Air Force finds new KC-46 deficiencies, jeopardizing planned delivery date

By:

WASHINGTON — The U.S. Air Force has added two new technical issues to the KC-46 tanker's list of problems, potentially throwing a wrench into the projected delivery of the first tanker in October.

The service confirmed to Defense News on Sept. 17 that both deficiencies are category-1 , the most serious designation of technical problems, and revolve around the tanker's refueling boom system.

At this point, the Air Force is unsure whether the two problems will be solved in time for KC-46 manufacturer Boeing to deliver the first tanker next month, said Air Force spokeswoman Ann Stefanek.

“Boeing and the program office are still reviewing the test data and assessing the risk and potential solutions to these deficiencies, and proceeding in parallel to aircraft delivery,” she said in a statement.

The first new deficiency, which the service has labeled “No Indication of Inadvertent Boom Loads,” refers to situations where boom operators unintentionally provide an input into the flight control stick that induces loads on the boom while it is in contact with a receiver aircraft. The KC-46 currently has no way to notify that operator that this is happening.

The second deficiency was found when pilots of receiver aircraft reported that the boom is too stiff during the part of the process when the receiver plane moves forward into the fuel transfer zone.

“We discovered these deficiencies during the course of flight testing,” Stefanek said. “As the program progresses through receiver certification testing, we are still in discovery phase with the tanker/receiver pairs. ... The test team is still writing the test reports, but submitted the DRs [deficiency reports] in advance to assist in accelerating root cause, corrective action development.”

In a statement, Boeing said that it continues to work with the Air Force to determine a path forward.

“These are not safety of flight issues and we are confident in the unmatched capabilities of the KC-46 tanker aircraft," the company said. "To date we have completed more than 4,000 contacts during flights with F-16, F/A-18, AV-8B, C-17, KC-10 and A-10 aircraft. The refueling system has been tested extensively — we have a well-tested system that works.”

The Air Force can accept tankers at its own discretion, with or without active deficiencies. However, both Boeing and the Air Force have worked under the assumption that the service will not do so until all category-1 issues have been worked out or downgraded to category-2, which signifies that a workaround has been put into place.

The news of two more deficiencies is a blow to Boeing, which had been hoping to deliver the first tanker in October after finally coming to an agreement with the Air Force earlier this year on a proposed schedule. The KC-46 program has been notoriously above cost, and Boeing's fixed-price contract with the Air Force has forced it to pay out more than $3.4 billion to cover those overruns.

It has also run years behind schedule: The company was initially slated to deliver the first 18 certified tankers by August 2017. Boeing now has until October 2018 to meet that deadline — called required assets available— but will almost surely miss it, as the Air Force does not have the resources to absorb 18 new tankers in a month.

Over the past year, Boeing has been racing to resolve three additional category-1 deficiencies. Two involve the tanker's remote vision system, or RVS, a series of cameras and sensors that allow the boom operator to direct fuel into a receiver aircraft.

Unlike legacy tanker operators, KC-46 boomers will be unable to look out a window in order to see the refueling process happen — making them entirely reliant on the RVS. However, certain lighting conditions make it difficult to see the receiver aircraft's receptacle, leading to incidents where the boom has scraped the plane being refueled.

To fix the issue, Boeing has developed and tested a fix to the RVS' software. The Air Force is currently reviewing that data, and both RVS-related deficiencies are still in effect.

The final issue involves the system centerline drogue system, which has a mechanical lock that sometimes inadvertently disconnects during a refueling. Boeing plans to create a software fix to ameliorate that problem, too, but it remains a category-1 deficiency.

https://www.defensenews.com/breaking-news/2018/09/17/air-force-finds-new-kc-46-deficiencies-putting-planned-delivery-date-in-jeopardy

On the same subject

  • Congress skeptical of Navy’s unmanned vessels plans

    July 16, 2020 | International, Naval

    Congress skeptical of Navy’s unmanned vessels plans

    Nathan Strout The U.S. Navy wants $464 million for unmanned surface vessels, but Congress is not on the same page. Legislators have so far declined to fully fund the massive investment into research and development for large and medium unmanned surface vessels as they work through the annual defense bill, citing the request as “excessive procurement ahead of satisfactory testing.” Among other things, that budget request would give the Navy $239 million to purchase two Overlord large unmanned surface vehicle (LUSV) prototypes for testing. While the Senate Armed Services Committee has declined to authorize any of the $464 million request, the House Armed Services Committee agreed to authorize just $270 million of that request — specifically cutting funding for the two LUSVs. Instead, the House version would provide the Navy $45 million to convert a Spearhead-class expeditionary fast transport ship into a LUSV for further testing. In a report on the bill issued by the Senate Armed Services Committee, lawmakers argued that the Navy already has the LUSVs that can fill the Strategic Capabilities Office's needs in this area. But perhaps more importantly, the committee members do not seem convinced that LUSVs are ready for prime time. “The committee remains concerned that the budget request's concurrent approach to LUSV design, technology development, and integration as well as a limited understanding of the LUSV concept of employment, requirements, and reliability for envisioned missions pose excessive acquisition risk for additional LUSV procurement in fiscal year 2021,” the report reads. “The committee is also concerned by the unclear policy implications of LUSVs, including ill-defined international unmanned surface vessel standards and the legal status of armed or potentially armed LUSVs.” Furthermore, legislators remain unconvinced that the current unmanned vessels can hold up to the physical environment of extended operations at sea. While the Navy requires its unmanned platforms to be able to operate continuously at sea for 30 days without maintenance or repairs, the committee report notes the Strategic Capabilities Office's prototypes have only demonstrated two to three days of continuous operation. The Senate version of the bill would require the Navy to formally qualify two main engines and electrical generators — including successfully demonstrating 30 days of continuous operations at sea — before Milestone B approval is granted. An industry group hit back July 9. In a letter to leaders of the Senate and House Armed Services Committees, the Association for Unmanned Vehicle Systems International called on legislators to fully fund the Navy's fiscal 2021 request. “It is imperative that Congress continues to fund the research and development (R&D) efforts included in the Navy's FY21 budget request,” wrote President and CEO Brian Wynne. “Failing to do so will disrupt the significant investment industry has made in unmanned systems over the last several years. The severe reduction in funding being considered in the FY21 NDAA would eliminate jobs, drive many small companies out of business, and cause larger companies to shift their R&D investments to more stable opportunities” The committee report argues that its requirements do not delay these programs, but in fact will enable the delivery of unmanned surface vehicles faster by ensuring they are “capable, reliable and sustainable.” In the meantime, the Navy has moved forward with its unmanned surface vehicle efforts. On July 13, the Navy awarded L3Harris $35 million to develop a medium unmanned surface vehicle prototype, with an option to buy eight more later on. If all options are exercised, the contract could be worth up to $294 million. “The award of Medium USV is the culmination of a great dialogue with industry to right-size the requirements for a capable, reliable, and affordable unmanned surface vehicle that will employ a variety of modular payloads,” said Capt. Pete Small, program manager of Unmanned Maritime Systems within the Unmanned and Small Combatants Program Executive Office. “Leveraging new rapid prototyping authorities and mature commercial technology will allow us to quickly deliver a capable prototype to the Surface Development Squadron to conduct experimentation and learning in support of the Navy's plans for a future fleet incorporating unmanned vessels.” The prototype is expected to be delivered in fiscal 2023. However, the Navy press release announcing the award notes that funding for future MUSV prototypes is uncertain. While the Navy has asked for additional fiscal 2021 funding for a second MUSV prototype in fiscal 2023, that acquisition strategy is yet to be determined. https://www.c4isrnet.com/unmanned/2020/07/15/congress-skeptical-of-navys-unmanned-vessels-plans/

  • New tropical boots coming by the end of 2019

    September 6, 2019 | International, Naval

    New tropical boots coming by the end of 2019

    By: Shawn Snow The Corps' new tropical boots may be on the feet of some Marines by the end of 2019, according to Marine officials. The Corps awarded two contracts on Aug. 29 for up to 140,000 total pairs of two styles of tropical boots, according to Maj. Ken Kunze, a spokesman for Marine Corps Systems Command. Kunze said one contract was awarded to ADS Inc. for a maximum order of 70,000 pairs of the Rocky brand tropical boot. That contract award was valued at $11.1 million dollars, Kunze said. Another contract was awarded to Provengo LLC for 70,000 pairs of the Danner brand tropical boot, with a contract valued at $13.7 million, according to Kunze. Kunze said the initial order for the new tropical boots is being procured in September and they should start arriving in 60 days to 90 days. The boots have gone through rigorous training during the past several years. In 2017, Marines with 3rd Battalion, 3rd Marines, evaluated three tropical boot prototypes from boot manufacturers Danner, Bates and Rocky while training in a jungle environment. The new boots will not be part of a Marine's general seabag issue. The boots are headed for the for the Consolidated Storage Program, and will be issued to Marines in predeployment training before heading to a hot or tropical climate, Manny Pacheco, a spokesman for Marine Corps Systems Command, previously told Marine Corps Times. https://www.marinecorpstimes.com/news/your-marine-corps/2019/09/05/new-tropical-boots-coming-by-the-end-of-2019

  • Joint venture with Ukrainian partner: Rheinmetall to produce artillery ammunition in Ukraine

    February 19, 2024 | International, Land

    Joint venture with Ukrainian partner: Rheinmetall to produce artillery ammunition in Ukraine

    The MoU was signed in the presence of Alexander Kamyshin, the Ukrainian Minister for Strategic Industries, during the Munich Security Conference.

All news