April 20, 2018 | International, Aerospace

Defense Department halts F-35 deliveries amid repair bill disagreement with Lockheed

By:

WASHINGTON — The Pentagon has suspended acceptance of most F-35 deliveries as manufacturer Lockheed Martin and the F-35 program office debate who should be responsible for fixing jets after a production issue last year.

“While all work in our factories remains active, the F-35 Joint Program Office has temporarily suspended accepting aircraft until we reach an agreement on a contractual issue and we expect this to be resolved soon,” a Lockheed spokeswoman confirmed in a statement, adding that the company remains confident that it can meet its delivery target of 91 aircraft for 2018.

News of the delivery pause was first reported by Reuters.

The dispute is rooted in a quality control issue that caused F-35 deliveries to stop from Sept. 21 to Oct. 20. At the time, corrosion was found in fastener holes of F-35As being repaired at Hill Air Force Base in Utah.

Lockheed and the JPO were able to agree on a corrective action plan, one source said, and Lockheed was able to complete planned deliveries of the F-35 for 2017.

But sometime after that, a dispute over who should pay for the fix resurfaced and the Defense Department opted to take another production pause, a source said, declining to comment on how long deliveries have been suspended.

“Per the direction of the program executive officer, F-35 deliveries have been temporarily paused while the government and Lockheed Martin reach an agreement on a contractual issue regarding repair work to remediate the known aircraft fastener hole primer quality escape,” said a statement from the F-35 joint program office.

“This is not a safety of flight issue but rather a contractual resourcing issue that needs to be resolved. The government has implemented this pause to ensure the warfighter receives a quality product from industry. We look forward to a swift resolution of this issue.”

Production of the aircraft is ongoing at Lockheed's line in Fort Worth, Texas, and at final assembly and check out facilities in Nagoya, Japan, and Cameri, Italy. A source noted that some customers have accepted planes due to warfighter demands.

According to Reuters, two aircraft have been delivered to the Defense Department since it imposed the suspension. Meanwhile, a repair bill for more than 200 jets is on the line.

The corrosion issue is just one of several production problems that has plagued the F-35 over the last couple years.

Vice Adm. Mat Winter, the F-35 joint program executive officer, spoke Wednesday at the Navy League's Sea Air Space conference but did not disclose the fact that deliveries had stopped.

A statement from the F-35 joint program office was added at 9:05EST on April 12.

https://www.defensenews.com/breaking-news/2018/04/11/defense-department-halts-f-35-deliveries-amid-repair-bill-disagreement-with-lockheed/

On the same subject

  • Le Taxan de Secapem labélisé

    November 5, 2019 | International, Aerospace

    Le Taxan de Secapem labélisé

    "Utilisé par les armées française" est un label récemment créé pour que les petites entreprises (de la micro entreprise à la PME) puissent valoriser leurs productions. Le sytème Taxan de Secapem vient d'être ainsi distingué. Produit depuis 1982, ce système est voué à l'entraînement du tir canon air-air et air-sol, et constitué d'une cible aérienne remorquée équipée pour restituer les résultats des tirs en temps réel. Le label, décerné officiellement par le ministère des armées française doit favoriser les exportations des ces produits. https://www.aerobuzz.fr/breves-defense/le-taxan-de-secapem-labelise/

  • Contractors Recovering From COVID Shutdowns: Bruce Jette

    May 14, 2020 | International, Land

    Contractors Recovering From COVID Shutdowns: Bruce Jette

    While the pandemic continues, Pentagon metrics show production on Army programs is returning to normal, the Army's acquisition chief told Breaking Defense. By SYDNEY J. FREEDBERG JR.on May 14, 2020 at 4:01 AM WASHINGTON: The number of defense contractors reopening after COVID-19 quarantines now exceeds the number of new shutdowns, the Army's senior acquisition official said in an interview. That is happening, Bruce Jette told me, because industry is learning and adapting. New health precautions, from disinfecting tools between shifts to social distancing on the factory floor, should contain further outbreaks of COVID-19 and keep Army programs on track, he said – even if there's a new upsurge in infections nationwide. According to daily updates from Defense Contract Management Agency, Jette said, “the openings are outweighing the number of closings, and total number of closings is down significantly, so things are improving quite a bit.” Of 10,509 facilities large and small that DCMA is tracking, 248 had closed at some point — but only 40 are still closed. The number of reopenings has exceeded the number of new closings since April 20. But, I asked, what if there's another spike, whether from states relaxing shutdown orders or a change in weather come the fall? Because of the new precautions now in place, Jette told me, “I would say that in the long run, if we had some degree of a resurgence, I don't think it would be as marked as the first one.” Learning To Cope There was an initial wave of shutdowns in the first days of the pandemic, Jette said, because a single case of COVID-19 might require putting the entire workforce at a facility into quarantine, particularly at smaller companies. That wasn't a panicked reaction, but a reasonable precaution. Workers had been mingling freely in close quarters, most coronavirus carriers were asymptomatic, and virtually no reliable tests were available. A company facing a single case had no way of knowing who else might already be infected. But that's no longer true, Jette went on. Private companies and government agencies alike have now broken up large groups of workers into smaller ones, creating “bubbles” in which any contagion can be contained. “For example, in the past, one shift came in and started using the tools from the other shift,” Jette said, as one example. “Now, between shifts, a cleaning team comes in and disinfects all the tools.” Wiping down shared equipment, surfaces, and spaces is just one part of a multi-layered defense against contagion. Workers on the same shift who once all came in and out together, chatting in close quarters and shaking hands, may now arrive and leave on staggered schedules so they can stay six feet apart at all times. Workflows have been changed and workstations physically moved, where possible, to permit social distancing on the factory floor. Employees who must work side-by-side wear masks and gloves. Those precautions reduce the chance of someone catching the coronavirus in the first place – and just as important, they make it harder for one infected employee to spread the disease, especially to colleagues outside their “bubble.” So when somebody does get sick, you only need to quarantine their particular team, not shut down the whole factory. “If somebody in the bubble comes down [with COVID],” he said, “ only that bubble ends up isolated.” Even Pentagon offices like Jette's own are getting cleaned more frequently and more thoroughly, he told me, even when no one working in them has actually gotten sick. “[Even when] nobody has become infected in a particular office,” he told me, “we are having a cleaning team go through and do one office here, one office there, and just do a thorough wipe-down to make sure that there's nothing that got into that office undetected.” These precautions aren't excessively onerous, disruptive, or costly, Jette said. They're just things nobody had thought about doing before – but now they might be useful even after the pandemic is under control. “I don't see it being a significant burden on the system; it was just something we didn't see was an issue before,” he said, “[but] I may well help us have fewer flus and colds if we just continue the same practice.” Dealing With Disruption Industry may be adapting well, but a global pandemic is still extraordinarily disruptive. Like the rest of the Defense Department, the Army is closely tracking not only its prime contractors but the smaller subcontractors and sub-sub-contractors, which are much more fragile. To date, the Army has pumped $167.5 million into small businesses to help them ride out COVID disruptions. “There have been some cost implications to the government,” Jette said, “but mostly with respect to the CARES Act,” which ensures workers at facilities closed by COVID are paid instead of let go. The main way the Army has helped out companies is by making payments they already had coming, just ahead of schedule. For example, Jette said, the service has started writing checks to contractors every 15 days instead of the normal 30. It's also increasing progress payments, normally limited to 80 percent of total contract value (85 percent for small business) to 90 percent (95 for small business). “Cash flow was one of those things we concerned ourselves with,” Jette said. “Congress gave us flexibilities there. There were things passed down from OMB in the White House that gave us some flexibility as well.” To help figure out which subcontractors might be in trouble, the Army's prime contractors have opened their books and shared information with the service, far beyond anything they were contractually obligated to do, Jette said. Since the early days of the pandemic, even before shutdowns began, he's been getting a daily report on the health of subcontractors, which now routinely runs over 60 pages. “The primes ... were all very cooperative in trying to give us visibility down to the lowest level supplier,” Jette said. “It's really been helpful for us, because it helps us get a better gauge on what we have to do if something goes awry. In some cases when a subcontractor shuts down, the primes can find an alternative supplier. But despite the huge size of the defense industrial base, Jette said, there are single points of failure where only one company that's been formally qualified to build a certain part or perform a certain industrial process. It takes time to get a back-up supplier up to speed – sometimes longer than the 16.8 days that, on average, it takes a quarantined facility to reopen. That has resulted in delays, Jette acknowledges, but, so far, Army programs are finding ways to make up the time elsewhere in their schedules and still deliver new weapons to the troops on time – what's called First Unit Equipped, or FUE. “Delivery schedules on some products have slipped a little bit right...but at this point, none of them has assuredly slipped the FUE,” Jette told me. “As of right now, the vast majority of challenges that we've had with COVID, we've been able to accommodate within the current contracts with minor changes.” But the factories aren't the only part of the system that has to function. “The most significant thing isn't production,” Jette said. “It's trying to get all the testing done to make sure that all the systems work.” While some testing takes place in labs, what's most complex is operational testing, which puts a new technology in the hands of soldiers in the field to see how it works in for a real unit, interacting with all the rest of that unit's gear, conducting a realistic mission in realistic conditions. That requires bringing together not only the soldiers but technical specialists from the manufacturers, Army program offices, and Army testing organizations across the country. “Those are not simple to just change or move around, [and] that's part of what we've struggled with,” Jette said. “In some cases, we have suppliers who provide a capability and it's ready to be tested and we just don't have the facilities or the units available yet for full testing.” Officials need adequate test data before they can approve a program to start production – what's known as a Milestone C decision. But, Jette said, if you have to delay that formal approval, you can compensate by getting ready to jump-start manufacturing as soon as you have the go-ahead. The contractor can even start production ahead of Milestone C at its own risk, if it's confident that testing will not find any significant problems. At some point, it comes down to what kind of risk you're willing to take. If you rev up your manufacturing base before testing is complete, but then testing discovers a problem you have to fix, you may have to make expensive, time-consuming changes to your design, to your production process, or even to items already built. But if you wait for all the testing to get done, no matter how long it takes, you may not get the kit to troops on schedule. Unprecedented Stresses It's a difficult and stressful time; Jette can't recall anything like it in his 30 years in the defense sector. “At least based on my experience which goes back to the early '90s,” he told me, “you may have had strains on a particular vendor, [but] this is fundamentally a nationwide challenge that covers all of our programs.” “I can't think of any time where we had such a longstanding challenge to keeping programs fully operational,” he said. “Probably the closest thing,” he said, is when Congress can't pass defense funding bills on time and passes a stopgap Continuing Resolution. A CR essentially puts spending on autopilot at last year's levels with no ability to start new programs, ramp up existing ones, or cancel failing ones. Like the pandemic, a CR can impact every function of the Defense Department, or even the entire federal government, for weeks or months on end. But funding problems don't threaten the health and safety of every worker the way the pandemic does. “In this case, we have to consider the financial underpinnings, but we also have to consider the impact to the people themselves.” “Our most valuable resources are people,” Jette said. “If I don't have good people, I'm not getting good work done. I want to make sure those people want to work here, and a big piece of that is giving them a safe and healthy environment.” https://breakingdefense.com/2020/05/contractors-recovering-from-covid-shutdowns-bruce-jette/

  • Northrop Grumman Delivers 500th AN/APG-81 AESA Radar for the F-35 Lightning II

    November 8, 2019 | International, Land

    Northrop Grumman Delivers 500th AN/APG-81 AESA Radar for the F-35 Lightning II

    Baltimore - November 7, 2019 - Northrop Grumman Corporation (NYSE: NOC) has delivered its 500th AN/APG-81 fire control radar for the F-35 Lightning II. The Northrop Grumman AN/APG-81 active electronically scanned array is the cornerstone of the F-35's advanced sensor suite, providing unparalleled battlespace situational awareness that translates into platform lethality, effectiveness and survivability. “As a principal member of the Lockheed Martin-led F-35 industry team, our continued investment in facilities and equipment, production enhancements in process and design, and expanded supply chain capability through second sourcing helped reach this milestone,” said Chris Fitzpatrick, director, F-35 programs, Northrop Grumman. “The 500th delivery of this top-of-the-line fighter radar was made possible by our continuous focus on quality and excellence across our company.” The AN/APG-81 radar has long-range active and passive air-to-air and air-to-ground modes that support a wide range of demanding missions. These modes are complemented by an array of stealth features as well as electronic warfare and intelligence, surveillance and reconnaissance functions. Northrop Grumman plays a key role in the development, modernization, sustainment and production of the F-35. In addition to producing the AN/APG-81 radar, the company manufactures the center fuselage and wing skins for the aircraft, produces and maintains several sensor systems, avionics, mission systems and mission-planning software, pilot and maintainer training systems courseware, electronic warfare simulation test capability, and low-observable technologies. To learn more about Northrop Grumman's role on the F-35 Lightning II, visit this website. Northrop Grumman is a leading global security company providing innovative systems, products and solutions in autonomous systems, cyber, C4ISR, space, strike, and logistics and modernization to customers worldwide. Please visit news.northropgrumman.com and follow us on Twitter, @NGCNews, for more information. View source version on Northrop Grumman: https://news.northropgrumman.com/news/releases/northrop-grumman-delivers-500th-anapg-81-aesa-radar-for-the-f-35-lightning-ii

All news