22 mai 2019 | International, Aérospatial, Naval

Navy Awards Sikorsky $1.13B for Next 12 CH-53K Heavy-Lift Helicopters

By:

The Department of the Navy awarded Sikorsky a $1.13-billion contract for 12 CH-53K King Stallion heavy-lift helicopters, the Defense Department announced on Friday.

The contract to the Lockheed Martin-owned company covers Lots 2 and 3 of the helicopter, which will replace the aging CH-53E Super Stallion. The Navy plans to buy 200 CH-53Ks over the life of the program.

This award comes after an overhaul of the helicopter's test program, which had fallen behind due to inefficiencies in the test plan and technical problems in the design of the aircraft. Those problems included an exhaust gas reingestion problem in the helo's three-engine design. A recent Pentagon Selected Acquisition Report noted 126 design deficiencies, Bloomberg has reported, and the Department of the Navy has since worked with Sikorsky to restructure the remaining test program.

After cost growth in the Lot 1 contract for the helicopters, the Navy and Marine Corps reduced this contract to 12, compared to a previous plan to buy 14 under Lots 2 and 3.

“The aircraft quantity was negotiated for 12 vice 14 aircraft due to cost growth identified during Lot 1 production as well as the cost of incorporating the correction of known technical deficiencies that have resulted from developmental flight test to date,” Navy spokesman Capt. Danny Hernandez told USNI News.
“The lower quantity will allow the program to afford the aircraft while preserving planned support efforts within the budget and program schedule.”

In a Friday news release, Navy and Marine Corps leadership expressed confidence in the program despite the challenges it has faced over the past year or so.

“The Marine Corps is very appreciative of the efforts by the Navy and our industry partners to be able to award the LRIP 2/3 contract,” Lt. Gen. Steven Rudder, the deputy commandant for aviation, said in a news release.
“This is a win for the Marine Corps and will secure the heavy-lift capability we need to meet future operational requirements and support the National Defense Strategy. I'm very confident in the success of the CH-53K program and look forward to fielding this critical capability.”

“This contract award reflects close cooperation and risk sharing between the Government and industry teams to deliver critical capabilities to the Marine Corps,” James Geurts, assistant secretary of the Navy for research, development and acquisition, said in the release.
“Working with our industry partners, the team ensured that solutions for technical challenges are incorporated into these production aircraft. This reflects the urgency to ensure we deliver capabilities necessary to support the Marine Corps and the Department of Navy's mission, while continuing to drive affordability and accountability into the program.”

In a House Armed Services Committee hearing earlier this spring, Daniel Nega, the deputy assistant secretary of the Navy for air programs, told lawmakers on the tactical air and land forces subcommittee that the upcoming contract would put the onus on Sikorsky to address remaining design flaws and fix any other problems that come up during the remainder of testing.

“The flight envelope's been tested to the corners; Gen. Rudder talked about how we've sort of wrung it out,” he said at the hearing.
“There's a relatively low risk that anything major will be found. However, if nuisance issues come along, we are not going to give those nuisance issues to the Marines, and the Navy and Marine Corps team is not going to accept the full risk of that. So the risk concurrency between the development and the production, that overlap is going to be taken care of.”

Asked how the contract awarded today would do that, Hernandez told USNI News that “the production contract is structured to ensure a deployable configuration is delivered for fleet use. All known issues are included in the contract, additionally the contract provides provisions for any new issues discovered during flight testing. This will ensure appropriate shared risk between the government and industry.”

Sikorsky's Path Forward

Despite the ongoing technical challenges with the helicopter design and the delays in the test program – which has set back the planned start of initial operational test and evaluation but does not appear to threaten the planned first deployment of the helicopter in 2023 or 2024 – Sikorsky officials remain confident that the aircraft is on the right path following last year's restructure.

“The majority of the technical issues that we've discovered over the 1,400 hours of flight test, nothing too terribly different than we would expect to find on a development program,” Bill Falk, Sikorsky's program director for CH-53K, told USNI News in an interview earlier this month.
“The majority of them are already resolved, already proven and demonstrated in aircraft. We do have a set of issues that we still are in the process of resolving and demonstrating, but we've got a plan in place, parts installing in the aircraft and flight test plans to demonstrate that.”

Falk said the company has dedicated one of its six test aircraft to tackle the exhaust gas reingestion issue, spending the last four or five months using computer-aided modeling and data from test flights to develop prototype solutions and test them out on the aircraft.

“We have enough data that we now understand what solution we need to install on the aircraft, demonstrate and validate, which will become part of the production solution,” Falk said.
“So we are at a completely different spot: where there was uncertainty four to five months ago, we have complete confidence now.”

The new test plan is also more focused than the original one, tying each flight test to the delivery of a specific capability rather than just flying for flying's sake, Falk told USNI News. The helicopter has already demonstrated that it meets or exceeds all requirements for speed, range, altitude, lift capacity and more. Sikorsky and the Navy/Marine Corps team have also conducted hot weather and brownout condition testing in Arizona, and they have certified the helicopter can be transported via C-5 and C-17 cargo planes.

A key upcoming test will be sea trials, where the CH-53K will have to prove it can fly on and off a flight deck and that Marines can maintain it at sea.

Falk said the Navy is looking at a window of late February or early March through May of 2020 for sea trials, and that the tests will take place aboard a yet-to-be-decided amphibious assault ship.

Initial operational test and evaluation is set to begin in early 2021, which would allow the Marine Corps to declare initial operational capability in time for the first deployment in 2023 or 2024.

Though work still remains to be done, Paul Fortunato, director of Marine Corps business development at Sikorsky, and John Rucci, the company's senior experimental test pilot for the CH-53K, said the new helicopter has already proven it is easier to operate and maintain than its predecessor and that its warfighting capability surpasses the requirements for the aircraft.

Rucci said pilots have total trust in the fly-by-wire cockpit, which essentially lands the helicopter on its own – meaning the pilots can focus on the mission at hand or evading a threat, or can safely land in a sandstorm or other degraded conditions.

And Fortunado said the helo was built with easy maintenance in mind: fewer tools are required, the all-electronic maintenance documents include graphics that maintainers can zoom in on and rotate to help them maintain or repair parts, the logistics footprint is smaller and easier for deployments aboard amphibious ships. The design even includes putting electronic components in “backwards,” meaning the connections are facing outwards and easily accessible when maintainers take off a panel, instead of the wiring being in the back like usual and requiring a Marine to use a mirror to see what is going on behind the component.

At Marine Corps Air Station New River in North Carolina, Falk said, Marines are using one of the system demonstration test article (SDTA) helicopters to work out any remaining issues in the maintenance manuals and to start learning more about how to fix and sustain the new helo.

“There's Marines crawling around that aircraft, taking it apart, putting it back together again, running the maintenance procedures, and basically using what we developed in order for them to be able to maintain the aircraft,” Falk said.
“So the opportunity for us before we start delivering production aircraft, we can learn from that, we can feed all that back, we can improve our maintenance procedures and basically when the aircraft is deployed deliver a much higher-quality, more efficient set of maintenance instructions. Plus, you've got Marines that have already used it, done it, learned.”

https://news.usni.org/2019/05/17/navy-awards-sikorsky-1-13b-for-next-12-ch-53k-heavy-lift-helicopters

Sur le même sujet

  • New COVID-19 bill extends contractor reimbursement, but no new funding

    17 décembre 2020 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

    New COVID-19 bill extends contractor reimbursement, but no new funding

    By: Joe Gould WASHINGTON ― A bipartisan group of lawmakers has unveiled a $748 billion coronavirus relief proposal that includes an extension of a prized reimbursement program for federal contractors, but without the billions of dollars previously sought by defense firms. Defense officials have warned they will need to tap modernization and readiness funds if Congress does not appropriate at least $10 billion for defense contractors' coronavirus-related expenses, as authorized by Section 3610 of the Coronavirus Aid, Relief, and Economic Security Act. However, the new proposal doesn't appropriate funding for the Section 3610 reimbursements. Negotiations on a final relief deal are ongoing, but the package includes a Section 3610 extension through April 30, 2021. The provision applies to all federal agencies, but it has been of particular interest to the Pentagon and defense industry. Added funding could come in the $1.4 trillion omnibus spending package for fiscal 2021, which is expected this week, or it could come with the next Congress and the incoming Biden administration in 2021. The defense industry has of late pushed for the extension of Section 3610 first, over added appropriations. “You have people who can't feed their families, you have people who are going to get evicted, you have people whose unemployment insurance is going to run out. They need Congress to pass this legislation,” Arnold Punaro, National Defense Industrial Association chairman, said of the new bipartisan relief package. “We prefer the defense industry have 3610, and we believe we'll have an opportunity with the new administration to make the case to them that it's still an important provision,” Punaro said, adding that the extension gives the incoming administration time to work on a “much more comprehensive approach.” Fifteen defense companies implored Congress on Friday to extend the program. In a letter to congressional leaders, they argued the extension is needed to maintain national security, but also “thousands of critical employees who would be difficult to replace within the industrial base.” “As COVID-19 rates hit record levels that were unanticipated not only when the CARES Act was enacted but just weeks ago, agencies are shifting work plans, reducing hours and taking other steps to ensure the health and safety of the workforce,” the letter stated. The reimbursement window was extended until Dec. 18 under the continuing resolution Congress passed on Friday. Originally the support was to stop at the end of fiscal 2020 in September. NDIA was among eight trade organizations that signed a Nov. 20 letter to Congress urging an extension of Section 3610. There have been a spate of similar letters from lawmakers to congressional leaders in recent weeks. “The current authority has saved thousands of NASA and defense contractors from being furloughed,” Florida Republican Rep. Bill Posey said in a letter with nine other lawmakers. “If the authority is not extended, many contractors — through no fault of their own — will face dire economic and financial consequences if they are restricted again from conducting their regular work on a NASA center or defense program and may be limited or unable due to the nature of their work to do so through a telework alternative.” Senate Intelligence Committee acting Chairman, Marco Rubio, R-Fla., and Vice Chairman Mark Warner, D-Va., pressed congressional leaders earlier this month to extend Section 3610. “Section 3610 has proven to be an important means of providing necessary relief during the pandemic to critical Intelligence Community industry partners ― and particularly to small businesses that provide highly specialized capabilities ― to retain key national security capabilities,” they said in a joint letter. https://www.defensenews.com/congress/2020/12/15/contractor-reimbursement-extension-in-new-covid-19-bill-but-no-new-funding/

  • US approves $7.5 billion in foreign weapons sales in one day

    7 juillet 2020 | International, Terrestre

    US approves $7.5 billion in foreign weapons sales in one day

    By: Aaron Mehta WASHINGTON — It was a happy Independence Day for American defense companies, with the U.S. State Department announcing Monday it has approved almost $7.5 billion in potential foreign military sales to five different countries. The potential sales, announced on the website of the Defense Security Cooperation Agency, involve UH-60M Black Hawk helicopters for Lithuania, E-2D Hawkeye aircraft for France, MV-22 Osprey aircraft for Indonesia, Stryker infantry vehicles for Argentina and aviation fuel for Israel. DSCA announcements mean that the State Department has decided the potential FMS cases meet its standards, but is not a guarantee the sales will to happen in their announced forms. Once approved by Congress, the foreign customer begins to negotiate on price and quantity, both of which can change during the final negotiations. Israel: The biggest price tag, at $3 billion, is 990 million gallons of petroleum-based fuel for Israel, including JP-8 aviation fuel, diesel fuel and unleaded gasoline. Vendors will be selected “using a competitive bid process through Defense Logistics Agency Energy for supply source,” according to the announcement. Israel operates the American-made F-35I Joint Strike Fighter, among other aviation assets. France: The French request to purchase three E-2D Advanced Hawkeye aircraft comes with an estimated price tag of $2 billion. The aircraft is to replace France's legacy E-2C Hawkeye fleet. In addition to the aircraft, the country wants 10 T-56-427A engines, three AN/APY-9 radar assemblies, four AN/ALQ-217 electronic support measure systems and one Joint Mission Planning System, among other technologies. “The E-2D aircraft will continue and expand French naval aviation capabilities and maintain interoperability with U.S. naval forces,” the DSCA announcement read. “As a current E-2C operator, France will have no difficulty absorbing this equipment and support into its armed forces.” Primary work will be done at Northrop Grumman's Melbourne, Florida, location. There will be industrial offsets required in the future, but those have not been defined at this point. This is the first DSCA notification of an arms sale to France since at least September 2017, as the country prefers to rely on its domestic arms industry. Indonesia: Indonesia was cleared to spend an estimated $2 billion to buy eight MV-22 Block C Osprey aircraft. Also included are 24 AE 1107C Rolls-Royce engines; 20 each of the AN/AAQ-27 forward-Looking infrared radars, AN/AAR-47 missile warning systems and AN/APR-39 radar warning receivers; and 20 each of the M-240-D 7.64mm machine guns and GAU-21 machine guns, among other gear. The potential sale is announced at a time when the U.S. is seeking to beef up both its presence and the capabilities of partner nations in the Pacific in order to blunt Chinese interests in the region. This is the first DSCA notification of an arms sale to Indonesia since at least September 2017. “This proposed sale will support the foreign policy goals and national security objectives of the United States by improving the security of an important regional partner that is a force for political stability, and economic progress in the Asia-Pacific region. It is vital to U.S. national interest to assist Indonesia in developing and maintaining a strong and effective self-defense capability,” the DSCA notification read, adding the sale will “enhance Indonesia's humanitarian and disaster relief capabilities and support amphibious operations.” Primary work will be done by Bell Textron in Amarillo, Texas, and Boeing in Ridley Park, Pennsylvania. Lithuania: The Baltic nation of Lithuania plans to spend $380 million to procure six UH-60M Black Hawk helicopters. The standard U.S. configuration requested includes 14 T700-GE-701D engines, 12 M240H machine guns, night vision goggles, a number of radios and thousands of rounds of ammunition. “The proposed sale of these UH-60 helicopters to Lithuania will significantly increase its capability to provide troop lift, border security, anti-terrorist, medical evacuation, search and rescue, re-supply/external lift, combat support in all weather,” per the DSCA. “These UH-60 helicopters will allow for interoperability with U.S. and NATO forces in rapid response to a variety of missions and quick positioning of troops with minimal helicopter assets. Lithuania intends to use these defense articles and services to modernize and expand its armed forces to provide multi-mission support in its region and combat terrorism threats.” The Black Hawks will replace the nation's Soviet-made Mi-8 fleet. The U.S. is helping fund Lithuania's purchase through the European Recapitalization Incentive Program, or ERIP, a tool developed in 2018 alongside U.S. European Command to speed up the process of getting allied nations off Russian gear. The State Department kicked in $30 million of ERIP funding to help complete that deal. So far, three of the eight countries to receive ERIP funds have used them to purchase Black Hawk helicopters. Work will primarily be done at Sikorsky's Stratford, Connecticut, location and General Electric Aircraft Company in Lynn, Massachusetts. Argentina: The South American nation seeks 27 M1126 Stryker infantry carrier vehicles, with an estimated $100 million price tag. In addition to the vehicles themselves comes a pile of equipment, including 27 M2 Flex .50-caliber machine guns, radios and smoke grenade launchers. In addition, the vehicles come with special de-processing services outside of the continental United States as well as contractor-provided training. “The proposed sale will improve Argentina's capability to meet current and future threats by increasing operational capabilities and force availability,” per DSCA. “Argentina will use the Stryker vehicles to conduct stability operations in support of disaster relief and international peace keeping obligations.” Primary work will occur at the General Dynamics Land Systems facility in Anniston, Alabama. This marks Argentina's second FMS request of the fiscal year, after a December request for $70 million worth of support for its aging P-3C fleet. https://www.defensenews.com/global/the-americas/2020/07/06/us-approves-75-billion-in-foreign-weapon-sales-in-one-day

  • Turkey wants to buy up to 100 South Korean tank engines

    30 mars 2022 | International, Terrestre

    Turkey wants to buy up to 100 South Korean tank engines

    Turkey's top defense procurement official says negotiations with two South Korean companies are focused on the quantity of power packs that would be supplied for the Altay program.

Toutes les nouvelles