "a complete fleet renewal." That's because none of the 18 vessels the government announced last week that it plans to buy will be an icebreaker, meaning the coast guard will be forced to continue relying on its existing icebreaker fleet for the foreseeable future. Many of those are nearing — or have already exceeded — their expected lifespans, which has resulted in breakdowns and other problems that have affected coast-guard operations, such as resupply runs and assisting ferries in winter. Federal procurement minister Carla Qualtrough acknowledged on the sidelines of the annual Cansec arms-trade show this week "there's definitely a capability gap on icebreakers," but wouldn't say when it would be addressed. Qualtrough instead indicated that any announcement on more ships for the coast guard would likely come after the government adds a third shipyard to the two that are already partners in the federal shipbuilding plan. "There's definitely more ships coming," she said on Thursday. "It will really be dependent on how long it takes the third yard to get itself ready to build the kind of ships we need." The search is expected to start in the coming weeks, but while many observers expect Davie Shipbuilding in Quebec City to emerge victorious, a senior government official maintained a decision is unlikely before October's election. The government's planned $15.7-billion investment unveiled last week includes two Arctic patrol ships to be built by Irving Shipbuilding in Halifax and 16 so-called multipurpose vessels from Seaspan Shipbuilding in Vancouver. But those vessels are what officials describe as "ice-capable," rather than icebreakers, meaning the coast guard will need to continue to rely on its existing fleet for many of its operations. The icebreaker fleet did receive a boost on Thursday, when the Canadian Coast Guard officially welcomed the CCGS Molly Kool to its ranks after several months of conversion work at Davie. The CCGS Molly Kool is the first of three second-hand icebreakers that Davie has sold to the government, which the coast guard has said it plans to use for the next 15 to 20 years to fill any gaps until replacements are built. But while the government is spending millions to refit its current icebreakers, which are on average 35 years old, and keep them running as long as possible, the question remains when those replacements will arrive. The only new icebreaker currently in the government's multibillion-dollar shipbuilding plan is the polar-class CCGS John G. Diefenbaker, which was expected in 2017 before various delays pushed it back to the next decade. "We haven't built a coast guard-designed icebreaker since 1983. That was the last time," said Rob Huebert, an expert on the coast guard at the University of Calgary. "And anything we have bought is usually second-hand from industry." The coast guard doesn't have clout in Ottawa, Huebert said, which has translated into a lack of long-term planning or investment by successive governments — except when there are political points to be scored. And while the addition of a third yard to the federal shipbuilding plan should mean icebreakers will follow soon after, Huebert said it is all ad hoc and will simply lead to the same problems down the road. "I get incensed by the fact that we do not have any form of a long-term coast-guard renewal for icebreakers." Documents obtained by The Canadian Press warned more than a third of the coast guard's 26 large vessels, including its icebreakers, had exceeded their expected lifespans — and that many wouldn't survive until replacements arrived. The fleet's advanced age was also already affecting the coast guard's ability to do its job, including reduced search-and-rescue coverage, ferry-service disruptions and cancelled resupply runs to Arctic and coastal communities. —Follow @leeberthiaume on Twitter Lee Berthiaume, The Canadian Press https://www.nationalnewswatch.com/2019/05/31/no-icebreakers-in-federal-governments-15-6b-plan-for-new-coast-guard-ships/#.XPFqzBZKiUl

  • Le Ministère de la Défense Nationale et les Forces armées canadiennes -- Conférence de Kingston sur la sécurité internationale  /  The Department of National Defence and Canadian Armed Forces update -- Kingston Conference on International Security

    October 29, 2021 | Local, Aerospace, Naval, Land, C4ISR, Security

    Le Ministère de la Défense Nationale et les Forces armées canadiennes -- Conférence de Kingston sur la sécurité internationale / The Department of National Defence and Canadian Armed Forces update -- Kingston Conference on International Security

    Chers collègues et partenaires du milieu de la défense, En tant que gestionnaire par intérim du BEPS, je tenais communiquer avec vous pour partager le texte du discours d'ouverture prononcé par le chef d'état-major par intérim, le général Wayne Eyre à la Conférence de Kingston sur la sécurité internationale. Je suis conscient que certains ont probablement assisté à la conférence, mais je crois qu'une version écrite peut être une référence utile. La conférence, EN CAS D'URGENCE : Le rôle des militaires dans la pandémie et les crises futures a eu lieu cette semaine. Conférence de Kingston sur la sécurité internationale Comme toujours, nous vous remercions de votre collaboration. (Veuillez noter que le discours est bilingue et n'a pas été entièrement traduit dans l'une ou l'autre des langues officielles.) Cordialement, ***** Dear colleagues and partners in defence, As the acting manager for the Strategic Engagement Office, I wanted to take this opportunity to share with you the opening address given by the Acting Chief of Staff, General Wayne Eyre at the Kingston Conference on International Security. I'm conscious of the fact that many of you probably attended but a written version of the address may be interesting as a reference. The conference, IN CASE OF EMERGENCY: The Military's Role in the Pandemic & Future Crises, was held this week. Kingston Conference on International Security As always, we thank you for your collaboration.

  • Arcfield Canada awarded $7.7M subcontract by L3Harris for supply chain services for CF-18 fleet - Skies Mag

    July 28, 2022 | Local, Aerospace

    Arcfield Canada awarded $7.7M subcontract by L3Harris for supply chain services for CF-18 fleet - Skies Mag

    Arcfield Canada has been awarded a subcontract by L3Harris Technologies to provide supply chain management services to the CF-18 fleet, based at CFB Cold Lake and Bagotville.

All news