A quiet Hunter - Navy's Future Frigate

Valued at $35 billion over its program life, Navy's Future Frigate project, Sea 5000 Phase 1, is second only to Future Submarine in terms of cost to the Australian taxpayer.

Navy will receive nine Hunter class frigates, built in South Australia to BAE System's Global Combat Ship (GCS) design and, although optimised for the Anti-Submarine Warfare (ASW) role, they are intended to be equally adept at Air Warfare and a number of other roles.

A number of sovereign features will separate the Hunter variant of the GCS from the UK's City class ASW frigates (Type 26), including integration of CEA Technologies' new generation CEAFAR2 radar, Lockheed Martin's Aegis Combat System and an Australian tactical interface developed by Saab Australia.

The program calls for steel to be cut on the first vessel in Osborne in late 2022 with the lead ship, HMAS Flinders, launched in the 2027-2028 timeframe and entering service between 2029 and 2031.

The nine ships form part of the Commonwealth's Continuous Naval Shipbuilding Strategy and will be built in three flights of three vessels, to ensure the design keeps abreast of rapidly evolving technology. Completion of the last frigate is not due to occur until the early 2040s and the class will form the backbone of Navy's major surface combatant fleet for decades to come.

The Hunter class will follow the Type 26 by around five years and will benefit from lessons learned during completion of at least the first two ships, before Flinders enters the water towards the end of the next decade.

The GCS design has been touted as the world's most capable ASW ship and in Royal Navy service it will be the successor to the Duke class (Type 23) frigates, long regarded as the benchmark in the domain. BAE Systems has also sold the design to Canada, where it will be known as the Canadian Surface Combatant (CSC) and the family now includes no fewer than 32 ships across three of the world's leading navies, all members of the Five Eyes community.

The good news for Australian taxpayers, at this early stage at least, is that Sea 5000 remains on schedule for the first steel to be cut at Osborne in 2022. Around 50 per cent of the first UK ship, HMS Glasgow, is now in production and steel was cut on the second, HMS Cardiff, in early August.

Acquiring the Future Frigate
The Future Frigate competition was fiercely fought by BAE Systems, with a version of the Global Combat Ship referred to within the company as GCS-A (Australia); Fincantieri, with a version of the ASW-optimised Fregata Europa Multi-Missione (FREMM) frigate in service with the Italian Navy; and Navantia, with an evolution of its F105 design (which forms the basis of Australia's Hobart class destroyers), known as the F-5000.

Following the release of a Request For Tender (RFT) in March 2017 the three shipbuilders submitted bids in August 2017 and each design was then subjected to a rigorous Competitive Evaluation Process (CEP).

At the RFT release, then Minister for Defence Industry Christopher Pyne made it clear that all nine frigates would be built in an Australian shipyard, using an Australian workforce. Furthermore, he stipulated each of the three shipbuilders would be required to demonstrate their ability and willingness to develop a local supply chain to support the shipbuilding enterprise. In addition, each was required to provide local industry with opportunities to bid into their existing global supply chains.

From a capability standpoint, the Commonwealth mandated the CEAFAR2 radar, a next generation radar based upon the highly successful CEAFAR fitted to post Anti-Ship Missile Defence (ASMD) Anzac frigates. In October 2017 then Prime Minister Malcolm Turnbull also announced that Aegis, together with an Australian tactical interface, would be mandatory for all future major surface combatants.

BAE System's GCS-A proposal was formally announced as the preferred tenderer on June 29, 2018, at which time it was also revealed the nine ships would henceforth be known as the Hunter class. The first three ships of the Hunter class will carry the names of three major Australian regions, all with strong historical maritime and naval ties. HMA Ships Flinders (II) (SA region named for explorer Captain Matthew Flinders - first circumnavigation of Australia and identified it as a continent); Hunter (NSW region named for Vice-Admiral John Hunter – first fleet Captain and 2nd Governor of NSW); and Tasman (state and sea named for explorer Abel Tasman – first known European explorer to reach Tasmania, NZ and Fiji).

When announcing the GCS-A as the preferred design, then Defence Minister Marise Payne said the GCS-A design was selected because it represented the most capable ASW platform.

“This is decision based entirely on capability; the best capability to equip Navy in Anti-Submarine Warfare, with range and endurance to operate either independently or as part of a task group,” she said.


Payne also revealed that government-owned ASC Shipbuilding would become a subsidiary of BAE Systems during the Hunter class build program, with the Commonwealth owning a sovereign share in the entity but reverting to government ownership at the end of the project.

“We were really pleased with that as an outcome, because ASC has great capability. We always wanted to use the workforce, but this allows us to join ASC and BAE together much earlier and we think that will be very positive,” explained BAE Systems' then Global Maritime Systems business development director, Nigel Stewart.

“We cut steel for the first Type 26 in the UK in June 2017 and we'll cut steel for full production of the Hunter class in 2022.”

On October 5, 2018, the Commonwealth signed an interim Advanced Work Arrangement (AWA), with BAE Systems Australia to enable the company to continue with workforce mobilisation activities. This contract also represented the initial step towards transitioning ASC Shipbuilding into BAE Systems for the duration of the Hunter project.

The Head Contract between ASC Shipbuilding, as the prime contractor, and the Commonwealth was signed at Osborne on December 14, 2018, at which time the government estimated Sea 5000 would contribute around $17 billion to the national economy and have create over 6,300 jobs by the program's peak in 2028.

Speaking in late August, Craig Lockhart, ASC Shipbuilding's managing director, said the build program is currently on track.

“We're exactly where we thought we would be in the program, bang on schedule, after coming through the preferred tenderer announcement in June 2018, to achieve contract signature in December – something I believe is a gold standard in terms of negotiation between the Commonwealth and industry,” he said to ADM.

“We signed the contract in December 2018 and we're really only eight months into the program, but we've mobilised very rapidly. We have over 400 people in the Hunter program right now and we have 50 people seconded to the UK Type 26 team in Glasgow, both managing the evolution of the design maturity and managing the transfer of technology from Glasgow over to ASC Shipbuilding.”

Global Combat Ship heritage
According to the Royal Navy, the Type 26 is designed “without compromise” to excel in the ASW role, as a successor to the Type 23 frigates. The UK Government announced in the 2015 Strategic Defence and Security Review (SDSR) that it would acquire eight ‘advanced ASW ships' and in 2017, BAE Systems was awarded a ₤3.7 billion contract for the construction of the first three ships.

Plate steel for the appropriately named HMS Glasgow was cut at BAE's shipyard in Govan, on the banks of the River Clyde on July 20, 2017 and is due to enter the water in the 2019-2020 timeframe, prior to entering service in the middle of the decade.

HMS Cardiff will enter the water about two years behind her sister ship and the first steel for her was cut at Govan on August 14. A UK Government decision on the second batch of five ships is expected around the time Glasgow is launched.

The UK ships are 149 metres long, with a beam of 20.8 metres and displace around 6,900 tonnes. A standard crew will comprise 157 personnel, including an embarked aviation element, but the ship has enough accommodation space to embark up to 208 people.

According to BAE Systems the frigate is ‘an advanced ASW warship designed for the critical protection of the Continuous At Sea Deterrent and Carrier Strike Group'. In simple terms, this translates to providing protection for the Royal Navy's nuclear submarine deterrent force (currently Vanguard and later Dreadnought class boats) and the two new 65,000-tonne Queen Elizabeth class aircraft carriers.

With ASW as their primary role, signature management is a very important consideration and every component within the ship is designed with this philosophy in mind. Its primary ASW sensors will be an upgraded version of Thales' 2087 towed array low frequency active and passive sonar, which is the subject of ‘de-risking' activities aboard a Type 23 vessel, and a hull-mounted Ultra Electronics Type 2150 hull-mounted sonar system.

In day to day submarine warfare operations, the ships' sonar will be combined with sensors aboard the Royal Navy's embarked AgustaWestland Merlin HMA.2 ASW helicopters. Each Type 26 ship can carry a single Merlin, but the flight deck on the stern is able to accommodate even larger helicopters, including the Boeing CH-47 Chinook heavy-lift helicopter.

A large multi-purpose integrated mission bay forward of the helicopter hangar can be used for a number of roles, including carriage of small watercraft and unmanned aerial, surface or undersea vehicles.

The UKs Type 26 ships will also come with a formidable air defence capability, for which the primary sensor is BAE Systems' Type 997 Artisan 3D medium-range air and surface surveillance radar. Principal effectors will be the MBDA Sea Ceptor missile defence system, launched from Mk.48 cannisters, and BAE Systems Mk.45 Mod.4 5-inch medium calibre gun, but the ships also have 24 Mk.41 Vertical Launch System (VLS) cells for other weapons.

Propulsion is a combined diesel-electric or gas (CODLOG) system based around the Rolls-Royce MT30 Marine Gas Turbine. Brochure figures claim a maximum speed in excess of 27 knots and a range of more than 7,000 nautical miles in electric motor-drive.

An Australian Hunter

The changes to the Type 26 reference design which define the GCS-A or Hunter class are largely confined to the ship's weapons and sensor systems, including substitution of the Artisan air surveillance radar with CEAFAR2 and Aegis combat system. Other changes will include increasing the number of Mk.41 VLS cells, reconfiguration of the ship's aviation capabilities to allow embarkation of the Navy's Sikorsky MH-60R Seahawk helicopter, and the integration of Harris Corporation's Hawklink Ku-band data link, as used by US Navy major surface combatants.

Australia's Hunter class ships will be easily identifiable by their unique mast configuration, which is being redesigned to take the CEAFAR radar into consideration, together with the integration of Hawklink and other sensors and communications systems.

“The Artisan radar of the UK's Type 26 is different to that of Hunter, so the approach to positioning the masts with CEAFAR radar needs careful consideration. The CEAFAR radar is heavier and has a higher power requirement, so it will require a more considered integration,” explained ASC Shipbuilding's Craig Lockhart.

“So, we're changing the mast structure and moving some UK-specific technology out in favour of Hawklink and other systems, which will allow Hunter to enjoy a much broader interoperability with partners and allies.

“The communications masts are provided by Rohde and Schwartz and again are subject to trade studies to consider their interoperability with the Hunter configuration.”

ASC Shipbuilding has created a mast working group within the integrated design team to study solutions, which may result in a different solution to mounting, structure and materials being used.

Because the CEAFAR radar is significantly more powerful than Artisan, the Hunter design will also require modifications to the heating, ventilation and cooling (HVAC) and spatial management.

“It produces more heat in certain modes, so it requires improved cooling management and at the same time it's heavier, so stability and displacement is being modelled,” Lockhart added.

“It's well within our design parameters, but the biggest challenge will be making sure the dynamics of the ships' power system work as well as planned and we can supply enough capacity to all parts of the ship.

“Whilst we're completely confident that the generating capacity is more than enough, we are making sure we model the system is such a way that we don't dilute the power supply to other parts of the platform – even when we need to operate the radar in conjunction with all the other platform and weapons systems.”

Other topside changes to the basic design will include removal of the forward Sea Ceptor silo and an increase in the number of Mk.41 VLS cells from 24 to 32, which will accommodate the Raytheon RIM-162 Evolved Sea Sparrow Missile (ESSM) and Standard Missile 2 (SM-2) weapons currently used by the RAN and its US ally.


Further aft, two four-cell missile launchers will be added for either the Navy's current anti-surface Boeing RGM-84 Block II weapon or, more likely, an advanced surface to surface missile which will be acquired in the future to replace the venerable Harpoon.

Combat system
As noted earlier, the announcement by government in October 2017 that it would mandate the Combat Management System enterprise across Navy's future major surface combatants, has resulted in Lockheed Martin being selected to supply its Aegis Combat System, with Saab Australia providing the sovereign tactical interface. Together with a common Co-operative Engagement (CEC) capability across the future fleet and standardised ESSM & SM-2 weapons, Hunter will enjoy close integration with US surface combatants.

The ship's aviation facilities will also be modified to accommodate the MH-60R, which will be Navy's primary combat helicopter for many years to come. These changes include the reconfiguration of the hangar bay itself, an Aircraft Ship Integrated Secure and Traverse (ASIST) track-mounted helicopter recovery system, which is currently also being fitted to the Hobart class Air Warfare Destroyers, and changes to the ship's air weapons magazine to accommodate the MH-60Rs Mk.54 torpedo and Lockheed Martin AGM-114N Hellfire missiles.

In RAN service, the standard ship's complement (with an embarked aviation element) will be 180 personnel, but the design still permits this number to grow to 208 if required.

Other modifications may be required as the detailed design of the Hunter evolves to incorporate future capabilities. One example of this is the Unmanned Aerial System (UAS) being acquired under Navy's Sea 129 Phase 5 (Maritime Tactical UAS) program, which may select a fixed wing or a rotary wing platform, or maybe even both.

“As we continue with the maturation of the final design process, part of our discussions with the Commonwealth – and with the various capability development groups in particular – is getting a detailed understanding of the through life upgrades they either have in the pipeline, or are considering as options,” Lockhart explained.

“We are looking at what's being done in other Navy upgrade programs such as the ASMD configuration changes that have been made to the Anzac class frigates and the aviation upgrades we've just completed on the Hobart Class. All of those are being assessed against the Hunter design space and we're taking as much opportunity as we can to de-risk the build program by making sure we have enough people in the upgrade programs of other platforms that we can transfer that thinking, learning and skills across.

“We're taking every opportunity to consider their relevance to Hunter, either as a design or build strategy, or as a through-life management consideration.”

Build in Australia
The planned drumbeat for shipbuilding at Osborne will see a little over three years between the start of work on HMAS Flinders in 2022 and that of the second ship (HMAS Hunter), reducing to two years between Hunter and the third ship (HMAS Tasman). This will progressively reduce throughout the build, resulting in an estimated gap of just 18 months between the eighth and ninth ship in the late 2030s or early 2040s.

But before construction can begin, a new digitally-enabled shipyard at Osborne South has to be completed, having been built from the ground up to be (arguably) the world's most advanced naval shipbuilding facility.

Construction of the new facility was announced as part of the government's continuous naval shipbuilding strategy, under a $535 million contract with Australian Naval Infrastructure (ANI) – see P44 for more on ANI. Progress on the facility is progressing to schedule and ASC Shipbuilding hopes to begin gaining access to the yard in March 2020.

“I walked through the shipyard yesterday and it's coming along quickly, they were putting the last side section on the main, 50-metre high, final assembly building and then the roof structure goes on,” Lockhart said on August 28.

“The key challenge is for us to get in early and integrate what I call the ‘shipyard production process' within the infrastructure. We'll get progressive access from March next year and we're on target for a successful handover in the middle of next year – and by then we'll have tested a large part of our digital production processes.

“We are setting up a highly efficient, digitalised shipyard and when we get our hands on it – certainly over the next few years – we'll have the world's most advanced shipbuilding facilities.”

Fully digital design
The Global Combat Ship itself has now migrated to a fully digital design, which provides BAE Systems with the capability to embed all aspects of the design and supply chain, right down to single fasteners. This design is controlled from a single configuration, which is updated at midnight every night.

However, this live design concept will prove a challenge in the future when the Hunter is itself a mature design and therefore achieves ‘separation' from the reference ship. This will be further exacerbated when the third variant (the Canadian Surface Combatant) reaches the threshold level of design maturity and the concept will require careful configuration management going forward.

“That configuration management process is what our engineering teams are working on right now, so when something is changed on Type 26 that has a platform implication on Hunter (or CSC), how will it be updated in the parts of the design that are common and still managed that live 3D configuration?” Lockhart said. “But it's a huge step forward for design evolution (and) it's a huge step forward for BAE Systems also and I think our customers are already seeing the benefit of managing data on a real-time basis.”

The Hunter design process has recently successfully achieved the Systems Readiness Requirements (SRR) milestone. Craig Lockhart said the review made 42 recommendations – fewer than the Type 26 design at a similar stage and reflecting the growing maturity of the GCS family design.

“Each of the recommendation categories were things that we were already actively working on with the Commonwealth and they were all broadly related to the changes above the main deck,” he said. “Things like, how is the radar going to interface with the rest of the ship? It has a very high power consumption, so modelling the power dynamics is a key characteristic we have to get our heads around. Also, things like, how is Aegis being delivered through the Foreign Military Sales (FMS) agreement? How well will it integrate with parts of the CMS such as guns, sensors, sonar, coms etc?”

The next major milestone will be a System Design Review (SDR), to be conducted in the fourth quarter of 2020 and which will be a major test of Hunter design maturity.

2020 cut steel
From a manufacturing process standpoint, ASC Shipbuilding will begin the construction of five hull blocks in December 2020, as a prototyping exercise to both verify capability but, more importantly perhaps, to test the digital production process at the shipyard.


The first block to be completed will be to the baseline Type 26 design which, thanks to the lead in fabrication by BAE Systems in Glasgow, can be readily quantified. The following blocks will be to the Hunter design and together they will be used to train the local workforce in South Australia, verify the skills balance and qualify the shipyard itself.
“Prototyping is a reason to test the end to end process. People think that it is about just making sure we can cut steel and weld it together,” Lockhart said. “It's not. It's a test of the design itself; it's a test of the design in the supply chain, to make sure we have the materials available when we need them; It's a test that we have design guidance information that is relevant; It's a test of the ability to produce an accurate digital work order for the relevant trades; it's the ability to schedule at the right time. It really is the ability to test without the fear of it going wrong – I'd rather have it go wrong and have the ability to appraise, amend and improve through prototyping.”

ASC Shipbuilding has already begun work on prototyping, long before steel is cut on the first hull block at the end of 2020 and is now actively engaged with local South Australian companies to work on the development of the digital work order process.

AIC and the Australian supply chain
Local industry was invited to bid for work in the prototyping phase of the Sea 5000 build program in late June, with an estimated $20 million in contracts up for grabs, but in the meantime Australian small to medium enterprises (SMEs) are already winning work supplying components and services to BAE System's GCS supply chain.

On July 9 for example, Defence Minister Linda Reynolds used a visit to BAE System's Govan shipyard to announce that Adelaide-based Airspeed had become the latest Australian SME to win work on the GCS program.

Airspeed will provide the Replenishment At Sea (RAS) ‘stump mast' for the Royal Navy's first three ships between now and 2023. Minister Reynolds noted that Airspeed was the second supplier from South Australia to join a number of Australian companies already working on the program, including CBG Systems (Moonraker), Electro Optic Systems, Liferaft Systems Australia, Mackay Consolidated Rubber, Rowlands Metalworks and prime, Thales Australia.

BAE Systems has broken the supply chain down into four categories: Categories A & B are large subsystems, such as propulsion systems, drive train, shaft line etc; Category C covers the supply of smaller components such as pumps and valves, pipes and fittings; and Category D covers the supply of services, such as paint, scaffolding etc.

“We have hard targets for Categories C & D to maximise what is delivered from the Australian supply chain component, but equally we are working with Category A & B suppliers to provide opportunities, with some notable successes,” Lockhart explained.

“We're working with companies including Rolls-Royce, MTU, Penske Power Systems etc. to bring work onshore to Australia. We're working hard with Rolls-Royce in particular to transition to a fully onshore solution over the course of the program and we're working to bring even more auxiliary component supply onshore as well.

“We're looking to use companies like Marand to supply into Rolls-Royce and to position Australian industry to sell into companies like Rolls-Royce, General Electric and Naval Group – these are all companies where we're well advanced in terms of their supply chain commitments, but also their commitment to help us deliver Australian Industry Content (AIC) and that's been well-received.”

A further opportunity for local industry participation will come with the development of a ‘Cruiser in a Cornfield' land-based test facility to test the CEAFAR2 radar, Aegis combat system and other sensors in an integrated environment and which is part of the de-risking activity for the Hunter program. ADM understands that ASC Shipbuilding is currently working with the Commonwealth to develop proposals for the design and construction of the facility, which will also be used throughout the life of the ship in the development of future upgrades under the Ship Zero concept – see P36 for more on this.

ASC Shipbuilding already has 900 local suppliers signed up through its Supply Chain Qualification Initiative, with around 450 in SA, 150 in WA and the remainder distributed throughout the country. The first Expressions of Interest – in support of the $20 million prototyping activity - are due to be released before the end of this year. Seven indigenous suppliers are already on the company's books and have benefited from mentoring to ensure they are ready to supply into the defence contracting environment, but the biggest challenge faced by the prospective supply chain, according to Lockhart, is cybersecurity.

“I think that's an unsighted challenge within the supply chain and one that will come with some cost and effort,” he said. “As BAE Systems and ASC Shipbuilding, we have to provide the customer with an assurance that when this platform comes together, the whole platform is cyber-accredited - and that inevitably flows through the supply chains. That's probably the challenge that will test us hardest.”

CSC and future sales
The Canadian Government originally selected the GCS design as the basis for its future Canadian Surface Combatant vessel in October 2018 and upheld its selection February this year, following a lawsuit brought on by one of the losing bidders.

Canada will acquire 15 ships, to be built locally by Irving Shipbuilding at its yard in Halifax, Nova Scotia under a C$45 billion deal to replace the Royal Canadian Navy's current fleet of 12 Halifax class and three Iroquois class destroyers. The prime contractor will be Lockheed Martin Canada, in partnership with BAE Systems, CAE, L3 technologies, MDA and Ultra Electronics and the first steel is expected to be cut in the early 2020s.

This brings the GCS order book to 32 units (eight for the UK, nine for Australia and 15 for Canada) across three variants and the mass of the combined order provides additional supply chain opportunities within the three countries.

BAE Systems has already formed a GCS user group community with the three governments and three navies involved to look at a range of common issues, including supply chain management.

“BAE Systems negotiating with a supplier with a 32-ship proposition perspective is a much more advantageous position to be in, rather than individual customers ordering in small batches,” Lockhart said. “The other thing is that it really gives the supply chain some long-term certainty and the ability to make investments.”

The prospect of increasing the GCS family further is also promising in the near term, with countries like Japan embarking on ASW frigate replacement programs. The Royal NZ Navy will also need to begin replacing its two Anzac frigates in the mid-2030s, despite their current upgrade program.

ADM is also watching the US FFG(X) program closely, with the possibility that it will be rescoped and rescheduled in the future. The Hunter class ship, with its pedigree of ASW capability, together with its state-of-the-art CEAFAR radar, US Aegis combat system, Hawklink datalink, CEC capability and US weapons, would arguably make a compelling reference design, should the US Navy seek alternatives to FFG(X) in its current form.

“This ship will be the most modern advanced ASW frigate in the water. The reason it won against its competitors was the unique capabilities it offered the UK, Australia and Canada for the roles that they require,” Craig Lockhart said.

“Hunter has the ability to operate as part of a global task force and it will have an interoperability with the US that is an advance of Type 26 and, as far as the CEAFAR radar is concerned, this is a very capable radar that is drawing the attention of the world's superpowers.”

https://www.australiandefence.com.au/news/a-quiet-hunter-navy-s-future-frigate


On the same subject

  • House panel unveils $674.6B Pentagon spending bill

    June 11, 2018 | International, Aerospace, Naval, Land, C4ISR, Security

    House panel unveils $674.6B Pentagon spending bill

    BY REBECCA KHEEL - 06/06/18 12:39 PM EDT The House Appropriations Committee on Wednesday unveiled its $674.6 billion Pentagon spending bill for fiscal 2019. The bill would provide $606.5 billion in base discretionary funding, which is about $900 million less than the Trump administration requested but $17.1 billion more than this year's spending level. The bill would also provide $68.1 billion for a war fund known as the Overseas Contingency Operations (OCO) account. “With the changing global dynamics and ever-growing threats to our security, it is absolutely imperative that our military is properly trained, equipped and fully supported in order to do their jobs,” Appropriations Committee Chairman Rodney Frelinghuysen (R-N.J.) said in a statement. “This legislation does all of this by including robust funding for our troops, the defense programs and activities necessary to accomplish our national goals and ideals, and to continue to rebuild our military.” The money would pay for a boost of 15,600 troops across the military and a 2.6 percent pay raise for service members, both matching what was requested by the administration. The bill would also provide $145.7 billion for equipment purchases and upgrades. That's split $133 billion for base requirements — or $2.5 billion more than requested — and $12.7 billion in OCO. The procurement money includes $22.7 billion for 12 new Navy ships, two more ships than the administration requested. The two extra ships are littoral combat ships, which Congress continues to support buying — despite the Navy's plan to transition away from the ship — so that shipyards keep working and will be able to keep pace on future orders. The bill would also fund a slew of aircraft, including $9.4 billion for 93 F-35 fighter jets and $1.9 billion for 24 F/A-18E/F Super Hornet aircraft. The bill includes funding for the procurement of 16 more F-35s than requested. The plane is built by Lockheed Martin in defense appropriations subcommittee Chairwoman Kay Granger's (R-Texas) district. Granger said the bill is an extension of last year's efforts to address readiness shortfalls. “It is a product of countless meetings and briefings with our military leaders and demonstrates our commitment to ensuring the U.S. military is the strongest, most capable military in the world,” she said in a statement. “Our military must have the resources it needs to respond to and deter threats from countries like Russia, China, Iran and North Korea, and also counter violent extremists throughout the world.” http://thehill.com/policy/defense/391001-house-panel-unveils-6746b-pentagon-spending-bill

  • Can the Army secure an American-made quadcopter?

    September 18, 2019 | International, Aerospace

    Can the Army secure an American-made quadcopter?

    By: Kelsey D. Atherton In a nondescript parking lot in Andover, Massachusetts, outside an aggressively generic office building, I am piloting an InstantEye quadcopter gently over the Merrimack River. At around 300 feet above the ground, I can no longer hear its rotors or make out its roughly basketball-sized body against the bright sky. With a press of a button and a slight change in angle, the InstantEye MK-2 turns and moves its camera to the porch where I am standing. The shade hides us a little, but after pressing another button the infrared camera identifies several bodies. If I was not piloting the drone, I would have no idea it was out there, looking at me. In recent years, the quadcopter has moved from a hobbyist toy that might see battlefield use to a dedicated family of drones at hobbyist, commercial and military levels. They all aim to provide roughly the same advantage: an unobtrusive eye in the sky, priced cheaply enough to replace easily if lost. That hobbyist drones have been adapted by uniformed militaries and nonstate actors into bomb-dropping threats is a natural outgrowth of technology cheap enough to make expendable. Now the Army wants to take advantage of this paradigm shift. “The UAS asset should be designed to be a vertical takeoff and landing (VTOL) aircraft that is rapidly deployable in austere, harsh environments,” read an Army solicitation posted in April 2019 to the FedBizOpps website. Besides VTOL, the Army wanted a drone with a camera payload, providing electro-optical/infrared radar video on a stable gimbal. It is the kind of capability that an officer could likely pick up for a few hundred dollars at the Pentagon City Mall. The future of tactical war likely looks like what happened with quadcopters: commercial technology cheap and useful enough to be adapted to military ends. But the drone market is compounded by one fact: the majority of hobbyist drones and their components are built in China, and working outside that market means foregoing much of the cost savings that make quadcopters so attractive. “We paint a large portion of the intelligence picture with minimal risk to men and equipment. What may take a scout team a day to do, may only take three hours for us,” Sgt. Christopher Curley, an Army SUAS master trainer, said in 2018. “The quadcopter is a great tool for quick recon. I relate it to fishing; you cast your reel, check that area and then move on.” Curley's suite of drones included the longer-range fixed-wing Ravens and Pumas, built to military specifications. Combined, the set of small drones can gather up to 60 percent of intelligence in training exercises. When it came to the quadcopters, Curley's unit relied on off-the-shelf drones. The Army is already training for a future where military quadcopters are ubiquitous. But to get there, it's had to rely heavily on commercial products. The phantom of the ops era “We don't market our products toward military use, nor we do sell direct to commercial or industrial users,” said Michael Oldenburg, a spokesman for DJI North America. DJI's drones have become ubiquitous in the civilian world and ever-present in military use, both formal and informal, as one of the simplest, cheapest ways to put a camera in the sky. All this even though DJI never intended to be a military contractor, and largely shies away from that role. Formally Da Jiang Innovations, the China-based firm was founded in 2006 as a company that made components for remote-control hobbyists. The DJI as we know it today starts in 2013, with the release of the ready-to-fly out of the box Phantom quadcopter. In the six years since the Phantom's release, DJI-produced drones have shown up on battlefields in Ukraine and Iraq. None of this was intended; after footage was released of a DJI Mavic releasing bombs in Ukraine, the company said “DJI strongly deplores any attempts to use our drones to cause harm; we build our products for peaceful purposes.” That DJI looms so large over the military quadcopter market is a second-order effect of the company's market share in the civilian world. A 2018 survey by Skylogic Research (funded, in part, by DJI) estimated that the company owned 74 percent of the hobbyist drone market, a figure that climbed to 86 percent when considering drones that cost $1,000 - $1,999. How extensively has the Pentagon used these drones? DJI said it only offers its products through resellers and so doesn't track what gets purchased by who and only learns about any military acquisitions after the fact. But it is possible to infer the extent of DJI drone use by the agencies within the Pentagon that have explicitly banned the company's products. Consider the fact that the Army issued an order in August 2017 for soldiers to stop using DJI-made drones, which hit communities as diverse as public affairs officers and special operators. Acquisition requests from 2017 show that the Army purchased everything from Phantom 3 quadcopters to Mavic quadcopters to Matrice 600 hexacopters, all made by DJI. A 2018 memo from the Deputy Secretary of Defense suspended all purchases of commercial off-the-shelf (COTS) drones, with an exception available by waiver. In May, Sen. Chris Murphy, D-Conn., boasted of a provision in the annual defense policy bill that specifically bans the Pentagon from purchasing drones made by a designated “strategic competitor,” primarily China. “We are okay with our products not meeting all of the needs of the DoD,” Oldenburg said. “They're not MilSpec; they're not designed to be used in the field of war or by any military organization that is conducting sensitive missions. We've never made that claim.” Robotic boom, robotic bust To understand how the Pentagon repeatedly found itself buying drones made outside the United States, consider another company: 3DR, a U.S.-based and venture-backed company that started making drone parts, transitioned to a retail quadcopter, and is now a software company for drones. “In 12 months,” Forbes wrote in 2016, “the company has gone from an industry leading U.S. drone startup to an organization struggling to survive – the result of mismanagement, ill-advised projections and a failed strategy that relied on a doomed flagship drone.” Still, there was one area where 3DR could reliably claim an advantage over DJI: the fact it was based in the United States. In August 2018, the Department of the Interior contracted 3DR for a modest purchase of 109 Solo quadcopters. This followed an earlier 2016 contract for the Solo, but by 2017, with 3DR transitioning from the hardware to the software business, Interior still needed a quadcopter that could meet its specific needs. So, the department turned to the makers of the quadcopters that kept showing up in the military. “Market research ... indicated the remaining UAS available from U.S.-based companies were up to 10x less capable for the same price, or up to 10x more costly than similarly capable DJI aircraft,” wrote the Department of the Interior in an evaluation of its DJI systems. In collaboration and consultation with the Interior Department, DJI created a more cyber-minded firmware and software suite for its existing drone hardware, dubbed “Government Edition.” That includes security features like the drone never needing to go online, and being unable to pair with regular, out-of-the-box commercial remotes. Government Edition drones come at a premium, but one of those quadcopters costs less than two retail models. Interior Department testing of the Government Edition hardware/firmware package, done in conjunction with NASA Kennedy Space Center, found “there was no indication that data was being transmitted outside the system and that they were operating as promised by DJI,” which largely matches the independent cybersecurity assessment DJI commissioned from Kivu Consulting. While not designed for military use, the Interior Department's evaluation of DJI quadcopters left an opening: the Pentagon could learn to work with the off-the-shelf drones it has, rather than buy the off-the-shelf drones it wants. Instant eye for the battlefield sky It is easy to assume the military is limited to hobbyist quadcopters built abroad. That's not the case. Most small uncrewed aerial systems used by the military are fixed-wing drones like the Raven, Dragon Eye and Wasp. Specialized quadcopters — such as the Canada-made Aeryon Scout, a high-end military quadcopter — were supplied to anti-Gaddafi forces in Libya in 2012. The problem is that the military version of Aeryon Scout is the $100,000 price tag. Commercial quadcopters — such as the DJI Phantom, Parrot drones and even 3DR Solo — were all available at a fraction of the price, and in many cases they were more than adequate to do the job. Pairing the lower cost in the civilian space with the capability and security expected from a product built to military specifications is tricky, but not impossible. But it is happening, for example, in Andover, Massachusetts. InstantEye is a product of Physical Science Inc. Developed with funding from, among other sources, the Army and the Commonwealth of Massachusetts, the InstantEye Mk-2 GEN3 quadcopters became a program of record for Special Operations Command in 2014. The InstantEye Mk2 and Mk3 quadcopters look like they could be sold on a shelf alongside hobbyist products, with the soft military gray casing slotting in between the bright whites and matte blacks of consumer models. Physical Science said the Pentagon has roughly 2,000 InstantEye kits across all combatant commands. (Each kit has two quadcopters, which means that's roughly 4,000 individual drones). These drones have seen action in Syria and the horn of Africa. A heavy-lift model can carry up to a 44-ounce payload, making it an ideal tool for clearing explosive ordnance with explosives of its own. Code in the drone allows it to maintain the same hovering position while releasing the payload, rather than the sudden loss of weight sending it rocketing upwards. Within the military specification drone market, PSI sees the InstantEye family as a direct competitor with the Black Hornet drone used by the U.S. Army, a sparrow-sized remote-control helicopter that fits into pockets and comes with a hefty price tag. PSI was vague on the cost but said it came in significantly less than the Black Hornet, which costs roughly $60,000 apiece. PSI officials said the drones are Buy American Act compliant, certified through the Defense Logistics Agency. At present capacity, PSI's Andover production facility makes about 50 two-drone kits a month. With greater demand and staffing, the company estimates it could produce between 80 and 100 such kits per month, if needed. In 2018, the Army requested roughly 1,700 small drones. Should FY2021 see a similar quantity of drones requested, it's possible that PSI's Andover facility could, with a modest increase in staffing, supply the whole lot. The Army can presently roll out quadcopters as a specialized piece of kit. But it might not be ready to provide quadcopters to every unit that wants one. Market forces, forces market The durability and use of InstantEye shows that the Pentagon can, if so determined, fund a quadcopter company into existence. It means that, in the face of concerns about the cybersecurity of off-the-shelf drones, the Pentagon still largely has access to the simple utility of an easy-to-fly aerial camera. What remains to be seen is if Pentagon investment can produce a drone made in the United States, priced at a point close to consumer drones and assembled abroad with parts sourced from across the globe. Undersecretary of Defense for Acquisition and Sustainment Ellen Lord announced in May the launch of the “Trusted Capital Marketplace,” a partnership to facilitate private and public capital going to investment in companies deemed critical to the defense industrial base and national security. At an August briefing, Lord announced that the first project for the marketplace would be the development of a small UAS. Why start with quadcopters? “It's because where we are right now in terms of having our entire U.S. marketplace eroded,” said Lord. “Essentially, we don't have much of a small UAS industrial base because DJI dumped so many low-price quadcopters on the markets. And we then became dependent on them, both from the defense point of view and the commercial point of view, and we know that a lot of the information is sent back to China from those.” DJI disputes Lord's claims, highlighting the Kivu Consulting cybersecurity audit that found no evidence of data automatically sent back to China, and stating that DJI's “market-leading position in the drone industry” is because it “continued to research, develop and deliver the most capable products to the market.” Lord gave other reasons for the focus on small drones as the marketplace's first project. One is that small drones are easy for the public to understand. There is also the possibility that, by funding military quadcopter development, the work could rebound into commercial market. “Plus, if we meet our defense needs, we feel that there are simpler versions that would be very, very attractive for the commercial market, as well,” said Lord. “So, there was a great pathway there for industry.” Matrice reloaded Ultimately, the present state of military and domestic quadcopter markets appears guided far more by happenstance than anything else. DJI, which fell into the off-the-shelf drone market following demand from the hobbyist market, has inadvertently found its products repeatedly sanctioned as inappropriate for roles they were never designed to fill. Companies like 3DR stumbled as much because of errors in execution as stiff competition. Through it all, the Pentagon has been able to foster and develop its own quadcopters built to military specifications, specifically by contracting for exactly what it needs. It just has yet to capture the same price point as commercial models. It remains to be seen if new initiatives such as the Trusted Capital Marketplace can balance stated goals of low-cost, military specifications and domestic production. But it is a problem the Army needs to solve. As one product manager for the service told Popular Science earlier this year, “There's no organic quadcopter capability in the Army.” https://www.c4isrnet.com/unmanned/2019/09/17/can-the-army-secure-an-american-made-quadcopter/

  • Contract Awards by US Department of Defense - Novembre 20, 2020

    November 23, 2020 | International, Aerospace, Naval, Land, C4ISR, Security

    Contract Awards by US Department of Defense - Novembre 20, 2020

    U.S. TRANSPORTATION COMMAND Four additional companies -- Alaska Airlines, Seattle, Washington (HTC711-21-D-CC01); Hawaiian Airlines Inc., Honolulu, Hawaii (HTC711-21-D-CC02); Jet Blue Airways, Long Island City, New York (HTC711-21-D-CC03); and Swift Air LLC, Greensboro, North Carolina (HTC711-21-D-CC04) -- have been awarded firm-fixed-price contracts under the Domestic Airlift Charter Services, Federal Aviation Administration Part 121, indefinite-delivery/indefinite-quantity, fixed-price contract, at estimated program value of $697,000,000. These funds were obligated on individual task orders issued among 16 contracts. The program initially began in October 2018. The contracts provide domestic air cargo and passenger charter services. Services shall be provided for the Department of Defense and other federal government agencies. Work will be performed within the continental U.S., all U.S. territories, Mexico, Canada, and the Caribbean Islands. Period of performance is from Nov. 20, 2020, to Sept. 30, 2023. Ordering is decentralized and will be determined at the task order level. The U.S. Transportation Command, Directorate of Acquisition, Scott Air Force Base, Illinois, is the contracting activity. DEFENSE LOGISTICS AGENCY Sysco-Central Alabama, Calera, Alabama, has been awarded a maximum $136,226,979 fixed-price with economic-price-adjustment, indefinite-delivery/indefinite-quantity contract for full-line food distribution. This was a competitive acquisition with two responses received. This is a four-year contract with no option periods. Location of performance is Alabama, with a Nov. 23, 2024, ordering period end date. Using customers are Air Force, Army, Marine Corps, Coast Guard and federal civilian agencies. Type of appropriation is fiscal 2020 through 2025 defense working capital funds. The contracting agency is the Defense Logistics Agency Troop Support, Philadelphia, Pennsylvania (SPE300-21-D-3311). SupplyCore Inc., Rockford, Illinois, has been awarded a maximum $92,000,000 firm-fixed-price contract for supply, storage and distribution of water purification systems. This was a competitive acquisition with two responses received. This is a four-year base contract with one one-year option period. Location of performance is Illinois, with a Nov. 19, 2024, performance completion date. Using services are Army and Marine Corps. Type of appropriation is fiscal 2021 through 2025 defense working capital funds. The contracting activity is the Defense Logistics Agency Land and Maritime, Columbus, Ohio (SPE7MX-21-D-0016). Creighton AB Inc., Reidsville, North Carolina, has been awarded a maximum $7,788,263 modification (P00002) exercising the first one-year option period of a one-year base contract (SPE1C1-20-D-1213) with four one-year option periods for men's broadfall trousers. This is a firm-fixed-price, indefinite-delivery/indefinite-quantity contract. Locations of performance are New York and North Carolina, with a Nov. 24, 2021, ordering period end date. Using military service is Navy. Type of appropriation is fiscal 2021 through 2022 defense working capital funds. The contracting activity is the Defense Logistics Agency Troop Support, Philadelphia, Pennsylvania. AIR FORCE PAE Applied Technologies LLC, Fort Worth, Texas, has been awarded a ceiling $98,000,000 indefinite-delivery/indefinite-quantity contract for U.S. Air forces in Europe – Air Forces Africa (USAFE-AFAFRICA) electronic warfare operations training and infrastructure maintenance services. This contract provides electronic warfare aircrew tactics evaluation, electronic warfare combat training, operation and maintenance of equipment and electronic warfare range infrastructure maintenance for USAFE-AFAFRICA. Work will be performed at various locations in Germany, the United Kingdom and Italy. The basic contract has a five-year ordering period ending Nov. 19, 2025. This award is result of a competitive acquisition and three offers were received. Fiscal 2021 operation and maintenance funds in the amount of $8,091,999 will be obligated via the first task order, which will be awarded immediately after the basic contract, and is expected to be completed Jan. 31, 2026. The 764th Enterprise Sourcing Squadron, Ramstein Air Base, Germany, is the contracting activity (FA5641-21-D-0001). ViaSat Inc., Carlsbad, California, has been awarded a $50,800,000 cost-plus-fixed-fee, indefinite-delivery/indefinite-quantity contract for development on prototype space systems. The contractor will provide studies, design, manufacturing, integration, performance qualification, network space segment elements, launch, flight and demonstration of prototype space systems. This also includes the development, integration and demonstration with ground terminals in conjunction with the government Ground Segment to reduce risk and assess performance and functionality for future protected service. It includes the associated program management, system engineering, certification, integration, test and evaluation and configuration management. Work will be performed in Carlsbad, California, and is expected to be completed Feb. 20, 2026. This award is the result of a competitive acquisition with one offer received. Fiscal 2020 and fiscal 2021 research, development, test and evaluation funds in the amount of $737,646 are being obligated to the first task order at time of award. Air Force Research Laboratory, Kirtland Air Force Base, New Mexico, is the contracting activity (FA9453-21-D-0029; task order: FA9453-21-F-0001). NAVY Kellogg Brown and Root Services Inc., Houston, Texas, was awarded a $64,827,880 indefinite-delivery/indefinite-quantity modification for the exercise of Option Three for base operating support services at Camp Lemonnier, Djibouti; Chabelley Airfield, Djibouti; and Camp Simba, Kenya. The work to be performed provides for all management and administration, security, fire and emergency, air operations, ordnance, material management and supply, facilities management and investment, pest control, integrated solid waste, pavement clearance, utilities, base support vehicles and equipment, morale, welfare and recreation support, galley, unaccompanied housing, custodial, grounds maintenance and landscaping and environmental services to provide base operations support services. After award of this option, the total cumulative contract value will be $263,190,457. Work will be performed in Djibouti City, Djibouti (89%); Manda Bay, Kenya (8%); and Chabelley, Djibouti (3%). This option period is from November 2020 to November 2021. No funds will be obligated at time of award. Fiscal 2021 operation and maintenance (O&M) (Navy); fiscal 2021 O&M (Air Force); and fiscal 2021 O&M (National Security Agency) contract funds in the amount of $61,043,871 for recurring work will be obligated on individual task orders issued during the option period. The Naval Facilities Engineering Systems Command, Europe Africa Central, Naples, Italy, is the contracting activity (N62470-17-D-4012). (Awarded Nov. 19, 2020) BAE Systems Technology Solutions & Services Inc., doing business as BAE Systems, Rockville, Maryland, is awarded a $16,506,245 firm-fixed-price contract modification (P00012) under previously awarded contract N00604-19-C-4001 to exercise Option Year Two for the operation and maintenance of Navy communication, electronic and computer systems. The contract included a 12-month base period and four one-year option periods. The exercise of this option will bring the estimated value of the contract to $46,060,784 and if all options are exercised, it will bring the total value to $80,115,425. Work will be performed in Oahu, Hawaii (94%); and Geraldton, Australia (6%). Work will begin December 2020 and is expected to be completed by November 2021; if all options are exercised, work will be completed by November 2023. Fiscal 2021 operation and maintenance (Navy) funds in the amount of $4,048,611 will be obligated at the time of award and funds will expire at the end of the current fiscal year. This contract was solicited on a full and open, unrestricted basis with two offers received. Naval Supply Systems Command, Fleet Logistics Center, Pearl Harbor Regional Contracting Department, Pearl Harbor, Hawaii, is the contracting activity. EMR Inc.,* Niceville, Florida, is awarded firm-fixed-price task order N69450-21-F-1409 at $13,968,592 under a multiple award construction contract for the munition storage area utilities project at Barksdale Air Force Base, Louisiana. The work to be performed includes civil and electrical disciplines. The civil work includes the replacement of the water distribution mains within the munitions storage area. The electrical work includes the replacement of all existing underground primary conductors with the exception of the existing underground emergency circuit. Work will be performed in Bossier City, Louisiana, and is expected to be completed by November 2022. Fiscal 2021 operation and maintenance (Air Force) contract funds in the amount of $13,986,592 are obligated on this award and will expire at the end of the current fiscal year. Two proposals were received for this task order. The Naval Facilities Engineering Systems Command, Southeast, Jacksonville, Florida, is the contracting activity (N69450-18-D-1318). Northrop Grumman Systems Corp., Bethpage, New York, is awarded a $10,713,544 firm-fixed-price modification to previously awarded contract N00024-17-C-6311 to procure two additional Surface-to-Surface Missile Modules (SSMM) for integration into the Littoral Combat Ship framework. The SSMM fires a Longbow Hellfire missile that will be added to the surface warfare mission module aboard the Littoral Combat Ship. Work will be performed in Huntsville, Alabama (80%); Bethpage, New York (18%); and Hollywood, Maryland (2%), and is expected to be completed by November 2022. Fiscal 2021 other procurement (Navy) (82%); and fiscal 2020 other procurement (Navy) (18%) funding in the amount of $10,713,544 will be obligated at the time of award and will not expire at the end of the current fiscal year. The Naval Sea Systems Command, Washington, D.C., is the contracting activity. Iridium Satellite LLC, Tempe, Arizona, is awarded a $9,667,301 cost-plus-fixed-fee option to support commercial satellite-based network services for the Department of Defense in the areas of satellite, ground node, user equipment/terminal software and hardware development, integration and testing. Work will be performed in in McLean, Virginia (50%); and Tempe, Arizona (50%), and is expected to be complete in November 2021. This contract includes a base year and options which, if exercised, would bring the cumulative value of this contract to $45,807,778. Fiscal 2020 research, development, test and evaluation (Navy) funding in the amount of $100,000 will be obligated at time of the option exercise and will not expire at the end of the current fiscal year. This contract was solicited on a sole-source basis via a synopsis posted in Federal Business Opportunities website in accordance with 10 U.S. Code 2304(c)(1); only one responsible source and no other supplies or services will satisfy agency requirements. The Naval Surface Warfare Center, Dahlgren Division, Dahlgren, Virginia, is the contracting activity (N00178-17-C-0001). Vigor Marine Shipyard LLC, Portland, Oregon, is awarded an $8,562,943 firm-fixed-price contract (N32205-21-C-4117) for a 50-calendar day shipyard availability for the mid-term availability on the USNS Matthew Perry (T-AKE 9). The contract includes options, which if exercised, would bring the total contract value to $8,821,718. Work will be performed in Portland, Oregon, and is expected to be completed by March 8, 2021. Contract funds in the amount of $8,562,943 are obligated in fiscal 2021 using working capital funds (Navy). This contract was competitively procured with proposals solicited via the beta.sam.gov website and two offers were received. The Military Sealift Command, Norfolk, Virginia, is the contracting activity. ARMY Amentum Services Inc., Germantown, Maryland, was awarded a $7,819,920 modification (000280) to contract W52P1J-12-G-0028 for logistics support services for Army prepositioned stocks. Work will be performed in Mannheim, Germany, with an estimated completion date of Nov. 21, 2021. Fiscal 2021 operation and maintenance (Army) funds in the amount of $7,819,920 were obligated at the time of the award. The U.S. Army Contracting Command, Rock Island Arsenal, Illinois, is the contracting activity. *Small business https://www.defense.gov/Newsroom/Contracts/Contract/Article/2423533/source/GovDelivery/

All news