24 septembre 2018 | International, Naval, Terrestre

US Marine Corps kills amphibious assault vehicle upgrade program

By:

WASHINGTON — The U.S. Marine Corps has killed its Amphibious Assault Vehicle survivability upgrade program as it turns focus to the future and aligns with the new National Defense Strategy.

The service executed a stop work order Aug. 27 to SAIC, which was under contract to perform survivability upgrades to the 40-plus-year-old AAV fleet to include new tracks to enhance mobility as well as increased underbelly armor, blast-mitigating seats, a new engine and transmission along with an assortment of suspension upgrades.

The order “allows [SAIC] to finish the four production control modules that they were building,” Marine Corps spokesman Manny Pacheco said in a statement sent to Defense News. “They have delivered three and we expect the fourth soon.

“All other work will be terminated.”

SAIC has already delivered 10 AAV Engineering and Manufacturing Development versions of the vehicle to the Marines.

The Marine Corps has spent approximately $125 million to date on the AAV Survivability Upgrade, or SU, program and has now identified approximately $96 million in fiscal 2019 funding that the Defense Department and Congress will have to reprioritize, according to Pacheco.

The idea was to keep the vehicles alive into 2035 as the Marine Corps begins to bring online its new Amphibious Combat Vehicle, or ACV, that would slowly replace the AAVs over time.

But in an effort to “better align programs with the National Defense Strategy and congressional guidance to reduce investment in legacy programs and focus buying power on modernization, the Marine Corps made the decision to divest the AAV SU program,” Pacheco said.

The AAV does not “meet the needs of modern Marine amphibious forcible entry operations,” he said. “Rather than continue to invest in that vehicle that, even in upgraded form, will not provide adequate maneuverability, survivability, or ship-to-shore performance, the Marine Corps believes these funds would be better used elsewhere to support modernization initiatives across the force.”

The decision was also motivated by the expected mobility and survivability demonstrated by the ACV, along with planned lethality, “which will ensure that our Marines have the firepower and survivability to succeed in the future fight,” Pacheco added.

“Reinvestment decisions will be made separately and focus on increasing lethality of the force,” Pacheco explained. “AAV SU divestiture assets may allow us to procure underfunded initiatives in the AAV modification line such as Tactical Communication Modernization and a Remote Weapons Station.”

The stop work order serves as another blow to SAIC, which lost in June a head-to-head competition to build the Marines' new ACV. BAE Systems was selected to build 30 low-rate initial production vehicles expected to be delivered by the fall of 2019, valued at $198 million.

The total value of the contract with all options exercised is expected to amount to about $1.2 billion.

But the AAV isn't likely the only program on the chopping block.

Defense leadership has been saying since last year that it can't continue to invest in older systems while also focusing on new programs; they have admitted there will come a time when those legacy systems will have to be scaled back to make way for more a modernized capability. The FY20 budget documents and five-year plans from each service have been submitted to the Office of the Secretary of Defense, and it's likely more examples of efforts to reprioritize funds from old to new platforms will emerge.

The Army has already terminated the Bradley A5 upgrade program in favor of the new Next-Generation Combat Vehicle. That upgrade would have included improvements like a third-generation FLIR, a cross-platform laser pointer, color day camera and an improved laser range finder.

And in the FY19 spending bill conference report, the Bradley A4 program took a $160 million hit due to a “revised acquisition strategy.”

While SAIC appears to have lost out both on the ACV program and now the AAV SU effort with the Marine Corps, the company is now setting its sights — building off its experience as an effective platform integrator — on the U.S. Army's Mobile Protected Firepower program.

The company, partnered with ST Kinetics and CMI Defence, will integrate CMI's Cockerill 3105 turret onto an ST Kinetics next-generation armored fighting vehicle chassis as its offering in the Mobile Protected Firepower competition that kicked off with the release of a request for proposals in November 2017.

And the company is working on some efforts related to the Next-Generation Combat Vehicle as well, SAIC's CEO, Tony Moraco, told Defense News in a recent interview.

https://www.defensenews.com/land/2018/09/24/us-marine-corps-kills-amphibious-assault-vehicle-upgrade-program

Sur le même sujet

  • Major Pentagon IT programs are reducing costs, but development challenges remain

    5 juin 2020 | International, C4ISR, Sécurité

    Major Pentagon IT programs are reducing costs, but development challenges remain

    Andrew Eversden A federal watchdog's review of 15 major information technology investments at the Department of Defense found that many programs were below cost estimates, though several had delays in their original timelines, shortfalls in cybersecurity testing and software development workforce challenges. The Government Accountability Office's 18th annual “Defense Acquisitions Annual Report," released June 3, evaluated 15 major business and non-business information technology programs, the first time the GAO evaluated IT programs as part of the review. The IT projects the GAO examined totaled $15.1 billion in spending. The report found that 11 of the 15 systems saw decreases in their in their life-cycle cost estimates. The biggest cost saver was the Army Contract Writing System, which decreased its cost estimate by $229 million. That system will replace several legacy platforms and serve as the Army's enterprise-wide contract management platform. Officials working on the systems with lower price tags said that the drops were due to contract cost revisions, program management efficiencies and lower costs than expected. Two of the remaining four programs that had higher costs experienced increases of over 20 percent, though the report doesn't note which programs. One program, not named in the report, experienced an increase of $315 million, or 151 percent. Officials from the unexpectedly expensive projects cited developmental challenges as a reason for the increases. Two-thirds of the projects experienced schedule delays, ranging from one month for the Marine Corps' Air Command and Control System Increment One, to five years for the Air Force's Defense Enterprise Accounting and Management System-Increment One. Officials for delayed programs told the GAO that slowdowns occurred because of cybersecurity gaps, performance issues and longer-than expected maintenance periods. The GAO also evaluated the use of software development by the systems, finding that 14 of the 15 programs were using various types of iterative software development, such as agile, incremental and waterfall, among others. Among the other findings: - All eight major business IT systems it evaluated were using commercial-off-the-shelf software, consistent with DoD guidance from 2017. COTS software is supposed to reduce cost, development time and increase delivery. - Six of the 15 systems were conducting cybersecurity testing during the developmental stages of the program, which allows the services to fix vulnerabilities early in the software life cycle before the program is used, saving money and reduce delays before systems are fully implemented. - Eleven of the 15 programs conducted operational cybersecurity testing, during which vulnerabilities and their effects are identified in a mission context, the GAO said. While Pentagon leaders push faster delivery times on software, many programs reported workforce challenges associated with rapid development. According to the GAO, nine of the 15 programs said it was “difficult to find staff with the requisite expertise.” Seven struggled to hire staff fast enough to complete development, while six reported not meeting software engineering staff plans to be a challenge. The watchdog evaluated five programs from the Air Force, four Navy projects, two Army investments and four programs from the office of the secretary of defense. The GAO report said that a companion report on other major Pentagon IT systems would be released later this year. https://www.c4isrnet.com/it-networks/2020/06/03/major-pentagon-it-programs-are-reducing-costs-but-development-challenges-remain/

  • Israel Seeks $8B Arms Deal At White House: F-35s, V-22s, KC-46s

    16 septembre 2020 | International, Aérospatial, Terrestre

    Israel Seeks $8B Arms Deal At White House: F-35s, V-22s, KC-46s

    ARIE EGOZI TEL AVIV: Israeli Prime Minister Benjamin Netanyahu asked President Donald Trump today for 12 Boeing V-22s, another squadron of F-35s to bring the total to 75, and the very early delivery of two Boeing KC-46As at the White House today. The request was made during a day of extraordinary meetings as President Trump, the Prime Minister of Israel and the Foreign Ministers of Bahrain and the United Arab Emirates were to sign what are being called the Abraham Accords, meant to normalize relations between the Arab states and Israel. The new weapons are meant to keep Israel's qualitative edge after the U.S agreed to sell the F-35 to the UAE and Teheran rattles its homemade swords, furious about the new era between Israel and some Gulf states. Hours before hosting the signing of historic peace agreements between Israel and the UAE and Bahrain, President Trump doubled down on the idea of selling F-35s to the UAE. “I personally would have no problem with it,” the president told Fox and Friends this morning, “I would have no problem in selling them the F-35.” The Israelis, who understand the US political system well, are likely to press Trump to put the new sales in motion before the November elections to minimize the chances they might fall victim to a change in power in Washington. “The Israeli request will be based on an accelerated process aimed at getting all the approvals before the November presidential elections” one Israeli source told BD. The request is also likely to include a replacement for Israeli Apache AH-64A combat helicopters that are planned to go out of service in 2025. Israel, one source says, will also ask for “increased numbers” of bunker buster bombs, usually thought to be designed to strike Iranian nuclear sites. On top of all that, the Israelis may seek an advanced communication satellite, a source told Breaking D. The request for a new weapons package would be in addition to the existing Foreign Military Financing agreement with the US. The current agreement, signed in 2016, increased US assistance from $ 34 billion in the decade to $38 billion between 2019 and 2028. Why is Israeli seeking so much new gear? It's not, Israeli sources explain, because of the prospective sale of F-35s to the UAE, but because they believe this deal will open a new arms race in the region and they want to stay head of it. Israel is also concerned about the possibility of leadership changes in some Gulf countries The assessments for what's needed were drawn up when the IDF formed a special team headed by Maj. General Tomer Bar, the IDF's head of its planning and force building department. This team is reviewing the operational demands of some of the IDF ground forces units. https://breakingdefense.com/2020/09/israel-seeks-8b-arms-deal-at-white-house-f-35s-v-22s-kc-46s/

  • CC-177 Globemaster III aircraft flying in British Columbia - Terrace Standard

    9 juillet 2021 | International, Aérospatial

    CC-177 Globemaster III aircraft flying in British Columbia - Terrace Standard

    Prince Rupert is a potential stop for Canadian Air Forces training exercise

Toutes les nouvelles