SECNAV: Ford Issues Due To Cost Cap, Explains Timeline

By Rich Abott |

The Secretary of the Navy today said the cost cap on the first Ford-class aircraft carrier helped lead to problems resulting in delays to the advanced weapons elevators (AWEs) and explained the government's issues and changing strategy with the shipbuilder.

Secretary of the Navy Richard Spencer said on Wednesday at a Heritage Foundation press roundtable that the Navy and shipbuilder/AWE builder Huntington Ingalls Industries [HII] planned to build a test elevator site, similar to the electromagnetic advanced landing system (EMALS) located in Lakehurst, N.J.

The Navy has used Joint Base McGuire-Dix-Lakehurst to test the General Atomics advanced arresting gear (AAG) and EMALS hundreds of times before testing them on the first new carrier, the USS Gerald R. Ford (CVN-78).

“Then we had the cost cap come in. And as [HII president and CEO] Mike Petters can say, you know fine, the cost cap comes in and no one builds the land site elevator. We had to cut costs somewhere. Sometimes we're our own worst enemy,” Spencer said.

In February, the Navy said it would start building the AWE land-based test site, after the fact, in Philadelphia (Defense Daily, Feb. 20).

Spencer said he thinks about it and wonders if anyone was expecting there to be second and third order effects of a cost cap.

“You don't get anything for free and you're not going to drive quality by cost cap. We have to start thinking differently when we go to cost control.”

Spencer also further illuminated the Navy's work with HII on the elevators. Last week, he strongly criticized the company after delays on the AWEs, saying the Navy's faith and confidence with HII senior management on the project were very low (Defense Daily, Oct. 25).

On Monday, Assistant Secretary of the Navy for Research, Development and Acquisition James Geurts said the Navy-HII team's output on the elevators has been much better in the last few months and he was cautiously optimistic on progress of the Ford elevators (Defense Daily, Oct. 29).

Spencer said in fall 2018 the Navy was finalizing the HII elevator plan. The company gave him a chart that said all 11 AWEs would be tested and certified by the end of the planned post-shakedown availability (PSA), which was then planned for July 15.

He said HII management reported high confidence of this timeline while Naval Reactors told him due to throttle and bearing issues the PSA would likely be pushed into September or October, “so I had more margin there. Did I feel confident? Completely confident.”

Then, in January, Spencer said he made a bet with President Trump that the AWEs would be finished with the PSA or he could be fired (Defense Daily, Jan. 8).

Spencer explained this was meant to rally the shipbuilders.

“What we weren't seeing down there was the spring in the step of the people on the waterfront, to be very frank with you. It was business as usual. So we said ok, here's a rally point, we're going to commit to this.”

However, in May 2019 he said HII management “goes oops, here we are, elevators aren't going to be ready until the end of 2020, possibly 2021. And that's when I went, do they really know what they're doing?”

Spencer called that a moment of inflection and called Thomas Fargo, chairman of the board of HII, asking if the board knew what was going on with management “because out trust and confidence on this specific project of the elevators has eroded significantly.”

While Spencer said Fargo said yes, there were continued frustrations on the government side.

“That's when Hondo [Geurts] and I said let's get a tiger team down there and let's take this over as the general contractor and HII can sub to us. And that's basically what's happened this last 3 months.”

Spencer said he went to the president and, after explaining the situation, was told “it's a complex system, keep knocking down the dragons.”

When asked if these lessons would apply to future ships, Spencer said the Navy wants to avoid a cost cap for the lead ship in a new class like upcoming guided-missile future frigate, FFG(X).

“We have to have an open discussion on first of class. Now, these are proven designs so it's going to be a little different, but we are adjusting it here and there and yes we should expect some hiccups,” he continued.

“Expectation management, I think, is key.”

Going forward, Spencer argued perhaps the Navy should make requirements for ships more flexible. He compared the Navy's process to the airline industry, which requires an airplane that can fit a certain number of people to transport them a certain amount of miles and has few change orders, then examines the options.

However, the government has shrunk the competitive base so far that contractors agree to following requirements but only if the government takes 60 to 100 percent of the risk.

“In some cases, you'd love to say should we change requirements to requests? Because if in fact you're a shipbuilder, why should I definitively lock you in if you have better ideas? Where is the flow to say if you want to get here you might want to consider this, which his 80 percent of the solution versus I will drive to 100% of your solution but the cost is going to be up here?”

Spencer said he understands it is difficult to change requirements because they serve a definite purpose but wondered at what cost and percent mission capability can the government make a compromise compared to the current inflexibility.

Relatedly, Spencer said he has “medium confidence” that a recent $197 million reprogramming request to Congress to fund more Ford fixes will be enough, simply because “first of classes is tough.”

“I'd be remiss if I said that was the last, to be very frank. I'd rather have the option to say we're going to come for more than saying no we're capped off now. I feel good on what we're finally learning on the end of this birthing process,” Spencer said.

https://www.defensedaily.com/secnav-ford-issues-due-cost-cap-might-need-money/navy-usmc/

Sur le même sujet

  • BAE building new campus for recently acquired GPS business

    6 novembre 2020 | International, C4ISR

    BAE building new campus for recently acquired GPS business

    Aaron Mehta WASHINGTON — BAE Systems announced Thursday it is investing more than $100 million in new infrastructure to support its navigation and sensor systems business, which was acquired from Collins Aerospace over the summer. The new campus, located in Cedar Rapids, Iowa, will condense the company's military GPS capabilities from around the country into one location. Included in the project is a 278,000-square-foot factory and research and development center, located on a 32-acre site just minutes from Eastern Iowa Airport. The building will include a large factory, several hundred offices, workstations, and both classified and unclassified labs, according to a company release, with the ability to add 50,000 square feet of space if needed. BAE spent $1.9 billion to land the business unit, which primarily focuses on military GPS technologies, in a deal that was completed July 31. The acquisition followed the merger of defense contracting giants United Technologies Corp. and Raytheon into Raytheon Technologies Corporation in June 2019. The U.S. Department of Justice approved that merger in March 2020, but only on the condition the companies divest UTC's military GPS and large space-based optical systems businesses, as well as Raytheon's military airborne radios business. In March, BAE's chief executive Jerry DeMuro told Defense News that the purchase, along with $275 million spent to purchase the airborne radio business, positioned the company well under the National Defense Strategy. The military GPS business includes a workforce of 700 employees that design and build advanced, hardened, secure GPS products, including devices that can utilize M-Code, a more secure U.S. military GPS signal. The business boasts more than 1.5 million GPS devices installed on more than 280 weapons systems. “Our world-class military GPS business is built on the rich talent pool in Greater Cedar Rapids,” John Watkins, vice president and general manager of precision strike and sensing solutions at BAE Systems, said in a statement. “This investment will provide our high-tech engineering and manufacturing experts with a world-class workspace and the tools to enhance operational excellence.” https://www.c4isrnet.com/industry/2020/11/05/bae-building-new-campus-for-recently-acquired-gps-business

  • Update: Pentagon, Lockheed Martin reach settlement on F-35 spare parts fees

    11 mars 2021 | International, Aérospatial

    Update: Pentagon, Lockheed Martin reach settlement on F-35 spare parts fees

    The Pentagon and Lockheed Martin have settled over hundreds of millions of US dollars in labour costs that the armed services incurred in managing non-ready-for-issue (non-RFI), or installation, spare parts for its fleet of F-35 Lightning II...

  • Army on path to use space sensors to help guns on the ground see farther

    7 juillet 2020 | International, Aérospatial, Terrestre

    Army on path to use space sensors to help guns on the ground see farther

    Jen Judson WASHINGTON — The Army is on a path to use space sensors to help its artillery see and shoot well beyond current capability. The service has already wrapped up an effort to achieve this capability, which took place in Europe in February and March, Gen. Mike Murray, Army Futures Command commander, told reporters in a media call. Murray was discussing how Army modernization would proceed despite COVID-19 social isolation measures in April. The Army will continue to build upon these early successes tapping into space assets to help guns on the ground hit long-range targets, an Army spokesperson told Defense News in a written statement. Conducted through Futures Command's cross functional team in charge of Assured Position, Navigation and Timing (A-PNT), the service was able to link space sensors with shooters in live-fire demonstrations in Grafenwoehr, Germany, on three separate occasions with the latest on March 23, the spokesperson wrote. Over the course of the demonstrations, the team “successfully sensed and hit targets at ranges beyond line of sight using satellite capabilities that have not been accessible to ground forces until now,” the spokesperson said. The exercise showed the “Army's ability to engage and defeat time sensitive targets with timely and accurate fires anywhere on the battlefield.” Tapping sensors that can help guide missiles and munitions to targets deep into the battlefield is critical to the Army's future long-range precision fires capability and key to operating across multiple domains. But achieving such distances requires connecting sensors and shooters that have never worked together before Long-Range Precision Fires (LRPF) is the Army's top modernization priority as it plays a critical role in the future battlefield and will be a centerpiece in the service's future Multi-Domain Operations doctrine currently in development. The LRPT cross functional team will continue to push the capabilities to far greater ranges than previously capable or than those distances previously allowed prior to the United States' withdrawal from the Intermediate-Range Nuclear Forces Treaty in 2019. During the initial live-fire demonstrations, a unit conducted an operation using the weapons and ammunition associated with their mission — in this case the Army integrated the capability with the Multiple Launch Rocket System (MLRS) and the M777 howitzer. The demonstrations used high explosive rounds equipped with a precision guidance kit fuze fired from the M777 howitzer or MRLS launcher. The Advanced Miniaturized Data Acquisition and Dissemination Vehicle accessed various sensors and target data was transmitted through the Joint Automated Deep Operations Coordination System and the Advanced Field Artillery Database System for the technical and tactical fire direction processes, the spokesperson detailed. The demonstrations gave “insight” into current capabilities “and their ability to link in novel ways to provide a capability down to the division operational level of combat,” the Army spokesperson said. Originally, pre-pandemic, the Army had planned to work on the capability throughout the scaled-back Defender Europe 2020 exercise using space-based sensors to pursue deep targets that “have not been responsive to ground forces until now,” according to the spokesperson. The APNT team will build upon the demonstrations by finding ways to reduce the sensor-to-shooter timeline to meet capability needs in the future anticipated operating environments. Ultimately, the Army will integrate the capability into the future Extended Range Cannon and a “full suite of Army fires platforms.” The ERCA cannon has already reached ranges of roughly 40 miles in recent tests at Yuma Proving Ground, Arizona. The service also plans to begin integrating with aviation platforms, the spokesperson said. The demonstrations are feeding into a “targeting process multi-domain operational strategy,” according to the spokesperson. The Army also plans to work on an architecture that connects both kinetic and non-kinetic assets from across joint, interagency and multinational partners. https://www.c4isrnet.com/2020/07/06/army-on-path-to-use-space-sensors-to-help-guns-on-the-ground-see-farther/

Toutes les nouvelles