30 juin 2021 | International, Naval

Navy's powerful aerial jamming pod moves to next phase

The jammer is the Navy's premier aerial electronic attack platform that will replace the ALQ-99 jamming pod and be mounted aboard EA-18 Growler aircraft.

https://www.c4isrnet.com/electronic-warfare/2021/06/29/navys-powerful-aerial-jamming-pod-moves-to-next-phase

Sur le même sujet

  • Some F-35 suppliers are having trouble delivering parts on schedule, and Turkey’s departure could make that worse

    14 mai 2020 | International, Aérospatial

    Some F-35 suppliers are having trouble delivering parts on schedule, and Turkey’s departure could make that worse

    By: Valerie Insinna WASHINGTON — Lockheed Martin's F-35 Joint Strike Fighter is on the verge of full-rate production, with a decision slated for early 2021. But a congressional watchdog group is concerned that as the company ramps up F-35 production, its suppliers are falling behind. And those supply chain problems could get even worse as Turkish defense manufacturers are pushed out of the program, the Government Accountability Office said in a May 12 report. According to the GAO, the number of F-35 parts delivered late skyrocketed from less than 2,000 in August 2017 to upward of 10,000 in July 2019. The number of parts shortages per month also climbed from 875 in July 2018 to more than 8,000 in July 2019. More than 60 percent of that sum was concentrated among 20 suppliers, it said. “To mitigate late deliveries and parts shortages — and deliver more aircraft on time — the airframe contractor has utilized methods such as reconfiguring the assembly line and moving planned work between different stations along the assembly line,” the GAO said. “According to the program office, such steps can cause production to be less efficient, which, in turn, can increase the number of labor hours necessary to build each aircraft,” which then drives up cost, the GAO added. Those problems could be compounded by Turkey's expulsion from the F-35 program, which was announced last year after the country moved forward with buying the Russian S-400 air defense system. Although Turkey financially contributed to the development of the F-35 as a partner in the program, the U.S. Defense Department has maintained that Turkey cannot buy or operate the F-35 until it gives up the S-400. The Pentagon has also taken action to begin stripping Turkish industry from the aircraft's supply chain, a process that involves finding new companies to make 1,005 parts, some of which are sole-sourced by Turkish companies. Ellen Lord, the Pentagon's undersecretary for acquisition and sustainment, had hoped to stop contracting with Turkish suppliers by March 2020, but in January she said that some contracts would extend through the year, according to Defense One. While the Defense Department has found new suppliers to manufacture the parts currently made in Turkey, it is uncertain whether the price of those components will be more expensive. Furthermore, as of December 2019, the new production rates for 15 components were lagging behind that of the legacy Turkish producers. “According to program officials, some of these new parts suppliers will not be producing at the rate required until next year, as roughly 10 percent are new to the F-35 program,” the GAO said. “Airframe contractor representatives stated it would take over a year to stand up these new suppliers, with lead times dependent on several factors, such as part complexity, quantity, and the supplier's production maturity. In addition, these new suppliers are required to go through qualification and testing to ensure the design integrity for their parts.” The F-35 Joint Program Office disagreed with the GAO's recommendation to provide certain information to Congress ahead of the full-rate production decision, including an evaluation of production risks and a readiness assessment of the suppliers that are replacing Turkish companies. In its statement, the JPO said it is already providing an acceptable number of updates on the program's readiness for full-rate production. Hard times for the F-35's engine supplier Not all F-35 production trends reported by the GAO were bad for the aircraft. Since 2016, Lockheed has made progress in delivering a greater proportion of F-35s on schedule, with 117 of 134 F-35s delivered on time in 2019. However, one of the biggest subsystems of the F-35 — the F135 engine produced by Pratt & Whitney — drifted in the opposite direction, with a whopping 91 percent of engines delivered behind schedule. At one point in 2019, Pratt & Whitney stopped deliveries of the F135 for an unspecified period due to test failures, which also contributed to the reduction of on-time deliveries. According to the Defense Contracts Management Agency, “there have been 18 engine test failures in 2019, which is eight more than in 2018, each requiring disassembly and rework,” the GAO wrote. “To address this issue, the engine contractor has developed new tooling for the assembly line and has established a team to identify characteristics leading to the test failures. Plans are also in place for additional training for employees.” https://www.defensenews.com/air/2020/05/12/some-f-35-suppliers-are-having-trouble-delivering-parts-on-schedule-and-turkeys-departure-could-make-that-worse/

  • US Navy awards contract to Serco for mass notification systems upgrade

    2 juillet 2019 | International, Autre défense

    US Navy awards contract to Serco for mass notification systems upgrade

    The US Naval Information Warfare Center (NIWC) Pacific has awarded a contract to Serco to perform upgrades to giant voice mass notification systems. The giant voice mass notification system is a voice announcing system used to provide warnings to communities living near naval installations in emergency situations. Under the contract, Serco will provide production and installation services for the systems located at different sites in the Western Pacific Region. The one-year task order is valued at around $8.3m. Work will include pre-installation testing and check-out, retrofit installation, inspection, pre-setup, optimisation, training, and systems operational verification testing. Serco chairman and CEO Dave Dacquino said: “Serco has a 20-plus year legacy of rapidly providing highly reliable support to meet the emerging requirements of the navy. “Serco is proud of the base modernisation services we are providing to help secure our bases, and detect and respond to threats.” NIWC Pacific awarded the task order under the $232m anti-terrorism/force protection (ATFP) naval electronic surveillance systems (NESS) indefinite-delivery, indefinite-quantity (ID/IQ) contract secured by Serco earlier this year. Under the contract, the company will deliver technical services to the Naval Facilities Engineering Command (NAVFAC), programme executive offices, and other US Department of Defence (DoD) agencies. Services are also offered to the Department of Homeland Security, US Marine Corps, and other government programmes. Serco is specialised in building and maintaining command, control, communications, computers, combat systems, intelligence, surveillance, and reconnaissance (C5ISR) systems for various branches of the DoD. Specific services provided by the firm include lifecycle sustainment engineering, systems integration, hardware procurement, software development, and technical support. In addition, the company provides installation and testing, operations and maintenance solutions. In March, the company won a contract from the US Navy to provide technical and programmatic support at naval bases globally. https://www.naval-technology.com/news/us-navy-awards-contract-serco-mass-notification-systems-upgrade/

  • Lockheed: F-35 upgrade delays will lead to fewer  2023 deliveries

    18 avril 2023 | International, Aérospatial

    Lockheed: F-35 upgrade delays will lead to fewer 2023 deliveries

    The vendor said putting Technology Refresh 3 into the F-35 has been very difficult, but that the company is now "in the very late innings."

Toutes les nouvelles