How the US Air Force is assembling its northernmost F-35 squadron amid a pandemic

By: Valerie Insinna

WASHINGTON — The COVID-19 pandemic could make it more difficult for the U.S. Air Force's newest F-35 squadron to organize its personnel and jets on schedule.

On April 21, the 356th Fighter Squadron at Eielson Air Force Base, Alaska, became the service's northernmost fighter squadron after receiving its first two F-35s. Pilots began flying those jets for training three days later, and another four F-35s on loan from Hill Air Force Base in Utah flew to Alaska on April 27.

But a couple key challenges could hamper the assemblage of the new squadron, said Col. Benjamin Bishop, commander of the base's 354th Fighter Wing.

“We're actually on timeline,” he told Defense News in an exclusive interview on April 28. “We have the pilots and maintainers already here to support operations throughout the summer. However, as you know, the Department of Defense has put a stop-movement order through [June 30], and that is something we're working through on a case-by-case basis.”

Under the current order, pilots and maintainers who are moving through the training pipeline have been granted a blanket exception to transfer to Eielson. But more experienced pilots, maintainers and support personnel coming from an operational base like Hill Air Force Base will need to receive an exception.

Getting additional F-35s to Eielson could also be an obstacle, as Lockheed Martin assesses whether it must slow down deliveries of the F-35 due to disruptions to its supply chain. In a statement to Defense News, Lockheed spokesman Brett Ashworth could not say whether the company was on track to deliver F-35s to Eielson on schedule.

“Lockheed Martin continues to work with our suppliers daily to determine the impacts of COVID-19 on F-35 production,” he said. “We are analyzing impacts at this time and should have more detail in the coming weeks.”

If the coronavirus pandemic delays the pace of F-35 deliveries to Eielson, the squadron will have to mitigate the shortfall in jets, Bishop said. “Currently, we're at a good pace on the road to readiness for our F-35 program here, and we'll continue to adapt and adjust to bring this mission capability to its full potential in the Indo-Pacific theater,” he noted.

Despite COVID-19 and the potential logistical challenges involved in sending people and F-35s to Eielson, day-to-day training operations have continued as normal, said Col. James Christensen, 356th Fighter Squadron commander. Having six F-35s on base allows maintainers to use the jets for training while also maximizing flight hours for the eight pilots currently in the 356th.

“We still do the mission the way we always have. We have the masks and the wipe procedures and social distancing,” Christensen said. “So [we're] being creative but still being able to get the mission done.”

There are strategic benefits to being the U.S. Air Force's northernmost fighter squadron, starting with access. With support from an aerial refueling tanker, the F-35s at Eielson can reach and target any location in Europe or the Asia-Pacific, Bishop said.

And even the harsh climate of Eielson has its perks. It's a short flight away from the Joint Pacific Alaska Range Complex, the Defense Department's largest instrumented training range, with 77,000 square miles of airspace, according to the 354th Fighter Wing.

“The F-35 is going to be able to fly in that airspace, but they're not going to be alone,” Bishop said. F-35s training in that area will regularly be joined by F-22s based at Joint Base Elmendorf-Richardson in Anchorage, as well as the F-16s in Eielson's 18th Aggressor Squadron that simulate enemy combat jets.

“You're going to see amazing fifth-generation tactics and integration tactics emerge,” he said.

Russia is investing in its Arctic infrastructure, and the U.S. military must make its own improvements to how it operates from and trains in the region, said Gen. Terrence O'Shaughnessy, who leads U.S. Northern Command and the North American Aerospace Defense Command.

“It's great to see some of the additional forces that are going in, whether it's the F-35s going to Eielson, whether it's the work of the Coast Guard to develop icebreakers,” he said during a May 4 event. “These are all relevant things for us to be able to operate in the Arctic. And that is absolutely, to me, key to our ability to defend ourselves.”

As the 356th stands up and becomes combat-ready, it will participate in the next Red Flag-Alaska, a multinational air-to-air combat training exercise slated to be held this August. The squadron is also looking for opportunities to deploy around the Asia-Pacific so that pilots can acclimate themselves to the long geographical distances that characterize the region, Christensen said.

“Everyone is excited just to have F-35s here because of the awesome training we can do, but we're also thinking about at some point we have to project this air power out into the Indo-Pacific theater as a combat force. And transitioning everyone, including the wing and including [Pacific Air Forces] — they all have to adjust the mission of Eielson,” he said.

Unlike other fighter bases, which usually swap out existing aircraft of existing squadrons with new jets, the two F-35 squadrons coming to Eielson aren't replacing anything, and infrastructure needs to be built to accommodate the anticipated growth in both people and aircraft.

When the first members of the 356th Fighter Squadron arrived on base in July 2019, Eielson was home to about 1,750 active-duty personnel, Bishop said. By December 2021, that number is expected to double, with the addition of about 1,500 airmen. In that time, 54 F-35s will be delivered to the base for a total of two squadrons — a notable increase from the 30 F-16s and KC-135s previously at Eielson.

An estimated $500 million will be spent on military construction to support the buildup at Eielson, including new operations buildings, a simulator building, heated hangars and other maintenance facilities, and a new cafeteria. A total of 41 facilities will be either built or refurbished with that funding, with 29 of those projects finished and others still under construction to support a second F-35 squadron, Bishop said.

And everything — from constructing new facilities to maintaining runways — is tougher in the subzero temperatures of the Arctic.

“Early on in this job, I learned that there are two seasons in Alaska,” Bishop said. “There's winter and construction season, with the former a lot longer than the latter. From a beddown perspective, how you put your construction plan together, you have to maneuver around that season.”

“In order to maintain efficiency of fighter operations up here, one of the things we did is we built walled weather shelters for our aircraft, so all of our aircraft are actually housed in weather shelters," he added. "That's not necessarily for the aircraft. That's more for the maintainers because having that insulated and heating facility, now you can do maintenance around the clock.”

Corrected at 5/12/20 at 2:53 p.m. with the correct size of the JPARC, which was recently expanded to 77,000 square miles of airspace.

https://www.defensenews.com/smr/frozen-pathways/2020/05/11/how-the-us-air-force-is-assembling-its-northernmost-f-35-squadron-amid-a-pandemic/

Sur le même sujet

  • Exclusive: PE firms, defense companies vie for Ball Corp's aerospace unit

    7 juillet 2023 | International, Autre défense

    Exclusive: PE firms, defense companies vie for Ball Corp's aerospace unit

    Private equity firms Blackstone Inc and Veritas Capital Fund Management LLC are competing against large defense companies to acquire the aerospace business of Ball Corp , according to people familiar with the matter.

  • Space Force may hire companies to service orbiting satellites

    22 février 2023 | International, Aérospatial, C4ISR

    Space Force may hire companies to service orbiting satellites

    The head of the Space Force's mobility enterprise said this week the service wants to buy commercial on-orbit logistics capabilities.

  • Navy Rushes To Get F-35s on USS JFK; Other Ford Carriers Wait Their Turn

    23 avril 2020 | International, Naval

    Navy Rushes To Get F-35s on USS JFK; Other Ford Carriers Wait Their Turn

    The service's aircraft carrier boss says the COVID economic slowdown hasn't effected building new carriers -- yet. By PAUL MCLEARY WASHINGTON: The Navy's rushed effort to retrofit its newest aircraft carrier to operate the F-35 will create a testbed for the service's other Ford carriers — which have not been built to fly the fifth generation aircraft — as the Navy juggles work on the remaining three big decks. The $11 billion USS John F. Kennedy (CVN 79) was designed and christened without the capability to fly the 5th generation fighter because of cost caps and the aircraft's infamously delayed development. Those schedule slippages forced the Navy to design and build the ships while the messy F-35 was still undergoing development. In the 2020 NDAA Congress indicated it had had it's fill of delays to the carrier and ordered the Navy to get to work refitting the Kennedy before it sets sail in 2024, forcing the Navy to improvise and refit the just-christened ship. Speaking with reporters today, Rear Adm. James Downey, head of the Navy's carrier programs, said those changes are forcing him to hold off on some early work on the forthcoming USS Enterprise (CVN 80), the third Ford-class carrier, and the USS Doris Miller (CVN 81) to ensure the Kennedy retrofits are done correctly before incorporating them on the other ships which have just started their build cycles. Downey said he's working to accelerate the integration of the F-35 on the JFK and prove out the upgrades in operational testing before doing similar work on the next Ford carrier to be built, the USS Enterprise. That way, all of the bugs will be ironed out on the JFK. The original plan to incorporate the F-35 on the four Ford-class ships was to phase the capability in after the ships were declared operational, and then to refit them as they came into port for overhaul. But Congress, frustrated that the nation's newest class of carrier couldn't operate the nation's newest fighter plane, told the Navy to speed things up. The namesake of the class, the $13.2 billion USS Gerald R. Ford, is currently acting as a training asset off the East Coast, where air wings get carrier certified as the ship continues to iron out remaining issues with its weapons elevators. Simply put, the Ford won't fly the F-35 for years to come. Those electromagnetic elevators have been one of the biggest issues plaguing the ship over the past two years, as the Navy installed them without first testing the new technology ashore, resulting in a ship that had no functioning weapons elevators. And what use is a warship without weapons? It's been slow progress to get them up and running, but the Navy recently certified that just the fifth of eleven elevators is now up and running. The working lifts have logged more than 8,000 cycles over the past several months of operational testing as the Ford acts as the Navy's East Coast training platform to certify pilots. The Ford has been operating one month at sea and one pierside for the last several months, and has launched 2,300 aircraft in that time. Downey said the Ford is keeping to its schedule, and that impending supply-chain issues the services are dealing with as the COVID-19 crisis shutters the global economy shouldn't have any near-term impact on the program overall. “We don't have any real significant concerns right now; we know where the suppliers are,” he said. “Prior to this, we had increased some of our procurements for spares and various materials so we had a pretty steady demand signal.” While the Ford class ships wait for the F-35 upgrades, the 36-year old USS Carl Vinson is undergoing a $34 million refit in Bremerton, Wash. so it can begin flying F-35s by 2021, making the veteran ship the first carrier in the Navy to fly the 5th generation aircraft even before the JFK. While both Nimitz and Ford-class aircraft carriers can operate with F-35Cs aboard, significant modifications are required for both classes to fly and sustain the aircraft for extended periods. Also, the ships will need the capability to push and fuse all the data the F-35s can generate, along with building additional classified spaces, new jet blast deflectors and other refits. Room also needs to be made for Osprey tiltrotor aircraft, which will replace the Navy's C-2A Greyhound fleet that are unable to haul the F-35's heavy engines out to the ship. The USS Enterprise is slated to deploy in 2028 and the USS Doris Miller will be ready to sail in 2032. In January, the Navy awarded Huntington Ingalls Industries' Newport News Shipbuilding a $24 billion contract for the two ships, compared to a predicted cost of $28 billion if the sea service had purchased them separately. https://breakingdefense.com/2020/04/navy-rushes-to-get-f-35s-on-uss-jfk-other-ford-carriers-will-wait

Toutes les nouvelles