24 décembre 2018 | Local, Naval

Quebec's Davie offers second supply ship at reduced cost to entice Liberal government to buy

David Pugliese, Ottawa Citizen

Naresh Raghubeer, a senior adviser to Davie Shipyards, said the Asterix sister ship — Obelix — can be ready for missions with the navy within 24 months: 'We've proven already we can do it'

A Quebec company is offering the Liberal government a second supply ship at a reduced price as it warns about further delays on a similar vessel being built for the Royal Canadian Navy by a firm on the West Coast.

Davie Shipyards delivered its first ship, Asterix, to the government on time and on budget in a deal worth $659 million. It is now offering a second ship at $500 million to entice the Liberals to move ahead with such a purchase.

But industry representatives privately say Davie faces an uphill battle as Asterix is at the heart of the trial of Vice Admiral Mark Norman and any government move to buy a sister ship would signal the actions of that naval officer in supporting the original deal was right.

Naresh Raghubeer, a senior adviser to Davie, said the Asterix sister ship — Obelix — can be ready for missions with the navy within 24 months. “We've proven already we can do it,” he added.

Davie was selected by the previous Conservative government for a sole-source deal to convert Asterix, a commercial vessel, into a naval supply ship. That was done after the military's two existing supply vessels were taken out of service because of damage and age.

When the Liberals formed a new government in the fall of 2015 they tried to delay the Asterix project but backed down after Davie warned it would have to shut down its yard.

Asterix has been operating for the last nine months, refuelling and resupplying Canadian and allied warships.

Norman, who had been head of the navy, was accused of leaking information to Davie about Liberal plans to delay Asterix as well as advocating for the Davie design. He is charged with one count of breach of trust but has said he did nothing wrong as he was following government directives.

Conservative leader Andrew Scheer questioned the Liberal government Dec. 12 in the Commons why it was not moving ahead with acquiring Obelix, pointing out the navy needed a second ship.

But Prime Minister Justin Trudeau accused Scheer of playing “petty politics.”

“The armed forces did an assessment,” Trudeau said. “They don't need the Obelix.”

Asked about the assessment, the Royal Canadian Navy referred Postmedia to a November 2014 internal document which outlined the requirements of a interim supply ship. The document was produced before a deal was reached on Asterix. The navy's statement noted that the Joint Support Ship being built at Seaspan Shipyards in Vancouver “remains a critical component for achieving success in both international and domestic” Canadian military missions.

That joint supply ship was supposed to be delivered by Seaspan in 2017. That schedule slipped and the 2019 and 2020 delivery dates were proposed. The latest delivery date for the first of two ships is now 2022-2023 but with the caveat attached “ with risk”, meaning that it could fall further behind schedule, government officials confirmed to Postmedia.

The cost of the Asterix project included the conversion of the ship, the lease of the vessel from Davie over a five-year period, and the company's provision of a 35-member civilian crew to run the vessel. The Royal Canadian Navy provides as many as 50 personnel to do the actual at-sea refuelling and resupply of its warships.

A similar arrangement could be made for Obelix but the cost would be lower since the engineering for the conversion process has already been worked out, Davie officials pointed out.

Raghubeer said Davie could fill the gap in supply ships while Seaspan continues to build the two vessels the government originally requested from that yard.

The Davie yard represents 50 per cent of Canada's shipbuilding capability. Currently the firm has 200 employees, down from the 1,400 working in 2017 when Asterix was delivered.

Both the Commons defence committee and the Senate defence committee recommended acquiring a second supply ship from Davie.

Davie's rival, Irving Shipbuilding, has voiced opposition to the Quebec company receiving any additional federal shipbuilding contracts.

https://nationalpost.com/news/quebecs-davie-offers-to-build-second-supply-ship-at-reduced-cost-to-entice-liberal-government-to-buy

Sur le même sujet

  • Boeing’s P-8 Poseidon would contribute roughly $358M annually to Canada if selected: study - Skies Mag

    31 mai 2023 | Local, Aérospatial

    Boeing’s P-8 Poseidon would contribute roughly $358M annually to Canada if selected: study - Skies Mag

    According to an independent study conducted by Doyletech Corporation, selecting the Boeing P-8 Poseidon for Canada's Multi-Mission Aircraft requirement would bring significant benefits to the country.

  • Federal government issues another extension for fighter replacement proposals

    7 mai 2020 | Local, Aérospatial

    Federal government issues another extension for fighter replacement proposals

    Posted on May 7, 2020 by Chris Thatcher Public Services and Procurement Canada has extended the deadline for proposals to replace the CF-188 Hornets until July 31, 2020. The 30-day extension is a response to the coronavirus pandemic that has disrupted business operations globally, especially in the aerospace sector. “The COVID-19 pandemic is presenting numerous challenges for businesses and their workforce, including the eligible suppliers for the Future Fighter Capability Project,” said a spokesperson for the department in a statement on May 6. “The unprecedented situation has impacted proposal finalization. To support our commitment to conducting an open, fair, and transparent competition, the extension will ensure all suppliers are able to submit their most competitive offer to Canada.” Three qualified contenders remain in the competition to replace the Royal Canadian Air Force fighter jet fleet: Sweden's Saab Aeronautics with the Gripen E and the United States-backed Boeing F/A-18 Super Hornet and Lockheed Martin F-35A Lightning II. Dassualt Aviation and Airbus Defense and Space withdrew their entrants, the Rafale and Eurofighter Typhoon, in 2018 and 2019, respectively. The project, valued at up to $19 billion, is seeking proposals for 88 advanced aircraft to replace an aging fleet of 76 A and B model Hornets that began entering service in the mid-1980s. The bids will be evaluated on technical capability, worth 60 per cent of the evaluation; acquisition and operating costs (20 per cent); and economic benefit to Canadian industry, also 20 per cent and the highest weighting for economic return on any defence procurement to date. It's the second time this year the federal government has prolonged the deadline for the request for proposals (RFP). In February, at the request of one of the suppliers, it granted a three-month extension from March 30 to June 30. Release of the formal RFP was also pushed back several times before being issued in July 2019, to accommodate changes during the draft RFP process. The project is the largest acquisition in recent Air Force history and has faced numerous schedule changes over the past decade. This latest change comes a week after Canada submitted an annual payment of US$70.1 million to remain in the F-35 development program, which is being supported by nine partner countries. To date, the government has invested US$541.3 million since 1997 into the multi-variant, next-generation fighter program. However, Canadian companies have captured US$1.8 billion in work on the fighter. “This participation provides Canadian industry with contract opportunities that are only available to program participants,” a spokesperson for National Defence told Canadian Press. “Our membership will also allow us preferential pricing and sequencing in the build schedule should the F-35 aircraft be successful in the current future fighter capability program.” Despite the recent delay because of COVID-19, PSPC still anticipates to award a contract in 2022. The first new aircraft would be delivered in early 2025. In the interim, the government is acquiring and upgrading 18 operational Australian F/A-18A Hornets to augment the current fleet of 76 Hornets. The RCAF is also finalizing an upgrade package for the 76 fighters that will likely include enhancements to their combat capability. https://www.skiesmag.com/news/government-extends-fighter-proposal-deadline/

  • CAE awarded contract by GA-ASI to develop synthetic training system

    28 janvier 2019 | Local, Aérospatial

    CAE awarded contract by GA-ASI to develop synthetic training system

    CAE announced on Jan. 24 that the company has been awarded a contract from General Atomics Aeronautical Systems, Inc. (GA-ASI) to develop a comprehensive synthetic training system for the United Kingdom's Protector RG Mk1 remotely piloted aircraft system (RPAS) program. The Protector will be operated by the Royal Air Force and is the U.K.-specific variant of GA-ASI's certifiable MQ-9B SkyGuardian RPAS, which can meet the most stringent certification requirements of aviation authorities. Under terms of the contract, CAE will design and develop a comprehensive synthetic training system that will include desktop and high-fidelity mission trainers specific to the Protector RPAS. The high-fidelity Protector mission trainers will be based on GA-ASI's certifiable ground control station (CGCS) and will be the first simulators developed for this advanced CGCS. CAE will also provide brief/debrief and scenario generation stations as part of the overall synthetic training system. “We are pleased to continue our global training partnership with GA-ASI to support the U.K. Protector program,” said Gene Colabatistto, CAE's group president, defence and security. “Protector will offer a new level of capability in an unmanned air system and will require well-trained aircrews. We will leverage developments we have made over the past several years creating the highest fidelity training devices for the Predator family of remotely piloted aircraft to produce a world-class synthetic training system for the Protector program.” Initial deliveries of the synthetic training system will be targeted for delivery in 2020 to RAF Waddington, the hub of U.K. Intelligence, Surveillance, Target Acquisition and Reconnaissance (ISTAR) that will be the main operating base for the Protector. “MQ-9B SkyGuardian, which Protector is based on, represents the next-generation of remotely piloted aircraft capabilities, including longer endurance and automatic take-off and landing,” said David R. Alexander, president, aircraft systems, GA-ASI. “The Protector synthetic training system will play a key role helping the Royal Air Force develop skilled aircrews, and we are pleased to collaborate with CAE as our training partner on this critical program.” https://www.skiesmag.com/press-releases/cae-awarded-contract-by-ga-asi-to-develop-synthetic-training-system

Toutes les nouvelles