24 août 2020 | International, Naval

Watchdog: 75 percent of sub and aircraft carrier maintenance ended late in recent years

While the U.S. Navy has spent nearly $3 billion to improve shipyard maintenance performance in recent years, “the shipyards continue to face persistent and substantial maintenance delays that hinder the readiness of aircraft carriers and submarines,” according to a government watchdog report released this week.

Three-quarters of the 51 aircraft carrier and submarine maintenance periods from fiscal 2015 to 2019 were completed late, resulting in 7,425 days of delays, according to the report by the Government Accountability Office.

The Navy's four shipyards — in Portsmouth, Virginia; Kittery, Maine; Honolulu, Hawaii; and Bremerton, Washington — provide vital maintenance that includes ship overhauls, nuclear refueling, alterations and refits, among other duties.

The aircraft carrier maintenance periods that ended late exceeded their deadlines by an average of 113 days, the GAO reports, while submarine maintenance periods ending late missed the mark by an average of 225 days.

Such availabilities last anywhere from six months to three years, and when they don't end on time, it gums up the entire system, delaying other maintenance periods, deployments and other needs.

The main factors leading to the tardiness had to do with shipyard workforce performance and having enough people to perform the vital work, the GAO found. Unplanned work, or tasks identified after finalizing maintenance plans, was also cited as a significant factor resulting in the delays.

While the Navy has taken steps to address such delays, the sea service has yet to fully address the unplanned work and workforce factors causing the majority of delays, according to the GAO.

https://www.navytimes.com/news/your-navy/2020/08/21/watchdog-75-percent-of-sub-and-aircraft-carrier-maintenance-ended-late-in-recent-years/

Sur le même sujet

  • Contracts for November 2, 2021

    3 novembre 2021 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

    Contracts for November 2, 2021

    Today

  • EU eyes beefed-up coast guard to protect outside borders

    13 septembre 2018 | International, Sécurité

    EU eyes beefed-up coast guard to protect outside borders

    By LORNE COOK | Associated Press European Commission President Jean-Claude Juncker delivers his State of Union speech at the European Parliament in Strasbourg, eastern France, Wednesday, Sept.12, 2018. (AP Photo/Jean-Francois Badias) BRUSSELS – European Commission President Jean-Claude Juncker on Wednesday unveiled new plans to beef up the EU's coast guard and asylum agency to better police Europe's outside borders and speed the deportation of unauthorized migrants. The proposals come as EU nations bicker over who should take responsibility for people rescued in the Mediterranean Sea trying to seek better lives in Europe, even as the number of crossings has declined sharply this year. "External borders must be protected more effectively," Juncker told EU lawmakers in Strasbourg, France, in a self-styled "state of the European Union" address. He said the EU's executive Commission is proposing a standing corps for the border and coast guard agency numbering 10,000 staff, including guards and migration experts, to be up and running by 2020. Juncker said the corps should be funded by some 2.2 billion euros in EU money from the bloc's next long-term budget. But EU nations still have to endorse his plans. Beyond that, the Commission's idea of what the 2021-2027 budget should look like and what its priorities should be are certain to differ from that of member states. Full article: http://www.foxnews.com/world/2018/09/12/eu-eyes-beefed-up-coast-guard-to-protect-outside-borders.amp.html

  • Austal focuses on ship repair, supplying components while it awaits construction contracts

    14 avril 2022 | International, Naval

    Austal focuses on ship repair, supplying components while it awaits construction contracts

    The Navy has gaps in its repair capacity and its supply base capacity. Austal has two production lines in need of work, after some shipbuilding programs were delayed. The company says it can adjust to meet Navy near-term needs in a mutually beneficial way.

Toutes les nouvelles