September 24, 2018 | Local, Naval

Federal officials don't want to be pinned down on a date to start building new navy: documents

DAVID PUGLIESE, OTTAWA CITIZEN

DND officials warned that committing to a specific time to start cutting steel on the warships 'will add additional risk'

Irving Shipbuilding is pushing federal officials to announce a firm date to begin construction on Canada's new fleet of warships, arguing that will help drive the project along. But the company is facing resistance from federal officials concerned about missing a publicly announced start date, as happened with the Arctic patrol ships now under construction, according to documents released to Postmedia.

Federal officials have continued to say that construction of the Canadian Surface Combatant fleet would begin sometime in the early 2020s but no specific date had been set.

Irving representatives tried last year to convince federal bureaucrats of the need to set a specific date to begin construction. “(Irving) noted that hard dates is what drives the work,” according to the report from the Jan. 17, 2017 meeting of deputy ministers overseeing the national shipbuilding plan.

But the firm faced pushback from Department of National Defence officials.

“DND cautioned against setting a hard production date to work towards, noting the challenges this approach caused on AOPS,” the report noted. DND officials warned that committing to a specific time to start cutting steel on the warships “will add additional risk.”

The AOPS were announced in 2007 by then prime minister Stephen Harper and were supposed to be in the water by 2013. But construction didn't start until 2015. The first ship was launched on Sept. 15 and won't be operational until 2019.

Three consortiums have submitted bids for the surface combatant program and those are still being evaluated. The project will see 15 warships buiilt by Irving Shipbuilding in Halifax. A winning bid is expected to be selected sometime this year.

The ships will form the backbone of the future Royal Canadian Navy.

Scott Leslie, director general of large combat ship construction at Public Services and Procurement Canada, said that a more precise construction date can't be provided now because a winning design has yet to be selected.

“There are a lot of variables around it, one of the main ones being which design is chosen and how much work is required to get that design evolved and buildable at Irving Shipyards,” Leslie explained.

Irving is worried about the gap after building of the Arctic Offshore Patrol Ships but before construction of the surface combatants. If the two projects are not aligned, workers could face layoffs and Irving is worried it will lose skilled personnel.

The government has already faced delays and rising costs with the warships. In 2008, it estimated the total cost to be about $26 billion. But in 2015, then navy commander Vice Admiral Mark Norman voiced concern that taxpayers may not have been given all the information and predicted the cost alone for the ships would be around $30 billion.

Cost estimates for the entire project are now between $55 billion and $60 billion. About half is for systems and equipment on the 15 ships, according to federal documents obtained by Postmedia through the Access to Information law. “Approximately one-half of the CSC build cost is comprised of labour in the (Irving's) Halifax yard and materials,” the documents added.

Last year, Jean-Denis Fréchette, the Parliamentary Budget Officer, estimated the CSC program would cost $61.82 billion. He also warned that every year the awarding of the contract is delayed beyond 2018, taxpayers will spend an extra $3 billion, because of inflation.

The first ship will be delivered in the mid 2020s.

In November, in a surprise twist, a French-Italian consortium declined to formally submit a bid and instead offered Canada a fleet of vessels at around $30 billion. Officials with Fincantieri of Italy and Naval Group of France said they don't believe the procurement process as currently designed will be successful.

https://ottawacitizen.com/news/canada/federal-officials-dont-want-to-be-pinned-down-on-a-date-to-start-building-new-navy-documents-show/wcm/eaace91c-ece6-4a5a-b130-e1d96b7ff261

On the same subject

  • As DND pushed for Boeing P-8 aircraft government officials quietly fast-tracked removal of Aurora planes

    November 29, 2023 | Local, Aerospace

    As DND pushed for Boeing P-8 aircraft government officials quietly fast-tracked removal of Aurora planes

    National Defence fast-tracked removal of Aurora aircraft by a decade despite spending hundreds of millions modernizing the planes

  • Lockheed Martin Canada Welcomes ANZAC Frigate HMNZS TE KAHA to Canada to Begin Modernization Contract Work

    March 7, 2018 | Local, Naval

    Lockheed Martin Canada Welcomes ANZAC Frigate HMNZS TE KAHA to Canada to Begin Modernization Contract Work

    OTTAWA, Ontario, March 7, 2018 /PRNewswire/ -- Lockheed Martin (NYSE: LMT) Canada has signed a formal contract with the New Zealand government for ship installation and trials to complete the upgrade and modernization of the ANZAC class frigates. The first of two frigates, Her Majesty's New Zealand Ship (HMNZS) TE KAHA arrived in Victoria yesterday. Lockheed Martin Canada is responsible for designing and supplying the upgraded combat system for each ANZAC Class Frigate, including a new combat management system – based on Lockheed Martin Canada's Combat Management System 330 – along with the supply and integration of various sensors, a missile system and a Combat Systems Trainer. Lockheed Martin Canada has entered into a subcontractual agreement with Seaspan Victoria Shipyards Co. Ltd in Victoria, BC, to install the new systems on the ship platforms. "We are very happy to continue our relationship with the Royal New Zealand Navy," said Acting Vice President and General Manager of Lockheed Martin Canada RMS, Gary Fudge. "The New Zealand ANZAC Frigate Systems Upgrade marked our official entrance onto the international market as a combat systems integrator in 2014. Our continued partnership with the Navy is something we are very proud of," added Fudge. "Our partnership with Canadian shipyards on the Halifax Class Modernization program and the confidence that Canada placed in those shipyards on the National Shipbuilding Strategy program led directly to our ability to contract the ANZAC refit work to Seaspan," stated Fudge. Today, Lockheed Martin Canada is the Combat Systems Integrator (CSI) for four major active programs across three countries, including New Zealand's frigate upgrade project, the Chilean Navy's Type 23 modernization, Canada's Arctic Offshore Patrol Ship, and the lead program which saw the initial development of the CMS 330, the Halifax Class Modernization program. "The modernization and upgrades of ANZAC class frigates are critically important to the Royal New Zealand Navy," said Vice President of International Naval Systems Programs Kevin Arthurs. "These upgrades will provide the ships with a greater degree of survivability through a faster decision-making process and a more appropriate response to a variety of threats," added Arthurs. Her Majesty's New Zealand Ship (HMNZS) TE KAHA arrived in Canada yesterday and HMNZS TE MANA is scheduled to arrive in 2019. Under Lockheed Martin Canada supervision and direction, Seaspan Shipyards will refit and install the new systems with an expected completion date of 2020 for the entire contract. The second frigate, HMNZS TE MANA, is scheduled to arrive in 2019. For additional information, visit our website: www.lockheedmartin.ca. About Lockheed Martin Lockheed Martin Canada, headquartered in Ottawa, is the Canadian-based arm of Lockheed Martin Corporation, a global security and aerospace company employing 100,000 people worldwide. Lockheed Martin Canada has been Canada's trusted defence partner for nearly 80 years specializing in the development, integration and sustainment of advanced technology systems, products and services. The company employs approximately 980 employees at major facilities in Ottawa, Montreal, Halifax, Calgary, and Victoria, working on a wide range of major programs spanning the aerospace, defence and commercial sectors. SOURCE Lockheed Martin https://news.lockheedmartin.com/2018-03-07-Lockheed-Martin-Canada-Welcomes-ANZAC-Frigate-HMNZS-TE-KAHA-to-Canada-to-Begin-Modernization-Contract-Work

  • Canada Seeks Spending Stability As Fighter Competition Heats Up

    December 20, 2018 | Local, Aerospace

    Canada Seeks Spending Stability As Fighter Competition Heats Up

    Canada's Liberal Party entered office in 2015 with a promise to correct the previous government's “erratic” commitment to defense spending and reopen the competition for the Boeing CF-18 replacement. As Prime Minister Justin Trudeau's government enters a reelection campaign three years later, the Department of National Defense now has a long-term strategy calling for a significant increase in spending through 2027 but has been unable to break the cycle of ... Full article: http://aviationweek.com/defense/canada-seeks-spending-stability-fighter-competition-heats

All news