Army validates design for future helicopter engine, remains on track despite COVID

By:

WASHINGTON — The Army has validated its design for its future helicopter engine, and the program remains on schedule to deliver the first engine for testing in the fourth quarter of fiscal 2021, according to service officials in charge of the effort.

The Improved Engine Turbine Program (ITEP) has seen a long — and often delayed — journey as the service wrestled with funding and development strategies for several years. ITEP will replace current engines in both UH-60 Black Hawk utility helicopters and AH-64 Apache attack helicopters

Since awarding a contract to General Electric Aviation in February 2019, the program has pushed forward on schedule, despite a protest from a competing team comprised of Honeywell and Pratt & Whitney, which paused work for roughly three months.

And, while the Coronavirus pandemic caused some anxiety among Army officials trying to keep the program on track, those in charge were able to complete the critical design review, conducted 100 percent virtually, according to Army spokesman David Hylton.

The ITEP Critical Design Review (CDR) was a multi-month process that consisted of three phases, Hylton told Defense News in a written statement. The engine control system component CDR was completed on June 5, followed by the software CDR on July 17 and the engine systems CDR on July 24, he said.

The Army and GE are making “tremendous efforts to keep COVID-19 impacts from delaying the program,” Hylton wrote.

GE is now working toward a test readiness review ahead of the first engine test.

“We are full steam ahead in terms of understanding where we need to go next with respect to the design, Col. Gregory Fortier, who is in charge of the program office for the Army's Future Attack Reconnaissance Aircraft, said during a media briefing last month.

The Army has “no reason to believe we will not fly” in fiscal 2023, he said.

According to FY21 Army budget request justification documents, the service plans to fly an aircraft with an ITEP engine installed in the first quarter of FY23 followed by a low-rate initial production decision in the fourth quarter of FY24.

A full-rate production decision is expected in FY26.

https://www.defensenews.com/land/2020/08/12/army-validates-design-for-future-helicopter-engine-remains-on-track-despite-covid/

On the same subject

  • Why ‘Help Wanted’ In A&D Doesn’t Mean The Same Anymore

    January 10, 2022 | International, Aerospace, Naval, Land, C4ISR, Security

    Why ‘Help Wanted’ In A&D Doesn’t Mean The Same Anymore

  • Spain’s defence budget growth lags behind Nato targets

    October 3, 2024 | International, Land

    Spain’s defence budget growth lags behind Nato targets

    GlobalData's latest report indicates that Spain's defence budget will rise from $10.3bn in 2020 to $27.3bn by 2029.

  • Three shipbuilding teams shortlisted to build new warships in UK

    December 14, 2018 | International, Naval

    Three shipbuilding teams shortlisted to build new warships in UK

    Teams will receive contracts worth up to £5 million to push ahead with plans to build five new Type 31e warships. Three shipbuilding teams have been awarded multi-million-pound contracts to push ahead with plans to build five new Type 31e warships in the UK for the Royal Navy, Defence Minister Stuart Andrew has announced today in Portsmouth. The Minister revealed that teams led by BAE Systems, Babcock and Atlas Elektronik UK have been shortlisted for the competition to build the five frigates for £1.25 billion. Each group has today been awarded a contract worth up to £5 million to fund the next stage of their plans, with the preferred bidder for the design and manufacture of the ships due to announced by the end of next year. The MOD want the first ship delivered in 2023. Speaking at Her Majesty's Naval Base in Portsmouth, Defence Minister Stuart Andrew said: This is the first frigate competition the UK has run in a generation, and today we are funding three shipbuilding teams with extremely exciting concepts to continue developing their plans. Next year we will announce the winning bidder, and one of these designs will go on to bolster our future fleet with five new ships, creating UK jobs and ensuring our Royal Navy maintains a truly global presence in an increasingly uncertain world. The awarding of the contracts is a key milestone in the National Shipbuilding Strategy, which was launched in September 2017. The Strategy met the challenges set by an independent report written by Sir John Parker, a figure with a wealth of leadership and boardroom experience in shipbuilding, and was underpinned by the commitment to build the new Type 31e ships. The bold Type 31e programme will move through procurement at an unprecedented pace: the vessel will commence production within 3 years of the launch of the programme, far quicker than similar programmes of this type. The ships will make up the next generation of the Royal Navy fleet, along with eight Type 26 warships which will start being delivered from the mid-2020s. The names of all eight Type 26 frigates have now been announced, and the Defence Secretary Gavin Williamson has also outlined that they will be homed in Devonport. The decision on where the Type 31e frigates will be based is still to be made. The Minister made the announcement on-board HMS Diamond, which returned to Portsmouth last month having been in the Mediterranean. https://www.gov.uk/government/news/three-shipbuilding-teams-shortlisted-to-build-new-warships-in-uk

All news