Auditor general trashes Liberal plan to keep CF-18s flying until 2032

Murray Brewster · CBC News

Fighter pilots, technicians are in short supply for Canada's fighter jets

Canada's auditor general has shot down the Liberal government's handling of the air force's aging CF-18s in a blistering report that raises questions about national security, and even long-term safety, regarding the viability of the country's frontline fighter jets.

Auditor General Michael Ferguson's fall report, tabled Tuesday, methodically picks apart the recent policy change at the Department of National Defence, which requires the military to have enough warplanes to meet Canada's commitments to both NORAD and NATO at the same time.

From the get-go the policy was a non-starter, and the federal government knew it, said Ferguson.

"The fighter force could not meet the requirement because National Defence was already experiencing a shortage in personnel, and the CF-18 was old and increasingly hard to maintain," said the audit.

As of April 2018, the air force's CF-18 squadrons faced a 22 per cent shortage in technical positions — and a startling number of technicians were not fully qualified to do maintenance.

Fighter pilots are also in short supply. The air force is losing more of them than it is training each year; among those who do remain, almost one third do not get the required 140 hours of flying time per year.

At a news conference following the release of the report, Defence Minister Harjit Sajjan conceded that personnel shortages were identified "early on" after the Liberals took over in 2015.

"This is a problem we knew we had," he said, pointing the finger at budget cuts made by the previous Conservative government. "This is what happens when you don't put enough resources into the military."

The extent of Liberals' own efforts to boost recruiting and retention of pilots and technicians in the three years since the election was the subject of some confusion Tuesday.

A written statement from Sajjan said the government "will launch new efforts to recruit and retain pilots and technicians."

During the news conference, the minister said the military's top commander had been directed to deal with the problem and that recruiting pilots is "a priority."

Pressed for specifics on recruitment, Sajjan said he's "going to leave it to the experts to figure out."

Proposed solution 'will not help solve' issues

The auditor's report took issue with the Liberal government's strategy to fill the so-called capability gap by buying additional interim aircraft.

The current proposal is to buy used Australian F-18s — of approximately the same vintage as Canada's CF-18s — and convert them for further use until the federal government completes the purchase of brand-new aircraft.

This plan, the auditor's report said, "will not help solve either the personnel shortage or the aging fleet."

Ferguson said an earlier, $6.3 billion plan to buy 18 brand new Super Hornet fighter jets on an interim basis would have been even worse — and the government was told so in no uncertain terms by the air force.

"National Defence's analysis showed that buying the Super Hornet alone would not allow the department to meet the new operational requirement," said the audit.

"The department stated that the Super Hornet would initially decrease, not increase, the daily number of aircraft available because technicians and pilots would have to be pulled away from the CF-18s to train on the new aircraft."

The proposal to buy Super Hornets was scrapped last spring after the manufacturer, Chicago-based Boeing, angered the Trudeau government in a separate trade dispute involving the sale of Bombardier passenger jets.

The Opposition Conservatives have long claimed the 'capability gap' was concocted by the Liberals as a way to push off a decision on a permanent replacement for the CF-18s. In the last election, Prime Minister Justin Trudeau pledged not to buy the F-35 stealth fighter, the preferred option of the Harper government.

Sparring in the House

The report led to sparring in the House of Commons, with the Conservatives seeing the auditor general's assessment as vindication.

"Today's report confirms what we have been saying all along," said James Bezan, the defence critic.

"Justin Trudeau deliberately misled Canadians by manufacturing a 'capability gap' to fulfil a misguided campaign promise, and in the process has put the safety and security of Canadians at risk."

Sajjan, however, believed the report supported the government's position.

"The report confirms what we have always known: The Harper Conservatives mismanaged the fighter jet files and misled Canadians for over a decade," he said.

"The report confirms a capability gap exists, and started under the Conservatives."

In fact, what the report said was that "Canada's fighter force could not meet the government's new operational requirement." It contained objective analysis of how many aircraft would be required to meet various contingencies.

Fleet 'will become more vulnerable'

Meanwhile, the auditor is warning that the Liberal government has no plan to upgrade the combat capabilities of the CF-18s to keep them current over the next decade while the air force waits for replacements.

The last major refurbishment of the war-fighting equipment on the jets happened in 2008, and Department of National Defence planners have done little since because they had been expecting new planes by 2020.

National Defence did not have a plan to upgrade the combat capability of the CF-18 even though it will now have to fly until 2032," said the audit.

"Without these upgrades, according to the department, the CF-18 will become more vulnerable as advanced combat aircraft and air defence systems continue to be developed and used by other nations."

The fact that the CF-18s are not up to date means they will not be able to operate in certain environments where the risk of surface-to-air missiles or advanced enemy planes is great.

That, in turn, "would limit Canada's contribution to NORAD and NATO operations," Ferguson said.

Sajjan said the department is looking at an upgrade to the combat systems.

"We would love to be able to solve this problem immediately," he said.

https://www.cbc.ca/news/politics/auditor-general-trashes-liberal-plan-to-keep-cf-18s-flying-until-2032-1.4912813

On the same subject

  • $1 billion and counting: Inside Canada's troubled efforts to build new warships

    February 25, 2020 | Local, Naval

    $1 billion and counting: Inside Canada's troubled efforts to build new warships

    Federal government tables figures showing what it's spent on the projects to date Murray Brewster The federal government has spent slightly more than $1.01 billion over the last seven years on design and preparatory contracts for the navy's new frigates and supply ships — and the projects still haven't bought anything that floats. The figures, tabled recently in Parliament, represent the first comprehensive snapshot of what has been spent thus far on the frequently-delayed project to build replacement warships. It's an enormous amount of money for two programs that have been operating for more than a decade with little to show for their efforts to date. It will be years before the Canadian Surface Combatant project — which aims to replace the navy's frontline frigates with 15 state-of-the-art vessels — and the Joint Support Ship program for two replenishment vessels actually deliver warships. The numbers and details for each advance contract were produced in the House of Commons in response to written questions from the Conservative opposition. The money was divided almost evenly between the federal government's two go-to shipyards: Irving Shipbuilding in Halifax, the prime contractor for the new frigates, and Seaspan of Vancouver, the builder of the supply ships. The breakdown raises critical questions about at least one of the programs, said a defence analyst, but it also shines a light on promises made by both Liberal and Conservative governments to keep spending under control for both of these projects — which could end up costing more than $64 billion. "I think there should be a level of concern [among the public] about whether or not what's being delivered in practice is what was advertised at the outset," said Dave Perry, a procurement expert and vice president of the Canadian Global Affairs Institute. A design still in flux Most of his concerns revolve around the new support ships, which the Liberal government says are in the process of being built now. The written responses, tabled in Parliament, note that the projected cost for the two supply ships — $3.4 billion — remains under review "as the design effort finalizes." Perry said he was astonished to learn that, "seven years and half-a-billion dollars into design work on an off-the-shelf design," the navy doesn't have the support ships, even though "the middle third of the ship is built" — and officials now say "the design effort isn't finished." Usually, he said, ships are designed before they're built. The head of the Department of National Defence's materiel branch said most of the preparatory contracts were needed to re-establish a Canadian shipbuilding industry that had been allowed to wither. 'A lot of patience' "I think we have to look at the totality of everything that's being accomplished under" the national shipbuilding strategy, said Troy Crosby, assistant deputy minister of materiel at DND. "Over that period of time, and with these expenditures, we've built a shipbuilding capability on two coasts, not just through National Defence but also through the coast guard, offshore fisheries science vessels. I understand it has taken a lot of patience, I suppose, and probably some uncertainty, but we're really getting to the point now where we can see delivering these capabilities to the navy." The largest cash outlays involve what's known as definition contracts, which went individually to both shipyards and were in excess of $330 million each. They're meant to cover the supervision of the projects and — more importantly — to help convert pre-existing warship designs purchased by the federal government to Canadian standards. The choices on each project were made at different times by different governments, but ministers serving both Liberal and Conservative governments decided that going with proven, off-the-shelf designs would be faster and less expensive than building from scratch. Now, after all the delays, it's still not clear that choosing off-the-shelf designs has saved any money. "I would be completely speculating on what it would cost to invest to develop the kind of expertise and capacity inside the government, inside National Defence and everybody involved, to be able to do something like that in-house," said Crosby. "The approach we've taken at this point, by basing both the Joint Support Ship and the Canadian Surface Combatant on pre-existing designs, allows us to retire a lot of risk in the way forward." When Crosby talks about "retiring risk," he's talking about the potential for further delays and cost overruns. Among the contracts, Irving Shipbuilding was given $136 million to support the drawing up of the design tender for the new frigates and to pay for the shipbuilding advice Irving was giving the federal government throughout the bidding process. Years ago, the federal government had enough in-house expertise to dispense with private sector guidance — but almost all of that expertise was lost over the past two decades as successive federal governments cut the defence and public works branches that would have done that work. The last time Canada built major warships was in the 1990s, when the current fleet of 12 patrol frigates was inaugurated. The federal government has chosen to base its new warships on the BAE Systems Type-26 design, which has been selected by the Royal Navy and the Royal Australian Navy. The hull and propulsion system on the new frigates will be "largely unchanged" from the British design, but the combat system will be different and uniquely Canadian, said Crosby. The project is still on track to start cutting steel for the new combat ships in 2023. Crosby said he would not speculate on when the navy will take delivery of the first one. Delivery of the joint support ships is expected to be staggered, with the first one due in 2024. There will be a two-year gap between ships, said Crosby, as the navy and the yard work through any technical issues arising with the first ship. If that timeline holds, the first support ship will arrive two decades after it was first proposed and announced by the Liberal government of former prime minister Paul Martin. https://www.cbc.ca/news/politics/frigates-joint-supply-ships-navy-procurement-canada-1.5474312

  • Title Publication Date	Department	News type Teaser Minister Blair announces $40 million to provide Ukraine with artillery ammunition at the 20th meeting of the Ukraine Defense Contact Group

    March 19, 2024 | Local, Land

    Title Publication Date Department News type Teaser Minister Blair announces $40 million to provide Ukraine with artillery ammunition at the 20th meeting of the Ukraine Defense Contact Group

    Today, the Honourable Bill Blair, Minister of National Defence, participated via videoconference in the 20th Ukraine Defense Contact Group (UDCG) meeting, hosted by United States Secretary of Defense Lloyd J. Austin III.

  • Facing more advanced threats, Canada secures US$5.9B deal for up to 16 P-8A Poseidon aircraft - Skies Mag

    December 3, 2023 | Local, Aerospace

    Facing more advanced threats, Canada secures US$5.9B deal for up to 16 P-8A Poseidon aircraft - Skies Mag

    The US$5.9B deal includes 14 P-8A aircraft, with options for up to two more, as well as associated equipment, training devices, and initial sustainment.

All news